ABSTRACT INTRODUCTION DIAGNOSTIC TESTS. MAIN CHARACTERISTICS AND CONDITIONS OF 9 kv NETWORK
|
|
- Simon Reed
- 6 years ago
- Views:
Transcription
1 LABORATORY AND ON SITE TESTS FOR THE DETERMINATION OF THE AGEING CONDITION OF MV PILC CABLES Nikola Kuljaca; Sergio Meregalli; Giuseppe Rizzi CESI RICERCA Italy ABSTRACT In the major cities in Europe the electrical distribution network was firstly established at the beginning of the past century and it is not unusual to find electrical components having a service life of sixty seventy years, still having a failure rate non dramatically higher than younger components. As a consequence the electrical Utilities are looking for methods/tools able to quantify the real ageing state of equipment and to propose a priority list for their replacement. INTRODUCTION AEM Elettricità supplies electricity to Milan city and the nearby town of Rozzano. AEM Elettricità is part of A2A group SpA. The present dimension of the company was established in 22 when AEM Distribuzione incorporated the remaining supply network and business branch of Enel Distribuzione in Milan. AEM Elettricità manages a MV (Medium Voltage) and LV (Low Voltage) network of 38 km and 576 km, respectively. The number of customers is about 8. with a maximum output power of 154 MW. The medium voltage network is organised in four different voltage levels, namely 23 kv (28 km), 15 kv (8 km), 9 kv (7 km) and 6.4 kv (14 km). The level of 23 kv was chosen for the progressive unification of the MV network replacing the cable of the remaining voltage levels. The 6.4 kv network is the oldest and has been almost completely eliminated while 15 kv network is of marginal consistency. The 9 kv network is also being removed gradually and its replacement will be completed in about years; then it is of particular interest to verify its state of ageing to confirm if the original plan can be maintained or if it is necessary to speed up the replacement to continue managing the network with acceptable failure rate (in line with the targets set by Italian Regulatory Authority for Electricity and Gas). Aim of the research presented in the paper is the determination of the ageing state of 9 kv cable based on onsite and laboratory tests. MAIN CHARACTERISTICS AND CONDITIONS OF 9 kv NETWORK Typically, for 9 kv level, cables with the following main characteristics are used: copper conductors, impregnated paper with a normal/stabilised compound, non-radial electric field, lead sheath and PVC outersheath. It is to be underlined that the insulation is oversized and suitable for Stefano Fratti, Salvatore Pugliese; Cesare Ravetta AEM Elettricità - Italy salvatore.pugliese@a2a.eu voltages up to 15 kv. The average failure rates (expressed as number of failures per km per year) are available for each MV level, and namely: 2.2 for the 23 kv voltage (ex AEM Distribuzione), 9.7 for the 9 kv voltage and 4.6 for the 23 kv voltage managed before 22 by ENEL Distribuzione. Figure 1 shows the failure distribution in 9 kv network in the period of time It is shown that approximately 68% originate on the joints, 25% failures are due to cables and the remaining due to different causes. 9 kv Level: Component Failure Distribution 9 kv JOINT 9 kv CABLE 9 kv OTHER CAUSES Figure 1: Failure distribution for 9 kv network The failure causes of on the cables mainly depend on the corrosion of the lead sheath with consequent deterioration of the insulation. The main causes of joints failure are the unsuitable type of filling compound used and the difficulty to control the electric field in the area where the cable three phases open. As mentioned, joints represent the most critical component of the underground 9 kv network. For setting up an optimised maintenance and replacement plan it is therefore important to understand if also the cable is in a very aged state. Replacement of the entire link is generally advisable in case of very aged cable while a proper maintenance to identify the most critical points of the line ad take suitable actions is advisable if the cable condition is still good or at least adequate to withstand network stresses. DIAGNOSTIC TESTS An experimental diagnostic campaign in field and in laboratory was planned with the aim of verifying the condition of network components, identifying the portions of the oldest network that need priority for replacement and verifying the effectiveness of diagnostic techniques to be used on site to avoid interruptions of service to customers. Field tests were based on measurement and location of Partial Discharge (PD) activity and measurement of loss angle (tg). Laboratory tests were performed on samples of
2 cables removed from service; in addition to the measurements performed on site, tests were carried out using two methods made commercially available in the recent years. These methods are particularly suitable for the diagnostic of paper insulated equipment. The first method is the measurement of Polarisation and Depolarisation Current (PDC) [1]. The system using a model of the tested object evaluates the measurement and provides different diagnostic indicators that can be used for a deep analysis of the insulation and so it allows a more precise assessment of the cable condition. The main test parameters are the voltage to be applied to the test object (in the range 2 kv DC ) and the duration of current measurements (in the range 1s 2s). Current measurement duration shall be optimised: for example setting a measuring time of 2s for both polarisation and depolarisation current will make the test to last more than 11 hours, a duration unsuitable for on site diagnostic of MV cables. The second recently developed method is the Frequency Domain Spectroscopy (FDS) [2], that is the measurement of tg over a wide frequency range (from,1 mhz to 1 khz). The equipment provides a series of sinusoidal voltages at specified frequencies evaluating, at each step, the dielectric response of the test object. The test voltage can be set by the User in the range -14 V (rms values) as well as the frequency range. A sweep over the entire frequency range may take about hours. On site tests About 7 underground lines (for a total length of 6 km) were investigated and the same number will undergo a similar diagnostic campaign in the near future. PD tests were performed using a system supplying a damped oscillating voltage (DOV). The applied voltage was gradually increased from 1 kv up to 2U and PD activity measured at different voltage levels; in case of very high activity the test was stopped at lower voltages. A system delivering a sinusoidal voltage at.1 Hz (VLF) was used for tg measurement. The measurements were performed at three different voltage levels in the range 1U 2U. The