Endorsed Assignments from ERS Framework

Size: px
Start display at page:

Download "Endorsed Assignments from ERS Framework"

Transcription

1 ERSTF Completion Endorsed Assignments from ERS Framework Ref Number Title ERS Recommendatio n Ongoing Responsibility 1 Synch Inertia at Interconnection Level Measure 2 Initial Frequency Deviation Measure 3 Synch Inertia at BA Level Measure 4 Freq Response at Interconnection Level Measure RS & FWG + MISO IDC SMEs + Rich Hydzik (other members in WI) + Julia Matevosyan (ERCOT) Current Data: EI IDC Data tentatively by June. WI RS to reach out to Peak RC ERCOT No Action HQ Francis Monette in RS data covered NERC IT Pooja Future Data: June Real Time Inertial Model Industry Practice BA 6 Net Demand Ramping Variability Measure RAS 7 Reactive Capability on the System Measure PAS & SAMS It is the output of Measure 3 results RAS Layne will bring it back to RAS for incorporation John will work with PAS to get granular data. John will socialize the Reactive White Paper with his subgroup and collect thoughts on future aspect RAS Meeting April PAS conference call Mar 24, Meeting April 6-7, and SAMS meeting May RELIABILITY ACCOUNTABILITY On going through Event

2 DERTF Work Plan 2/22/ What are Distributed Energy Resources? Brian Evans-Mongeon, Layne Brown, Sylvester Toe, Tony Jankowski, Gary Keenan a. Definitions i. Functional Model - NERC b. Behind the Meter Generation (BTMG) i. Size/scale ii. Net metering arrangements iii. Customer owned c. Distributed Generation (DG) i. Directly connected to utility distribution facilities ii. Interconnected generator resource d. Typical resources? Solar, small hydro, wind, what? ERS Meeting Update Brian designed a strawman for definitions. I would like to offer a cut at the definitions for BTMG and DG. I am suggesting a strong link to existing definitions in order to keep things relatively close to determinants like BES and such. BTMG: A generating unit or multiple generating units at a single location (regardless of ownership), of any nameplate size, on the customer s side of the retail meter that serve all or part of the customer s retail Load with electric energy. All electrical equipment from and including the generation set up to the metering point is considered to be behind-the-meter. DER: Resource(s) with gross individual nameplate rating less than or equal to 20 MVA or gross plant/facility aggregate nameplate rating less than or equal to 75 MVA including the generator terminals through the high-side of the step-up transformer(s) connected at a voltage of under 100 kv including interconnections with a utility s distribution facilities. What about storage? 2. How are Distributed Energy Resources connected? Sylvester Toe a. Low voltage BTMG NEC code and utility requirements b. Distributed Generation NESC and utility requirements 3. How are Distributed Energy Resources modeled? Jens Boemer, Gary Keenan, Barry Mather, Quoc Le, Dariush Shirmohammadi a. Distribution load is netted at source bus on present models b. Is it being modeled discretely anywhere? c. When does it become significant? 4. What are Distributed Energy Resources operating characteristics? Jason MacDowell, Rich Hydzik, Dariush Shirmohammadi a. IEEE 1547 Requirements 1

3 i. Now ii. Future b. Frequency and voltage ride through (pending NERC PRC-024-2) c. Active fault source? d. Can it run independently of utility connection? e. Smart or passive? f. Governor action 5. What effects to Distributed Energy Resources have on the Bulk Electric System (BES)? Tony Jankowski, Gary Keenan, Charlie Smith, Dariush Shirmohammadi a. Planning What is the net load? What is the peak load to serve? b. Operations MSSC how big is it? c. Negative distribution load? Flow up the transformer? Fault source? d. Balancing Authority Load i. DER nets with load from BA perspective ii. Steady or variable? iii. Predictable in BA load forecast? iv. How does it affect operating reserve requirements? e. X 6. Applicable NERC Reliability Standards Jason MacDowell, Gary Keenan a. MOD Steady State Data for Modeling and Simulation of Interconnected Transmission System b. MOD Dynamics Data for Modeling and Simulation of the Interconnected Transmission System c. MOD Documentation of Data Reporting Requirements for Actual and Forecast Demands, Net Energy for Load, and Controllable Demand-Side Management d. MOD Aggregated Actual and Forecast Demands and Net Energy for Load e. MOD Reporting of Interruptible Demands and Direct Control Load Management f. MOD Providing Interruptible Demands and Direct Load Control Management Data to System Operators and Reliability Coordinators g. MOD Documentation of the Accounting Methodology for the Effects of Demand- Side Management in Demand and Energy Forecasts h. MOD-031 is pending i. MOD-032 replaces MOD-010 j. MOD-033 replaces MOD-012 k. PRC-006 UFLS l. PRC-0?? UVLS schemes m. PRC-019 n. PRC (pending) Generator Voltage and Frequency Coordination 7. Recommendations a. Connection requirements b. Modeling 2