results of the tests have shown two cables with very high values of tg and one point (in the cable) generating a very high level of PD, see examples of figures 2 and 3. One joint was immediately fixed, while the other lines identified as very aged have been left in service. After about two years from the diagnostic campaign, two joints and a cable identified as non critical failed. The failure analysis highlighted that water penetration was the cause of the failures. Water penetrated in the cable because of lead sheath corrosion and in the joints because of wrong type of filling compound used that could not guarantee the correct joint sealing. Figure 2: Examples of on site tg measurement Figure 3: Examples of on site PD measurement Laboratory tests The entire 9 kv underground network is based on belted PILC cables having a service age comprised in the range 2-7 years. The design of the cables is expected to be quite similar but basic material (paper and impregnating compound) have changed over a so long time span. Three periods of time were identified as moments of important development of the network: for each period some cable samples (without accessories) were removed from service to be analysed in laboratory. The average length of the samples is about 5 m. Table 1 shows main sample characteristics. The table highlights that the cable removed have a service time of approximately 2-25 years, 45- years and about 7 years respectively. Table 1: main characteristics of the cable samples Sample (n) Installation date/service age (yr) C1 C6 C 1985/ / /21 C3 C4 C7 C8 1962/ / / /48 C2 C5 C9 1938/ / /68 Several measurements were performed on the removed samples at high and low voltages. PD activity (with both DOV and power frequency PF) and tg with PF and VLF were measured at high voltage (up to 1.5U ), PDC and FDS systems were used at low voltage. Some measurements were performed at ambient temperature as well as at higher temperatures to investigate the related influence. At the end of the diagnostic campaign, breakdown test, visual and chemical analysis on cable components were also performed to have a better insight of insulation real ageing state.
3 PD measurements resulted in a very limited activity with both voltage stresses; in few cases PD activity was detected but it was verified by an acoustic sensor that weak points were located in the area where the cable three phases open. Tg measurements were performed in two different configurations: the first stressing one phase at a time being the other two connected to the grounded lead sheath, the second stressing the three phases connected in parallel for a total of 4 measurements per sample. Generally no significant differences were evidenced among the different measurements indicating an homogeneous ageing condition of the samples. For sake of simplicity in presenting the results in the following pictures, only one measurement is reported for each cable sample. Figure 4 shows tg values measured at 1U and at 1.5U with PF; it can be noted that independently from service age the measured values are quite low and comparable to those typical of new cables V and at 1 U with PF and VLF As shown in figure, the values measured at PF are very similar. [ -3 ] Cables C1 and C2: at,1 Hz, Uo and 2Uo Temperature [C] C1 3F Uo C1 3F 2Uo C2 3F Uo C2 3F 2Uo Figure 6: VLF voltage, variation of tg with temperature For VLF stress the agreement is quite good in most cases, the higher differences could be justified by small differences on cable temperature during tests. In fact as shown later, the temperature of the sample is a very important parameter especially in the low frequency region for older cables. 6 [ -3 ] 8 6 (5kV) D (5 - kv) [ -3 ] Hz-FDS Hz-SBr.1Hz-FDS.1Hz-VLF Cable Number 1-V 2-B 3-R 4-R 5-V 6-R 7-M 8-G 9-M -B Cable Phase Figure 4: tg and tg values measured at ambient temperature with PF Measurement performed at higher temperatures did not show any important differences respect those at ambient temperature and in some cases tg values decreased as shown in the example of figure 5. tg d [ -3 ] Cables C1 and C2: at Uo Temperature [C] Limit Figure 5: Variation of tg with temperature at PF Tg measurements at VLF showed values in the range 5 4* -3 at ambient temperature; remarkable differences between recent and older cables were found at higher temperatures as reported in figure 6 for sample 1 (22 years old) and 2 (69 years old). With FDS system tg values were measured at 14 V in a frequency range Hz - 1 khz. Figure 7 reports the comparison of tg values measured at 1R 1B 1V 2R 2B 2V Figure 7: tg measured at 14 V and 1U at PF and VLF Figure 8 shows tg values at three different temperatures. It can be noted that increasing the temperature the curve moves toward the right side without changing its shape according to the theory Cable 3: FDS Curves at different temperatures Figure 8: Variation of FDS curve with temperature Moreover, the figure shows that the minimum value of the curve is comprised in a frequency range from few Hz to about Hz. This feature, constant for all the measured samples, justifies the decrease of tg value at PF when increasing sample temperature as shown in figure 5. Even if the minimum tg values measured for all the samples with FDS system are very similar, the shape of the curves exhibit some differences. In particular, as shown in figure 9, younger sample have flatter curve than older ones. 2C 4C 6C
4 1 C1 and C9: curves 9 RVM: Max Return Voltage C1 C9 Voltage [V] Figure 9: FDS curves for young and old sample This feature explains the strong increase of tg values of older cables at VLF at high temperature. In fact with young samples (having a flatter curve) the increase is reduced with respect to older samples. For the measurement with PDC system, a voltage of Vdc was chosen after comparison of measurement results at different stress values; a polarisation and depolarisation time of 4 s was chosen, for a total test duration of about two hours. As already mentioned from the recorded currents the system has the possibility to investigate different possible diagnostic indicators and namely: tg values at different frequencies, polarisation index, polarisation spectrum, return voltage parameters, insulation resistance and evaluation of humidity in the insulation system. For all the samples the measurements were performed at ambient temperature only. Figure shows a comparison between tg values measured by FDS system and those calculated by PDC system. tan Ι 1.. Ι.. Fase Polarisation Polarizzazione Fase Depolarisation Depolarizzazione Frequency [ Hz ] Figure : tg values measured by FDS system and calculated by PDC system The figure shows that the agreement is excellent in the frequency range.1-1hz, while for higher frequencies an important difference can be noted, due to the particular test sequence used by PDC system. The values of the different diagnostic indicators were reported as a function of service age to verify the presence of a correlation. Figure 11 shows the maximum value of return voltage. It can be seen that the voltages relevant to the younger cables have lower values than all the others, while the values belonging to the other two groups are not clearly separated. FDS Age [years] Figure 11: maximum value of the return voltage as a function of service age At the end of diagnostic measurements, samples were subjected to the determination of the dielectric residual strength with the aim of finding possible correlation between the values of the diagnostic indictors and the real ageing state of the cables. The residual strength was determined at PF increasing the applied voltage by 5 kv steps (of 15 min each). Five cables (C4, C7, C8, C9 and C) were kept to breakdown. In any case no puncture occurred in the cable itself but in the terminations that, for assembling reasons were the weakest points of the test objects. To avoid the destruction of the samples without obtaining results directly related with dielectric properties of the cable, the breakdown test was then converted in a withstand test, with a minimum requirement higher than typical network overvoltages (for example those caused by failure) previously evaluated with EMTP program. All the remaining cables passed PF (2 kv) as well as the subsequent lightning impulse (8 kvp) withstand test. The results of breakdown/withstand tests are summarised in figure 12 where the maximum power frequency overvoltage expected in 9 kv AEM Elettricità system is also displayed. Voltage [kvrms] C1 C2 Breakdown / Withstand Test C3 C4 C5 C6 Cable Figure 12: PF breakdown (red) and withstand (blue) tests For obtaining further information on the real aging of the insulation system, cables taken to breakdown were disassembled for visual and chemical/physical analysis. In the oldest cable the external armour was heavy corroded but the impervious lead sheath guaranteed a perfect seal against water or other contaminant ingress and inner components were still in good conditions. Figure 13 shows two insulating paper tapes taken from a 21 yr cable (upper) and from a 68 yr old cable (bottom), respectively. C7 C8 C9 C Max P.F. overvoltage
5 Figure 13: Comparison between paper tapes removed from a 21 (upper) and 68 years old (lower) cables The figure clearly shows the change of colour of the paper tape of the older cable sample. Chemical analyses were performed on small quantities of compound taken from insulation of cables with the aim of identifying the presence of typical products of ageing. At the purpose FT-IR Spectroscopy was used. The aim was to detect the presence of CO bond (at 1693 cm -1 ) that is a product of the ageing process of the insulation [3]. Figure 14 shows the spectra of a young and an old sample. Figure 14: Comparison between young (left) and old (right) cable FT-IR spectroscopy Vertical arrow identifies the presence of peak at 1693 cm -1 on old sample and absence of same peak on young cable. The reference peaks, typical of impregnating compound, are located between 3 and 28 cm -1. Moreover, paper tapes, taken from the belt area of the cables, were used for other tests: determination of water content, degree of polymerisation and the tensile strength. The results obtained are reported in table 2. Table 2: Results of physical/chemical tests Sample Water content (%) Degree of polymerisation Tensile strength (MPa) C4 (43 Y),15, C7 (45Y),14, C9 (68 Y) 1,42 1, C (21 Y),, The table shows that C9 cable, beside the colour of paper tapes, has a higher water content and a lower tensile strength. The very large spread of the tensile strength test results of sample C can be explained by the fact that the papers of this cable were very wrinkled. For the interpretation of the results of the diagnostic measurements it is necessary to have a correlation between the measured values and the real ageing degree of the components (cable in this case). The data available in technical literature are not completely exhaustive neither for the newest diagnostic systems nor for the traditional ones. Taking into account the data found in bibliography and our experience, for each of the diagnostic indicator two levels were identified. Values lower than the minimum indicate a safe situation (green light), values above highest limit indicate a very aged component (red light) and the values between the two limits indicate an intermediate ageing degree (yellow light) requiring deeper analysis or the need of subsequent checks. Figure 15 shows for the tested samples a traffic light like chart reporting the ageing degree derived by the interpretation of each of the diagnostic indicator considered. TanD Hz TanD VLF PDC FDS Vbdo Tamb Hot Tamb Hot Relet Cvlf/cfi Ipol Vmax Trmax Sp Tg min C1 C6 C C3 C4 C7 C8 C2 C5 C9 Figure 15: Chart with the interpretation of the diagnostic measurements The chart is divided into three zones according to the service age of the cable. It can be noted that for each zone different degrees of ageing conditions are identified, but in any case for the youngest cables the green evaluation is prevalent, for the oldest cables several red and yellow evaluations are present and the middle aged cables have an intermediate colour distribution. Considering that no very critical cables were found, it was decided to induce artificial defects on some samples. The defects chosen aimed to simulate real defects and namely the penetration of humidity inside the insulation and leakage of insulating compound. The lead sheaths were cut on two cables, having a service age of about 2 and 7 years, and the samples immersed into water. The terminations were removed from a third sample having a service age of 7 years approximately. The cable was hanged with the removed termination up-side down, in such a way to allow the spilling of impregnating compound. A heating tape was wrapped around the cable to increase the temperature to ease paper draining. Diagnostic measurements were performed at regular interval. Figure 16 shows for sample C1 the variation of tg curve as a function of immersion in water time. The figure shows that after 46 days tg variation in the very low frequency zone is negligible, while it is more consistent for frequencies higher than.1 Hz. In particular, the minimum value is increased confirming that it is correlated to humidity content of the insulation. After 46 days of immersion in water, tg of the immersed cable was measured with VLF at the voltage levels of 6 and 9 kv, the values being 14* -3 and 36* -3 respectively.