4 c. Performance requirements? d. Accounting Load/Gen? e. Modifications to any NERC Standards? 8. Membership 9. X 3

5 Transient Stability Analysis of an all Converter Interfaced Generation (CIG) WECC system Deepak Ramasubramanian Ph.D. Student Vijay Vittal John Undrill Arizona State University

6 Premise and assumptions Voltage source representation of the converter used All conventional generating units (2592 units) replaced by converter model of appropriate MVA rating Active power droop enabled on CIG when present on replaced conventional generating unit. Same value of droop coefficient used P max of converter assumed to be P max of turbine of replaced conventional generating unit 5% reactive power droop enabled on all CIG Terminal voltage control enabled on all CIG 2

7 Voltage source representation of the converter E d = V td0 + i d R f i q X f E q = V tq0 + i q R f + i d X f (1) 3

8 Voltage source representation of the converter R f and X f represent the resistance and reactance of the converter coupling filter and/or generation step up transformer between the converter and point of connection to the grid They have a value of 0.004pu and 0.05pu on a converter MVA base A steady state PWM amplitude modulation ratio (m) of 0.6 has been assumed. V T is the amplitude of the triangular carrier wave for generating the switching pulses 4

9 Control model Reactive power controller Active power controller 5

10 Features of control model Change in electrical frequency (Δω) calculated by rate of change of bus voltage angle Value of Q max adjusted according to change in terminal voltage while value of P max adjusted accordingly to maintain MVA of the converter Hard current trip at I max = 1.7pu Overvoltage trip if terminal voltage rises 0.15pu above the steady state voltage for more than 0.1s All time constants have a value of 0.01s except T frq which has a default software established value of 0.05s 6

11 System studied Simulation run on the WECC 2012 system: Number of buses: Number of conventional generating units: 2592 Number of induction motor loads: 5380 Around 90% of total load is voltage dependent. 7

12 Simulation results Five generating units across the system observed Plant E Five key buses identified across to system to observe the voltage Bus 2 Bus 1 Bus 5 Plant D Plant F The interaction between the northern and southern regions of the system studied Controller gains used: Bus 3 K p = 1.0, K i = 5.0 Generating units Key Buses Plant C Bus 4 Plant B Plant A K ip = 10.0, K iq = 10.0 K ip = 10.0, K iq = 120 (only for Plant A units) Simulations carried out in GE- PSLF 8

13 Generation outage Two of the three units at Plant A in Arizona tripped at t=15s. Loss of 2755 MW of generation 9

14 The frequency is calculated as rate of change of voltage phase angle 10

15 Analysis of results Arizona exports close to 4000 MW of power to California Large electrical separation between northern and southern regions of WECC 2755 MW generation outage causes phase angles to move away from each other in the first 0.5s after disturbance System separation prevented by increased inflow of power, due to droop control, from Northwest area to central northern California 11

16 Voltage at the key buses shows that as phase separation increases, the voltage at around the center of the north-south interface (Bus 3), decreases. 12

17 Total pre-disturbance active power generation is MW Total post-disturbance active power generation is MW 86.5% of the lost generation (due to trip of two Plant A units) is recovered through droop control Remaining 13.5% of the lost generation is recovered through voltage dependent loads 13

18 Third unit at Plant A is electrically closest to the outage Converter response to the outage is quick Converter current is within limits Voltage control loop brings the voltage back to the pre-disturbance value Very little reserve margin available as Plant A units operate close to their maximum active power limit 14

19 Effect of R p on generation outage With the trip of the two Plant A units, the system behavior with active power droop coefficient as 2R p and R p /2 has been observed Individual CIG units would still have different values of droop The droop coefficient in the previous study was considered to be R p 15

20 Active power droop coefficient was 2R p in this scenario. 16

21 Active power droop coefficient was R p /2 in this scenario. 17

22 Change in active power droop coefficient changes the settling time and final steady state value. Large value of droop coefficient corresponds to smaller proportional gain in the active loop and thus results in a longer settling time with greater oscillatory behavior. Simulation Metrics: With droop coefficient R p, a 40 second simulation run took 8.10 minutes with the first 20 seconds of simulation taking 3.52 minutes. Simulation time step: s Computer specifications: i7 processor, 16.0 gb of RAM. 18