6 Values measured on the same cable and at the same voltage levels before starting the ageing were 8.6* -3 and 9.7* -3, respectively. This seems to indicate the importance of carrying out measurements at different voltages. Increasing the voltage a failure was obtained at a voltage of 12 kv..1.1 Cable C1: variation with water penetration day 28 days 46 days Figure 16: Tg curve versus time of immersion in water Samples of sound cable having a length of, and 1 m were connected to the immersed cable (about 5 m long) to evaluate the sensitivity of the measuring method to detect short portion of humid cable. Figure 17 shows the results adding m of new cable to C1 sample. The figure reports the FDS curves of the short humid sample (blue line), that of the new m cable (purple line), that of the series of the two cables (green line) and that calculated (red dotted) using the characteristics of the two cables. The picture underlines the influence of the cable length on the sensitivity of the method in pinpointing short aged parts... Tgd as a function of cable lenght C1 (5 m) BM ( m) C1-BM calc C1-BM Meas Figure 17: Influence of cable length on tg curve Measurements of tg as a function of draining time were performed on cable C9; the results do not show any appreciable variation with respect to initial condition. On the same cable PD measurements were performed after 15 heating cycles with PF and DOV. Figure 18 shows the results obtained with PF stress at U. Figure 18: PD pattern of drained cable The figure shows a clear PD activity typical of internal defects. The maximum level of about 3 pc makes this measurement not very sensitive for on site application. PD measurements performed with DOV on the sample show a similar pattern with a PD level of several thousands of pc. CONCLUSIONS A diagnostic campaign was carried out with the aim of assessing the insulation condition of 9 kv cables of AEM Elettricità. Electrical tests were performed on site and in laboratory. Laboratory tests were carried out on cable samples removed from service and representative of installed population; moreover chemical/physical analyses were performed on insulation system components. The results of the tests have shown that cable samples have still sufficient residual dielectric characteristics to withstand the service stresses. Beside the experience gained has shown that a single diagnostic indicator is not generally sufficient to assess the ageing state of PILC cables and several methods are necessary. For laboratory tests all the methods described in the paper have shown to be useful to assess the ageing state of samples representative of cable network population. Under on site conditions the number of tests must be optimised in order to reduce testing time. On the base of our experience the minimum set of test methods should include the determination of FDS curve and HV tests, namely the measurement of tg values at two voltage levels (e.g. in the range of U ) and the measurement of PD activity. Further activities in laboratory and on site are necessary to confirm the results. ACKNOWLEDGMENTS This work has been financed by the Research Fund for the Italian Electrical System under the Contract Agreement between CESI RICERCA and the Ministry of Economic Development - General Directorate for Energy and Mining Resources stipulated on June 21, 27 in compliance with the Decree n.73 of June 18, 27. Special thanks to Sergio Belvedere and Massimo Garotta for conducting laboratory activities. REFERENCES [1] W. Zaengl, 21, Dielectric spectroscopy in time and frequency domain for HV power equipment (transformers, cables etc) 12 th ISH, Bangalore, India [2] R. Neimanis, January 24, Diagnosis of moisture in oil/paper distribution cables, IEEE Transactions on Power Delivery Vol. 19 N 1 [3] V. Buchholz, 21 Condition assessment of distribution PILC cables, IEEE Electrical Insulation Magazine, Vol 2, pages 1-12
Partial discharge diagnostics on very long and branched cable circuits
11 Nordic Insulation Symposium Stockholm, June 11-13, 2001 Partial discharge diagnostics on very long and branched cable circuits Nico van Schaik, E. Fred Steennis, Wim Boone and Dick M. van Aartrijk KEMA
More informationMV Power Cable Diagnostics by Frequency Domain Spectroscopy. Peter Werelius Programma Electric AB
MV Power Cable Diagnostics by Frequency Domain Spectroscopy Peter Werelius Programma Electric AB Frequency Domain Spectroscopy Measurements of insulation capacitance and losses in a frequency interval
More informationTHE PROPAGATION OF PARTIAL DISCHARGE PULSES IN A HIGH VOLTAGE CABLE
THE PROPAGATION OF PARTIAL DISCHARGE PULSES IN A HIGH VOLTAGE CABLE Z.Liu, B.T.Phung, T.R.Blackburn and R.E.James School of Electrical Engineering and Telecommuniications University of New South Wales
More informationUSING DAMPED AC VOLTAGES
MODERN & TESTING DIAGNOSIS OF POWER CABLES USING DAMPED AC VOLTAGES BY EDWARD GULSKI AND ROGIER JONGEN, Onsite HV Solutions ag, Switzerland AND RALPH PATTERSON, Power Products & Solutions LLC, United States
More informationApplication of Polarisation Depolarisation Current (PDC) technique on fault and trouble analysis of stator insulation
CIGRE SC A1 & D1 JOINT COLLOQUIUM October 24, 2007 Application of Polarisation Depolarisation Current (PDC) technique on fault and trouble analysis of stator insulation S. A. BHUMIWAT Independent Consultant
More informationRESIDUAL LIFE ASSESSMENT OF GENERATOR TRANSFORMERS IN OLD HYDRO POWER PLANTS
RESIDUAL LIFE ASSESSMENT OF GENERATOR TRANSFORMERS IN OLD HYDRO POWER PLANTS Authored by: Sanjay Srivastava, Chief Engineer (HE&RM), Rakesh Kumar, Director (HE&RM), R.K. Jayaswal, Dy. Director (HE&RM)
More informationTRANSFORMERS FAULT ANALYSIS - A MULTIDISCIPLINARY APPROACH
TRANSFORMERS FAULT ANALYSIS - A MULTIDISCIPLINARY APPROACH Giuseppe Cappai, Bernhard Heinrich, Giuseppe Simioli, Leonardo Trevisan Weidmann Electrical Technology AG, Switzerland Abstract: A large solar
More informationINVESTIGATION ON THE TECHNOLOGIES FOR DEFECT LOCALIZATION AND CHARACTERIZATION ON MEDIUM VOLTAGE UNDERGROUND LINES
INVESTIGATION ON THE TECHNOLOGIES FOR DEFECT LOCALIZATION AND CHARACTERIZATION ON MEDIUM VOLTAGE UNDERGROUND LINES Gonzalo MAIZ, Iberdrola Distribución, (Spain), gmaiz@iberdrola.es Armando RODRIGO, Instituto
More informationIDAX 300 Insulation Diagnostic Analyzer. Dielectric Frequency Response Also known as: Frequency Domain Spectroscopy
IDAX 300 Insulation Diagnostic Analyzer Dielectric Frequency Response Also known as: Frequency Domain Spectroscopy 1 Frequency Domain Spectroscopy Hi V A Lo Ground C HL Measure at several frequencies Use
More informationAll the standards referred to the most current issue, including all amendment supplements. as of the date of the bid.
1. Scope This specification defines the methods, the procedures and the requirements to verify the cables manufactured according to I.E.C. Specifications NPS361. 2. Standards All the standards referred
More informationCorrelation between time and frequency domain polarisation measurements for transformer moisture assessment
Australasian Universities Power Engineering Conference (AUPEC 24) 26-29 September 24, Brisbane, Australia Correlation between time and frequency domain polarisation measurements for transformer moisture
More informationCondition-based maintenance of power transformers Complete three-phase system Turns Ratio: Recovery Voltage: Winding Resistance:
ETP SYSTEM Condition-based maintenance of power transformers The predictive and condition based maintenance is nowadays accepted as the most efficient solution to guarantee the proper operation of critical
More informationMV Power Cable Testing Training
MV Power Cable Testing Training Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq Since power cables are used
More informationPD Testing Considerations for MV Plant Cables
PD Testing Considerations for MV Plant Cables Cable Testing Philosophy Damage Mistake Aging Repair Manufacturing Transportation Installation Operation Power frequency 50/60 Hz Power frequency 50/60 Hz
More informationFault location on power cables. Fault location on power cables
Fault location on power cables Fault location on power cables Contents: 1. Introduction 2. Construction of power cables 3. Cable faults 1. Introduction Fault location on communication and power cables
More informationTesting and PD Diagnosis of MV Cable Systems with DAC Voltage Educational Session May St Pete Beach, Fl
Testing and PD Diagnosis of MV Cable Systems with DAC Voltage Educational Session May 26 2011 St Pete Beach, Fl HDW ELECTRONICS, INC. THE BEST IN CABLE FAULT LOCATING TECHNOLOGY by Henning Oetjen Frank
More informationBEST PRACTICES FOR OFFLINE DIAGNOSIS OF MV CABLES
BEST PRACTICES FOR OFFLINE DIAGNOSIS OF MV CABLES HEIN PUTTER Productmanager cable testing and -diagnosis Megger Site Germany 1 13 th Insucon conference 16-18 th Mai 2017, Birmingham, UK Agenda Introduction
More informationSimultaneous Partial Discharge and Tan Delta Measurements: New Technology in Cable Diagnostics
Simultaneous Partial Discharge and Tan Delta Measurements: New Technology in Cable Diagnostics Dominique Bolliger, Ph.D. HV TECHNOLOGIES, Inc. Manassas, VA, USA d.bolliger@hvtechnologies.com Abstract In
More informationEffective Maintenance Test Techniques and Diagnostic Measurements to Improve the Performance and Reliability of Power System Transformers
Effective Maintenance Test Techniques and Diagnostic Measurements to Improve the Performance and Reliability of Power System Transformers Alexander Dierks, Herman Viljoen, Alectrix (Pty) Ltd, South Africa
More informationEI HIGH VOLTAGE INSULATION TESTING POLICY
Network(s): Summary: ENGINEERING INSTRUCTION EI 09-0001 HIGH VOLTAGE INSULATION TESTING POLICY EPN, LPN, SPN This engineering instruction details the policy for the on-site insulation testing of new and
More informationCable diagnostic in MV underground cable networks
Cable diagnostic in MV underground cable networks Theoretical background and practical application VLF testing tan delta loss factor measurement Partial discharge localization and measurement Author: Tobias
More informationTRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 SCOPE 2.0 BONDING METHODS
1.0 SCOPE 2.0 BONDING METHODS 2.1 Introduction 2.2 Design 2.3 Single-Point Bonding 2.4 Cross Bonding 2.5 Sheath Sectionalizing Joints 2.6 Sheath Standing Voltage 2.7 Sheath Voltage at Through Fault 2.8
More informationVLF. DAC tandelta. Partial Discharge. Experience the world of Megger electrical testing
Cable Testing & Diagnostics Solutions for Medium Voltage Networks (1 kv - 36 kv) VLF Partial Discharge DC DAC tandelta Cable Testing Cable Diagnostics? There are two main applications for cable testing:
More informationشركة الوقت للكهرباء والمقاوالت ذ.م.م.