23 DC voltage dip and subsequent recovery Assumption of a battery as a constant source of power for all units is not realistic Disturbance in the network would cause dc capacitor voltage to vary Magnitude of ac voltage produced by converter generally falls in proportion to its dc voltage Two units of Plant A tripped followed by a 10% reduction in dc voltage 0.02s later dc voltage gradually restored over the next 10s dc voltage reduced only in Arizona and Southern California 19

24 Drop in dc voltage does not increase the phase separation between the two areas. 20

25 The transient decrease in bus voltage is however greater when compared to the transient decrease with constant dc voltage 21

26 Analysis of results The dc voltage was reduced only in the southern region of the system Reduction in terminal voltage along with loss of generation, increases power flow along northsouth interfaced Increased power flow causes the voltage at the center to decrease With predominant voltage dependent load, continuous change in dc voltage (over a period of 10s after disturbance) causes load to continuously change and thus more pronounced oscillatory behavior 22

27 Line fault followed by outage Three phase fault applied at midpoint of a line between Arizona and Southern California areas Fault cleared and line tripped in 0.05s Initial flow of power on the line: MW and MVAR from the Arizona side Active power generation in both areas and behavior of one unit of Plant A observed 23

28 Arizona active power generation Southern California active power generation 24

29 Terminal voltage of one unit of Plant A Current of one unit of Plant A 25

30 Line closure Closure of a transmission line should not cause excessive current and voltage transients Power flow solved with major line open resulting in angle difference of between the buses to which the line was connected The line was closed during simulation 26

31 Current of a CIG unit located near the line Current of a CIG unit located one bus away 27

32 Conclusion An all CIG WECC system, if required, is viable The system operates in a stable manner for various contingencies Long proven principle of droop relationships works Important to consider the source behind the dc bus and incorporate its model into positive sequence simulations A coordinated well designed wide area control structure may also be required 28

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission

More information

Fault Ride Through Technical Assessment Report Template

Fault Ride Through Technical Assessment Report Template Fault Ride Through Technical Assessment Report Template Notes: 1. This template is intended to provide guidelines into the minimum content and scope of the technical studies required to demonstrate compliance

More information

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017 Industry Webinar Reactive Power Planning NERC System Analysis and Modeling Subcommittee (SAMS) March 2017 Webinar Topics Reliability Guideline on Reactive Power Planning Webinar Topics Fundamentals of

More information

Lessons Learned in Model Validation for NERC Compliance

Lessons Learned in Model Validation for NERC Compliance Lessons Learned in Model Validation for NERC Compliance usa.siemens.com/digitalgrid NERC Modeling, Data, and Analysis MOD 025 2: Generator Real and Reactive Power Capability Demonstration MOD 026 1: Verification

More information

Forward Looking Frequency Trends Technical Brief ERS Framework 1 Measures 1, 2, and 4: Forward Looking Frequency Analysis

Forward Looking Frequency Trends Technical Brief ERS Framework 1 Measures 1, 2, and 4: Forward Looking Frequency Analysis Forward Looking Frequency Trends Technical Brief ERS Framework 1 Measures 1, 2, and 4: Forward Looking Frequency Analysis The NERC Planning Committee and Operating Committee jointly created the Essential

More information

Harmonizing the Changing Resource Mix Keeping the Grid Together

Harmonizing the Changing Resource Mix Keeping the Grid Together Harmonizing the Changing Resource Mix Keeping the Grid Together Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 30, 2017 NERC-IEEE Memorandum of Understanding

More information

Real Time Stability Analysis at Peak Reliability. Slaven Kincic, Hongming Zhang JSIS May 2017, SLC

Real Time Stability Analysis at Peak Reliability. Slaven Kincic, Hongming Zhang JSIS May 2017, SLC Real Time Stability Analysis at Peak Reliability Slaven Kincic, Hongming Zhang JSIS May 2017, SLC Overview: Overview of Peak s DSA Application; o Set up o User Cases Transient Stability Criteria; TSAT

More information

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity Event Analysis Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity July 2011 Page 1 of 10 Table of Contents Executive Summary... 3 I. Event

More information

Integration of Wind Generation into Weak Grids

Integration of Wind Generation into Weak Grids Integration of Wind Generation into Weak Grids Jason MacDowell GE Energy Consulting NERC ERSTF Atlanta, GA December 10-11, 2014 Outline Conventional and Power Electronic (PE) Sources Stability limitations

More information

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources Connection, Modeling and Reliability Considerations November 2016 NERC Report Title Report Date I Table of Contents Preface... iii Executive Summary... iv Introduction... v

More information

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/ ITC Holdings Planning Criteria Below 100 kv * Category: Planning Type: Policy Eff. Date/Rev. # 12/09/2015 000 Contents 1. Goal... 2 2. Steady State Voltage & Thermal Loading Criteria... 2 2.1. System Loading...

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020 TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES Document 9020 Puget Sound Energy, Inc. PSE-TC-160.50 December 19, 2016 TABLE OF CONTENTS

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

Keeping it up to Speed Off-Nominal Frequency Operations. CETAC 2018 San Ramon

Keeping it up to Speed Off-Nominal Frequency Operations. CETAC 2018 San Ramon Keeping it up to Speed Off-Nominal Frequency Operations CETAC 2018 San Ramon 1 Welcome CETAC 2018 San Ramon Valley Conference Center General Class Information: Safety/Fire evacuation In event of emergency,

More information

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-2 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units

More information

Response of Grid Interconnected Solar PV inverters to Transmission System Faults

Response of Grid Interconnected Solar PV inverters to Transmission System Faults Response of Grid Interconnected Solar PV inverters to Transmission System Faults David Piper, P.E. Operations Planning & Analysis SCE Grid Control Center July 18, 2017 1 OVERVIEW 1. Overview of the event

More information

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION Document 9022 Puget Sound Energy, Inc. PSE-TC-160.70 December

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

Southern Company Interconnection Requirements for Inverter-Based Generation

Southern Company Interconnection Requirements for Inverter-Based Generation Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection

More information

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting Document C-29 Procedures for System Modeling: January 5 th, 2016 TFSS Revisions Clean Open Process Posting Prepared by the SS-37 Working Group on Base Case Development for the Task Force on System Studies.

More information

Loss of Solar Resources during Transmission Disturbances due to Inverter Settings II

Loss of Solar Resources during Transmission Disturbances due to Inverter Settings II Loss of Solar Resources during Transmission Disturbances due to Inverter Settings II Informational Webinar on Level 2 NERC Alert Ryan Quint, Senior Manager, Advanced Analytics and Modeling Rich Bauer,

More information

Transmission Interconnection Requirements for Inverter-Based Generation

Transmission Interconnection Requirements for Inverter-Based Generation Transmission Requirements for Inverter-Based Generation June 25, 2018 Page 1 Overview: Every generator interconnecting to the transmission system must adhere to all applicable Federal and State jurisdictional

More information

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Unit Auxiliary Transformer (UAT) Relay Loadability Report Background and Objective Reliability Standard, PRC 025 1 Generator Relay Loadability (standard), developed under NERC Project 2010 13.2 Phase 2 of Relay Loadability: Generation, was adopted by the NERC

More information

Final ballot January BOT adoption February 2015

Final ballot January BOT adoption February 2015 Standard PRC-024-21(X) Generator Frequency and Voltage Protective Relay Settings Standard Development Timeline This section is maintained by the drafting team during the development of the standard and

More information

1

1 Guidelines and Technical Basis Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive

More information

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017 Grid codes and wind farm interconnections CNY Engineering Expo Syracuse, NY November 13, 2017 Purposes of grid codes Grid codes are designed to ensure stable operating conditions and to coordinate the

More information

Standard MOD Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions

Standard MOD Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions Standard MOD-026-1 Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions A. Introduction 1. Title: Verification of Models and Data for Generator Excitation

More information

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Overview Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Abstract Introduction to HVDC Background on Highgate Operation and Control schemes of Highgate 22 Why

More information

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements Robert Nelson Senior Expert Engineering Manager and Manager of Codes, Standards, and Regulations Siemens Wind Turbines -

More information

Target Mchunu and Themba Khoza Eskom Transmission Division, System Operator Grid Code Management

Target Mchunu and Themba Khoza Eskom Transmission Division, System Operator Grid Code Management GRID CONNECTION CODE FOR RENEWABLE POWER PLANTS (RPPs) CONNECTED TO THE ELECTRICITY TRANSMISSION SYSTEM (TS) OR THE DISTRIBUTION SYSTEM (DS) IN SOUTH AFRICA Target Mchunu and Themba Khoza Eskom Transmission

More information

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control Spring 2014 Instructor: Kai Sun 1 References Saadat s Chapters 12.6 ~12.7 Kundur s Sections

More information

VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM

VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM 1 VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM Thierry Van Cutsem Department of Electrical and Computer Engineering University of Liège, Belgium Modified version of a presentation at the IEEE PES General

More information

1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report

1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report 1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report Rich Bauer Associate Director Reliability Risk Management / Event Analysis Mid C Seminar July 19, 2017 Western Interconnection

More information

Facilitating Bulk Wind Power Integration Using LCC HVDC

Facilitating Bulk Wind Power Integration Using LCC HVDC 21, rue d Artois, F-758 PARIS CIGRE US National Committee http : //www.cigre.org 213 Grid of the Future Symposium Facilitating Bulk Wind Power Integration Using LCC HVDC A. HERNANDEZ * R.MAJUMDER W. GALLI