CONTRACTING COMPANY W.L.L. is a leading corporate in the United Arab Emirates offering quality services in the field of High Voltage Electrical work 400, 132 & 33 kv and Medium Voltage Power Distribution
More informationEffective maintenance test techniques for power transformers
Effective maintenance test techniques for power transformers by Alexander Dierks, Herman Viljoen, Alectrix, South Africa, and Dr. Michael Krüger, Omicron Electronics, Austria Due to ever-increasing pressure
More informationREPORT OF PERFORMANCE TIC
REPORT OF PERFORMANCE TIC 1580-13 OBJECT TYPE Three-core power cable 18/30(36) kv, 3x500 mm2, 2XWY(P)-FR XLPE Rated voltage, U 0/U (U m) 18/30 (36) kv Conductor material Cu Conductor cross-section 3x500
More informationMATEFU Insulation co-ordination and high voltage testing of fusion magnets
Stefan Fink: MATEFU Insulation co-ordination and high voltage testing of fusion magnets Le Chateau CEA Cadarache, France April 7th, 29 Insulation co-ordination Some principle considerations of HV testing
More informationThis Certificate consists of 75 pages in total.
Object Heat shrinkable indoor termination 1086-16 Type MZDNK-3-15-C Rated voltage, U 0 /U (U m ) 8,7/15 (17,5) kv Conductor material Cu Conductor cross-section 3 x 185 mm 2 Insulation material XLPE Manufacturer
More informationAnalysis of Major Changes to Arrester Standards IEC STEVE BREWER
Analysis of Major Changes to Arrester Standards IEC 60099-4 STEVE BREWER Analysis of Major Changes to Arrester Standard IEC 60099-4 Steve Brewer- Senior Product Manager - HPS Arrester Business Unit Agenda
More informationPOWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009
POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009 Nkosinathi Buthelezi Senior Consultant: Power Transformers and Reactors Presentation Content Standardization of Power
More informationAspects of PD interpretation in HV power cables. by Edward Gulski, Piotr Cichecki, Rogier Jongen
Aspects of PD interpretation in HV power cables by Edward Gulski, Piotr Cichecki, Rogier Jongen General There are several aspects having influence on the diagnostic information and the condition judgment
More informationAfrica Utility Week Focus Day Substation Condition Monitoring Benefits of Ultrasound
Africa Utility Week Focus Day 2014 Substation Condition Monitoring Benefits of Ultrasound Agenda Review - Substation Condition Monitoring Electrical discharge Types and origin In switchgear Results/consequences
More informationCable testing and diagnostics
Cable testing and diagnostics To ensure the flow Cost-optimised maintenance through cable diagnostics The sheath and cable testing supports you in assessing whether a cable system is safe and ready to
More informationEnergy Division. Bowthorpe LV/MV Surge Arresters
Energy Division Bowthorpe LV/MV Surge Arresters Bowthorpe EMP LV/MV surge arresters OCP, Open Cage Polymeric series Bowthorpe pioneered the development of polymeric housed surge arresters in the early
More informationEstimating the Impact of VLF Frequency on Effectiveness of VLF Withstand Diagnostics
Estimating the Impact of VLF on Effectiveness of VLF Withstand Diagnostics Nigel Hampton (1), Jean Carlos Hernandez-Mejia (2), Marina Kuntsevich (3), Joshua Perkel (1), Vivek Tomer (3) 1 - NEETRAC, Atlanta,
More informationECP HV INSULATION TESTING
Document Number: ECP 11-0006 Network(s): Summary: All ENGINEERING COMMISSIONING PROCEDURE ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing of new and
More informationInnovative Test Techniques and Diagnostic Measurements to Improve the Performance and Reliability of Power System Transformers
Innovative Test Techniques and Diagnostic Measurements to Improve the Performance and Reliability of Power System Transformers Dr. Michael Krüger, Alexander Kraetge, OMICRON electronics GmbH, Austria Alexander
More informationNEW MV CABLE ACCESSORY WITH EMBEDDED SENSOR TO CHECK PARTIAL DISCHARGE ACTIVITY
NEW MV CABLE ACCESSORY WITH EMBEDDED SENSOR TO CHECK PARTIAL DISCHARGE ACTIVITY Lorenzo PERETTO Luigi FODDAI Simone ORRU Luigi PUDDU Altea Switzerland ENEL Italy ENEL Italy REPL Italy lperetto@alteasolutions.com
More informationAssuring the Reliability of Critical Power Cable Systems
Assuring the Reliability of Critical Power Cable Systems Presented by: Benjamin Lanz Manager of Application Engineering IMCORP Power Cable Reliability Consulting & Diagnostics Some of the technologies
More informationCable fault location in power cables. Systematics for cable testing, diagnosis and cable fault location
Cable fault location in power cables Systematics for cable testing, diagnosis and cable fault location CABLE JOINTS, CABLE TERMINATIONS, CABLE GLANDS, CABLE CLEATS FEEDER PILLARS, FUSE LINKS, ARC FLASH,
More informationPHG 70 TD PD / PHG 80 TD PD
PHG 70 TD PD / PHG 80 TD PD BAUR VLF test and diagnostics system Functions Universal test and diagnostics system flexible, modular, extendable Cutting-edge testing and diagnostics technology: VLF truesinus
More informationTRAINING OVERVIEW EDUCATION IS POWER. HIGH V O L T A G E T E S T S OLUTION S. reliable. precision.
TRAINING OVERVIEW EDUCATION IS POWER www.hipotronics.com/training reliable. precision. HIGH V O L T A G E T E S T S OLUTION S 2 EDUCATION IS POWER EDUCATION IS POWER LEARN WHAT WE HAVE TO OFFER Through
More informationA Study on the Effect of Performing VLF Withstand Tests on Field Aged Degraded Joints
WETS D 15 2.4 Drapeau A Study on the Effect of Performing VLF Withstand Tests on Field Aged Degraded Joints Jean-François DRAPEAU Researcher Expertise Équipement électriques IREQ Jacques CÔTÉ, HQD Simon
More informationEFFECT OF INTEGRATION ERROR ON PARTIAL DISCHARGE MEASUREMENTS ON CAST RESIN TRANSFORMERS. C. Ceretta, R. Gobbo, G. Pesavento
Sept. 22-24, 28, Florence, Italy EFFECT OF INTEGRATION ERROR ON PARTIAL DISCHARGE MEASUREMENTS ON CAST RESIN TRANSFORMERS C. Ceretta, R. Gobbo, G. Pesavento Dept. of Electrical Engineering University of
More informationOFFLINE PD DIAGNOSTICS USING SEVERAL EXCITATION VOLTAGES
OFFLINE PD DIAGNOSTICS USING SEVERAL EXCITATION VOLTAGES Hein PUTTER Frank PETZOLD Philipp LEGLER Megger Germany Megger Germany Megger - Germany hein.putter@megger.com frank.petzold@megger.com philipp.legler@megger.com
More informationINSULATION DIAGNOSIS OF HIGH VOLTAGE POWER CABLES
INSULATION DIAGNOSIS OF HIGH VOLTAGE POWER CABLES Edward GULSKI, Delft University of Technology, (The Netherlands), e.gulski@tudelft.nl Johan J SMIT, Delft University of Technology, (The Netherlands),
More informationPD Diagnostic Applications and TechImp solutions
PD Diagnostic Applications and TechImp solutions Condition Assessment Solutions for Electrical Systems. PD based innovative tools for the Condition Based Maintenance. MD-04.05.004 - rev. 00-29/08/2006
More informationCable fault location. The shortcut to locating a fault
Cable fault location The shortcut to locating a fault Reliable cable fault location with BAUR Top quality supply is our utmost concern You want to offer your customers a reliable power supply and to use
More informationEvaluation of Distribution Line Spacers through the Leakage Current Monitoring
Tsinghua University, Beijing, China, August -9, H-6 Evaluation of Distribution Line Spacers through the Leakage Current Monitoring A. G. Kanashiro *, W. Pinheiro and G. F. Burani Institute of Electrotechnics
More informationCondition Assessment of High Voltage Insulation in Power System Equipment. R.E. James and Q. Su. The Institution of Engineering and Technology
Condition Assessment of High Voltage Insulation in Power System Equipment R.E. James and Q. Su The Institution of Engineering and Technology Contents Preface xi 1 Introduction 1 1.1 Interconnection of
More informationWIRE AND CABLE ENGINEERING GUIDE
Excerpt From Prysmian s WIRE AND CABLE ENGINEERING GUIDE Page 1 of 8 CABLE TESTING Testing represents an integral part in the life of a cable. A cable will be subjected to multiple tests in its lifetime
More informationPartial Discharge Measurement and Monitoring on High Voltage XLPE Cables
21, rue d Artois, F-75008 PARIS AUCKLAND 2013 http : //www.cigre.org Partial Discharge Measurement and Monitoring on High Voltage XLPE Cables Michael Krüger, Rene Hummel, Stefan Böhler, OMICRON Austria
More informationElectric Stresses on Surge Arrester Insulation under Standard and
Chapter 5 Electric Stresses on Surge Arrester Insulation under Standard and Non-standard Impulse Voltages 5.1 Introduction Metal oxide surge arresters are used to protect medium and high voltage systems
More informationPart 1: General. Part 3: Mechanical loads Part 4: Climatic loads Part 5: Chemical loads
ISO 16750-2 (2012) at a glance Road vehicles. Environmental conditions and testing for electrical and electronic equipment Part 2: Electrical loads The relating standards: ISO 16750-2 (2003) ISO 16750-2
More informationEvaluation of Distribution Line Spacers Located Near the Coast
Evaluation of Distribution Line Spacers Located Near the Coast WALTER PINHEIRO ARNALDO G. KANASHIRO 2 GERALDO F. BURANI 2 Consultant Engineer University of São Paulo Av. Prof. Luciano Gualberto, 289, São
More informationTECHIMP Technologies & Services for Diagnostics and Monitoring of High Voltage Assets
TECHIMP Technologies & Services for Diagnostics and Monitoring of High Voltage Assets Who we are TECHIMP is one of the leading providers of Condition Assessment Services Data Acquisition and Test Equipment
More informationIEC Type Test Report Report No. EU1517-H-00.1 H4 Series Porcelain-housed Arrester 20,000 A Line Discharge Class 4
IEC Type Test Report Report No. EU1517-H-00.1 H4 Series Porcelain-housed Arrester 20,000 A Line Discharge Class 4 This report records the results of type tests made on H4 series 20 ka Line Discharge Class
More informationBY JASON SOUCHAK, Megger
IMPROVING SYSTEM RELIABILITY WITH OFFLINE PD TESTING BY JASON SOUCHAK, Megger Partial discharge (PD) testing is a new generation of diagnostic testing for medium- and high-voltage underground power cable
More informationAn Overview of Diagnostic Testing of Medium Voltage Power Cables John Densley
An Overview of Diagnostic Testing of Medium Voltage Power Cables John Densley ArborLec Solutions Inc. CIGRE WG 21:04 in 1994 Purpose of diagnostic test is: To evaluate and locate degradation phenomena