More information

Wind Power Facility Technical Requirements CHANGE HISTORY

Wind Power Facility Technical Requirements CHANGE HISTORY CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical

More information

Operationalizing Phasor Technology. Model Validation. Webinar. Ken Martin. March 4, Presented by. Page 0

Operationalizing Phasor Technology. Model Validation. Webinar. Ken Martin. March 4, Presented by. Page 0 Operationalizing Phasor Technology Model Validation Webinar March 4, 2014 Presented by Ken Martin Page 0 Model Use and Validation for Operations and Planning Compare System Performance with Model Prediction

More information

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-1 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0A DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

Analysis of Effect on Transient Stability of Interconnected Power System by Introduction of HVDC Link.

Analysis of Effect on Transient Stability of Interconnected Power System by Introduction of HVDC Link. Analysis of Effect on Transient Stability of Interconnected Power System by Introduction of HVDC Link. Mr.S.B.Dandawate*, Mrs.S.L.Shaikh** *,**(Department of Electrical Engineering, Walchand College of

More information

Stability Enhancement for Transmission Lines using Static Synchronous Series Compensator

Stability Enhancement for Transmission Lines using Static Synchronous Series Compensator Stability Enhancement for Transmission Lines using Static Synchronous Series Compensator Ishwar Lal Yadav Department of Electrical Engineering Rungta College of Engineering and Technology Bhilai, India

More information

generation greater than 75 MVA (gross aggregate nameplate rating) Generation in the ERCOT Interconnection with the following characteristics:

generation greater than 75 MVA (gross aggregate nameplate rating) Generation in the ERCOT Interconnection with the following characteristics: A. Introduction 1. Title: Verification of Models and Data for Turbine/Governor and Load Control or Active Power/Frequency Control Functions 2. Number: MOD-027-1 3. Purpose: To verify that the turbine/governor

More information

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number:  Address: NORTH CAROLINA INTERCONNECTION REQUEST Utility: Designated Contact Person: Address: Telephone Number: Fax: E-Mail Address: An is considered complete when it provides all applicable and correct information

More information

IEEE Std Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards

IEEE Std Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards IEEE Std 1547-2018 Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards Clayton Stice, ERCOT Jens C. Boemer, EPRI (on behalf of SCC21) NERC SPIDER

More information

ESB National Grid Transmission Planning Criteria

ESB National Grid Transmission Planning Criteria ESB National Grid Transmission Planning Criteria 1 General Principles 1.1 Objective The specific function of transmission planning is to ensure the co-ordinated development of a reliable, efficient, and

More information

Implementation of Revised IEEE Standard 1547

Implementation of Revised IEEE Standard 1547 MAY 31, 2017 HOLYOKE, MASSACHUSETTS Implementation of Revised IEEE Standard 1547 Presentation to ISO-TO Operations Committee David Forrest Key Points As New England adds significant amounts of Distributed

More information

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications 1 1 1 1 1 1 1 1 0 1 0 1 0 1 Reliability Guideline: Generating Unit Operations During Complete Loss of Communications Preamble: It is in the public interest for the North American Electric Reliability Corporation

More information

Level 6 Graduate Diploma in Engineering Electrical Energy Systems

Level 6 Graduate Diploma in Engineering Electrical Energy Systems 9210-114 Level 6 Graduate Diploma in Engineering Electrical Energy Systems Sample Paper You should have the following for this examination one answer book non-programmable calculator pen, pencil, ruler,

More information

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4 MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS July 2016 Version 4 This page intentionally blank LEGISLATIVE AUTHORITY Section 15.0.3(1) of The Manitoba Hydro Act (C.C.S.M. c. H190) authorizes

More information

Short-Circuit Modeling and System Strength

Short-Circuit Modeling and System Strength Short-Circuit Modeling and System Strength White Paper February 2018 NERC Report Title Report Date I Table of Contents Preface... iii Introduction... iv Short-circuit ratio... iv Modeling Accuracy... v

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0 DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

BPS-Connected Inverter-Based Resource Performance

BPS-Connected Inverter-Based Resource Performance 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Reliability Guideline BPS-Connected Inverter-Based Resource Performance May 2018 20 21 22 23 24 25 26 27 28 29 NERC Report Title Report Date I 30 31 32 33

More information

RELIABILITY: Our Advantages, Challenges, and Opportunities

RELIABILITY: Our Advantages, Challenges, and Opportunities RELIABILITY: Our Advantages, Challenges, and Opportunities NERC Reliability Leadership Summit March 21, 2017 Edmund O. Schweitzer, III Ph.D. President, Schweitzer Engineering Laboratories, Inc. Copyright

More information

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines Central Hudson Gas & Electric Corporation Transmission Planning Guidelines Version 4.0 March 16, 2016 Version 3.0 March 16, 2009 Version 2.0 August 01, 1988 Version 1.0 June 26, 1967 Table of Contents

More information

Doãn Văn Đông, College of technology _ Danang University. 2. Local Techniques a. Passive Techniques

Doãn Văn Đông, College of technology _ Danang University. 2. Local Techniques a. Passive Techniques Detection of Distributed Generation Islanding Using Negative Sequence Component of Voltage Doãn Văn Đông, College of technology _ Danang University Abstract Distributed generation in simple term can be

More information

Bulk Electric System Definition Reference Document

Bulk Electric System Definition Reference Document Bulk Electric System Definition Reference Document January, 2014 This draft reference document is posted for stakeholder comments prior to being finalized to support implementation of the Phase 2 Bulk

More information

NVESTIGATIONS OF RECENT BLACK-

NVESTIGATIONS OF RECENT BLACK- DIGITAL VISION outs indicate that the root cause of almost all major power system disturbances is voltage collapse rather than the underfrequency conditions prevalent in the blackouts of the 1960s and

More information

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications 1 1 1 1 1 1 1 1 0 1 0 1 0 1 Reliability Guideline: Generating Unit Operations During Complete Loss of Communications Preamble It is in the public interest for the North American Electric Reliability Corporation

More information

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team.

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team. December 7 th, 2010 NPCC Full Member Committee; Please find attached a draft revised NPCC Regional Reliability Directory #12 Underfrequency Load Shedding Program Requirements and a draft revised NPCC UFLS

More information

DER_A Benchmark Update

DER_A Benchmark Update DER_A Benchmark Update Deepak Ramasubramanian, EPRI Anish Gaikwad, EPRI Pouyan Pourbeik, PEACE NERC LMTF October 31 st 2017 Austin, TX DISCLAIMER The DER_A model is still a beta model under test and development

More information

Standard MOD Verification of Models and Data for Generator Excitation Control Sys tem or Plant Volt/Var Control Functions

Standard MOD Verification of Models and Data for Generator Excitation Control Sys tem or Plant Volt/Var Control Functions Standard MOD-026-1 Verification of Models and Data for Generator Excitation Control Sys tem or Plant Volt/Var Control Functions Standard Development Roadmap This section is maintained by the drafting team

More information

EH2741 Communication and Control in Electric Power Systems Lecture 2

EH2741 Communication and Control in Electric Power Systems Lecture 2 KTH ROYAL INSTITUTE OF TECHNOLOGY EH2741 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsno@kth.se Course map Outline Transmission Grids vs Distribution grids Primary Equipment

More information

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 PRC-025-1 Generator Relay Loadability A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 Purpose: To set load-responsive protective relays associated with generation Facilities

More information

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1 NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1 Charles J. Mozina, Consultant Beckwith Electric Co., Inc. www.beckwithelectric.com I. Introduction During the 2003 blackout,

More information

Modeling of Distributed Generation under Next Generation Interconnection Requirements. Anna Edwards. A thesis. Submitted in partial fulfillment of the

Modeling of Distributed Generation under Next Generation Interconnection Requirements. Anna Edwards. A thesis. Submitted in partial fulfillment of the Modeling of Distributed Generation under Next Generation Interconnection Requirements Anna Edwards A thesis Submitted in partial fulfillment of the requirements for the degree of: Master of Science in

More information

PRC Disturbance Monitoring and Reporting Requirements

PRC Disturbance Monitoring and Reporting Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2 MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS April 2009 Version 2 LEGISLATIVE AUTHORITY Section 15(5) of The Manitoba Hydro Act authorizes Manitoba Hydro to set, coordinate and enforce

More information

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition NERC System Protection and Control Subcommittee March 2016 NERC Report Title Report Date I Table

More information

AMEREN s (On Behalf of Its Transmission Owning Affiliates, Including Ameren Missouri, Ameren Illinois, and Ameren Transmission Company of Illinois)

AMEREN s (On Behalf of Its Transmission Owning Affiliates, Including Ameren Missouri, Ameren Illinois, and Ameren Transmission Company of Illinois) AMEREN s (On Behalf of Its Transmission Owning Affiliates, Including Missouri, Illinois, and Transmission Company of Illinois) TRANSMISSION PLANNING CRITERIA AND GUIDELINES March 28, 2003 Revised April

More information

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY WN U-60 Attachment C to Schedule 152, Page 1 SCHEDULE 152 APPLICATION FOR INTERCONNECTING A GENERATING FACILITY TIER 2 OR TIER 3 This Application is considered complete when it provides all applicable

More information

CAISO Restricted - Do Not Distribute Outside of RC Project LOI and NDA Entities Page 1 of 24

CAISO Restricted - Do Not Distribute Outside of RC Project LOI and NDA Entities Page 1 of 24 RC0120A - RC IRO-010 Data Specification NOTE: Changes from Peak's Attachment A are highlighted in red in columns C through G Section Category Number Responsible Pa Data Item Data Transfer Method 1.1 Transmission

More information

Bulk Electric System Definition Reference Document

Bulk Electric System Definition Reference Document Bulk Electric System Definition Reference Document JanuaryVersion 2 April 2014 This technical reference was created by the Definition of Bulk Electric System drafting team to assist entities in applying

More information

Inverter-Based Resource Disturbance Analysis

Inverter-Based Resource Disturbance Analysis Inverter-Based Resource Disturbance Analysis Key Findings and Recommendations Informational Webinar February 15, 2018 August 16, 2016 Blue Cut Fire Disturbance Key Findings and Recommendations 2 Western

More information

Lessons Learned in Model Validation for NERC Compliance

Lessons Learned in Model Validation for NERC Compliance Lessons Learned in Model Validation for NERC Compliance usa.siemens.com/digitalgrid NERC Modeling, Data, and Analysis MOD 025 2: Generator Real and Reactive Power Capability Demonstration MOD 026 1: Verification

More information

Power Plant and Transmission System Protection Coordination

Power Plant and Transmission System Protection Coordination Technical Reference Document Power Plant and Transmission System Protection Coordination NERC System Protection and Control Subcommittee Revision 1 July 2010 Table of Contents 1. Introduction... 1 1.1.

More information

Interconnection-Wide Oscillation Analysis: Baselining Oscillation Modes in the North American Power System Objective Purpose

Interconnection-Wide Oscillation Analysis: Baselining Oscillation Modes in the North American Power System Objective Purpose Interconnection-Wide Oscillation Analysis: Baselining Oscillation Modes in the North American Power System NERC Synchronized Measurement Subcommittee (SMS) Scope Document Objective The objective of the

More information

EE 742 Power System Components. Y. Baghzouz ECE Department UNLV

EE 742 Power System Components. Y. Baghzouz ECE Department UNLV EE 742 Power System Components Y. Baghzouz ECE Department UNLV Desire to have a system with high reliability and power quality High reliability ensured by High quality of components High level of system

More information

System Protection and Control Subcommittee

System Protection and Control Subcommittee Power Plant and Transmission System Protection Coordination Volts Per Hertz (24), Undervoltage (27), Overvoltage (59), and Under/Overfrequency (81) Protection System Protection and Control Subcommittee

More information

Possible Future Modifications to IEEE 1547

Possible Future Modifications to IEEE 1547 California Rule 21 SWIG Possible Future Modifications to IEEE 1547 Michael Sheehan, P.E IREC mikes@irecusa.com PV Significant Trends Installed prices for distributed PV installations fell by at least 11

More information

Robert W. Cummings - NERC Director of System Analysis and Reliability Initiatives William Herbsleb - Chairman of Frequency Response Standard Drafting

Robert W. Cummings - NERC Director of System Analysis and Reliability Initiatives William Herbsleb - Chairman of Frequency Response Standard Drafting Generator Governor and Information Settings Webinar Robert W. Cummings - NERC Director of System Analysis and Reliability Initiatives William Herbsleb - Chairman of Frequency Response Standard Drafting

More information

Power Conditioning Equipment for Improvement of Power Quality in Distribution Systems M. Weinhold R. Zurowski T. Mangold L. Voss

Power Conditioning Equipment for Improvement of Power Quality in Distribution Systems M. Weinhold R. Zurowski T. Mangold L. Voss Power Conditioning Equipment for Improvement of Power Quality in Distribution Systems M. Weinhold R. Zurowski T. Mangold L. Voss Siemens AG, EV NP3 P.O. Box 3220 91050 Erlangen, Germany e-mail: Michael.Weinhold@erls04.siemens.de

More information

TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line

TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line Vince Leung March 27, 2017 Reviewed by Johnny Nguyen Table of Contents Background 2 Objective 3 Base Case Assumptions

More information

( ) usable, minor formatting/editing required ( ) modification needed ( ) superseded by ( ) other ( ) obsolete/archived)

( ) usable, minor formatting/editing required ( ) modification needed ( ) superseded by ( ) other ( ) obsolete/archived) Document name Category Model Validation Report for May 16, 2014 RAS Event ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy ( ) Guideline (X) Report or other ( ) Charter Document date

More information

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell Power Plant and Transmission System Protection Coordination Phase Distance (21) and Voltage-Controlled or Voltage-Restrained Overcurrent Protection (51V) NERC Protection Coordination Webinar Series June

More information

CHAPTER 4 POWER QUALITY AND VAR COMPENSATION IN DISTRIBUTION SYSTEMS

CHAPTER 4 POWER QUALITY AND VAR COMPENSATION IN DISTRIBUTION SYSTEMS 84 CHAPTER 4 POWER QUALITY AND VAR COMPENSATION IN DISTRIBUTION SYSTEMS 4.1 INTRODUCTION Now a days, the growth of digital economy implies a widespread use of electronic equipment not only in the industrial

More information

Transmission System Phase Backup Protection

Transmission System Phase Backup Protection Reliability Guideline Transmission System Phase Backup Protection NERC System Protection and Control Subcommittee Draft for Planning Committee Approval June 2011 Table of Contents 1. Introduction and Need

More information

Harnessing of wind power in the present era system

Harnessing of wind power in the present era system International Journal of Scientific & Engineering Research Volume 3, Issue 1, January-2012 1 Harnessing of wind power in the present era system Raghunadha Sastry R, Deepthy N Abstract This paper deals

More information

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 Purpose: To set load-responsive protective relays associated with generation Facilities at a level to prevent unnecessary tripping

More information

Using Synchrophasors for Frequency Response Analysis in the Western Interconnection. Bonneville Power Administration -- WECC JSIS Chair

Using Synchrophasors for Frequency Response Analysis in the Western Interconnection. Bonneville Power Administration -- WECC JSIS Chair 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2014 Grid of the Future Symposium Using Synchrophasors for Frequency Response Analysis in the Western Interconnection

More information

Modeling and Evaluation of Geomagnetic Storms in the Electric Power System

Modeling and Evaluation of Geomagnetic Storms in the Electric Power System 21, rue d Artois, F-75008 PARIS C4-306 CIGRE 2014 http : //www.cigre.org Modeling and Evaluation of Geomagnetic Storms in the Electric Power System K. PATIL Siemens Power Technologies International, Siemens

More information

each time the Frequency is above 51Hz. Continuous operation is required

each time the Frequency is above 51Hz. Continuous operation is required GC0101 EXTRACT OF EUROPEAN CONNECTION CONDITIONS LEGAL TEXT DATED 08/01/2018. ECC.6 ECC.6.1 ECC.6.1.1 ECC.6.1.2 ECC.6.1.2.1 ECC.6.1.2.1.1 ECC.6.1.2.1.2 ECC.6.1.2.1.3 TECHNICAL, DESIGN AND OPERATIONAL CRITERIA

More information

MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above

MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above March 13, 2018 Issued by: Dehn Stevens, Director System Planning and Services 1.0 SCOPE This document defines the criteria

More information

HISTORY: How we got to where we are. March 2015 Roy Boyer 1

HISTORY: How we got to where we are. March 2015 Roy Boyer 1 HISTORY: How we got to where we are March 2015 Roy Boyer 1 Traditional Stability Analysis: 1. Maintain synchronism of synchronous machines 2. Simplifying assumptions: 1. Balanced positive sequence system

More information

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV) Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV) IRR-DCC-MV 1. Introduction 1 IRR-DCC-MV 2. Scope 1 IRR-DCC-MV 2.1. General 1 IRR-DCC-MV 2.2. Affected

More information

Stability Issues of Smart Grid Transmission Line Switching

Stability Issues of Smart Grid Transmission Line Switching Preprints of the 19th World Congress The International Federation of Automatic Control Stability Issues of Smart Grid Transmission Line Switching Garng. M. Huang * W. Wang* Jun An** *Texas A&M University,

More information

Fault Induced Delayed Voltage Recovery (FIDVR) Advisory

Fault Induced Delayed Voltage Recovery (FIDVR) Advisory Fault Induced Delayed Voltage Recovery (FIDVR) Advisory NERC Synchronized Measurement Subcommittee (SMS) NASPI Engineering Analysis Task Team (EATT) July 2015 Why the Advisory? The goal of this advisory

More information

Voltage and Frequency Dependency

Voltage and Frequency Dependency Average hourly generation (GW) System Operability Framework Voltage and Frequency Dependency The demand and generation we see on the electricity network has been changing in recent years and is set to

More information

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS AND MEDIUM-SIZE FACILITIES (5,000-25,000KW) CONNECTED

More information

Power Plant and Transmission System Protection Coordination

Power Plant and Transmission System Protection Coordination Agenda Item 5.h Attachment 1 A Technical Reference Document Power Plant and Transmission System Protection Coordination Draft 6.9 November 19, 2009 NERC System Protection and Control Subcommittee November

More information