More informationCHAPTER 10 HIGH VOLTAGE TESTING OF ELECTRICAL APPARATUS
CHAPTER 10 HIGH VOLTAGE TESTING OF ELECTRICAL APPARATUS 1. Introduction 2. Classification of High Voltage Tests 3. Test Voltages 4. High Voltage Testing of Electrical Apparatus 1. INTRODUCTION Purpose
More informationInvestigations on a Combined Resonance/VLF HV Test System Partial Discharge (PD) characteristics at VLF and DAC voltages
Investigations on a Combined Resonance/VLF HV Test System Partial Discharge (PD) characteristics at VLF and DAC voltages F. Petzold, H.T. Putter, D. Götz, H. Schlapp, S. Markalous SebaKMT GmbH Baunach/Radeburg,
More informationExtending the Functionality of On-line PD Monitoring Equipment for MV Power Cables
24 th Nordic Insulation Symposium on Materials, Components and Diagnostics 152 Extending the Functionality of On-line PD Monitoring Equipment for MV Power Cables Y. Li 1, P.A.A.F. Wouters 1, P. Wagenaars
More informationTT 0710/03. TYPE TEST OF 3 Phase Solid Earthing Bonding Link Box, Type: LB.W.3SA.3.1
TT 0710/03 TYPE TEST OF 3 Phase Solid Earthing Bonding Link Box, Type: LB.W.3SA.3.1 Tested by: IPH, Berlin RPT No : 2977.2100555.0379 Date: 09 June to 24 June, 2010 Pages: 30 Appendix: --- TT0710.03 A3
More informationCIGRE General Session, Paris 2014 Group Meeting SC B1 Insulated Cables, 27th August, 2014 Results of CAG Questionnaire
1 1. Number of Questionnaires Returned 23 2. Number of suggestions for work 64 3. Suggestions for new work within the scope of SCB1 or for additional work by current Working Groups in? 3.1 cable system
More informationA Study on Lightning Overvoltage Characteristics of Grounding Systems in Underground Distribution Power Cables
J Electr Eng Technol Vol. 9, No. 2: 628-634, 2014 http://dx.doi.org/10.5370/jeet.2014.9.2.628 ISSN(Print) 1975-0102 ISSN(Online) 2093-7423 A Study on Lightning Overvoltage Characteristics of Grounding
More informationType 297, High-Voltage Mica Capacitors Corona-free Mica Coupling Capacitors for Medium-Voltage PDA s
Designed for Partial Discharge Analyzers (PDA s) monitoring rotating machinery or other medium-voltage equipment from 1 to 35 kvac RMS at power-line frequencies of 10 Hz to 1 khz, Mica Capacitor Type 297
More informationECP HV INSULATION TESTING
Document Number: ECP 11-0006 Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE EPN, LPN, SPN ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing
More informationCONDITION ASSESSMENT OF XLPE MV CABLE JOINTS BY USING AN INSULATION TESTER
CONDITION ASSESSMENT OF XLPE MV CABLE JOINTS BY USING AN INSULATION TESTER Henrik ENOKSEN Espen EBERG Sverre HVIDSTEN SINTEF Energy Research - Norway SINTEF Energy Research - Norway SINTEF Energy Research
More informationInvestigation of PD Detection on XLPE Cables
Investigation of PD Detection on XLPE Cables Hio Nam O, T.R. Blackburn and B.T. Phung School of Electrical Engineering and Telecommunications The University New South Wales, Australia Abstract- The insulation
More informationTests on Extruded Cables
Tests on Extruded Cables Pierre Argaut Chairman of CIGRE SC B1 October 26 th, 2011 At least, once in your life, you have heard these words: Development Tests Long-term Tests Prequalification Tests Extension
More informationStatistical Characteristics of Partial Discharge Caused by Typical Defects in Cable Joint under Oscillating Voltage
Journal of Energy and Power Engineering 9 () 3-3 doi:.7/93-897/.3. D DAVID PUBLISHIG Statistical Characteristics of Partial Discharge Caused by Typical Defects in Cable Joint under Oscillating Voltage
More informationUser s Manual For CT Model IMB
User s Manual For CT Model IMB 2 of (13) Contents: A. Introduction... 3 B. Steps on receipt and opening the cases... 3 C. Transportation and handling... 3 D. Unpacking the transformer... 4 E. Storage...
More informationON-LINE PARTIAL DISCHARGE TESTING OF SOME OF THE WORST PERFORMING CIRCUITS ON A UTILITY DISTRIBUTION SYSTEM
ON-LINE PARTIAL DISCHARGE TESTING OF SOME OF THE WORST PERFORMING CIRCUITS ON A UTILITY DISTRIBUTION SYSTEM D. Clark¹ R. Mackinlay² M. Seltzer-Grant² S. Goodfellow² Lee Renforth² Jamie McWilliam³ and Roger
More informationLong lengths transmission power cables on-site testing up to 500 kv by damped AC voltages
Long lengths transmission power cables on-site testing up to 500 kv by damped AC voltages Paul P. SEITZ, Ben QUAK, Seitz Instruments AG, Niederrohrdorf, Switzerland, pps@seitz-instruments.ch Edward GULSKI,
More informationDesign of HV Switching for Polarization & Depolarization Current Measurement
Design of HV Switching for Polarization & Depolarization Current Measurement N. F. Kasri, M. A. M. Piah, A. A. Suleiman, N. A. M. Jamail, N. Bashir and N. A. Muhamad Institute of High Voltage & High Current
More informationMatz Ohlen Director Transformer Test Systems. Megger Sweden
Matz Ohlen Director Transformer Test Systems Megger Sweden Frequency response analysis of power transformers Measuring and analyzing data as function of frequency, variable frequency diagnostics Impedance
More informationH V T E S T S O L U T I O N S PA RT N E RS F O R H V & E M C
H V T E S T S O L U T I O N S PA RT N E RS F O R H V & E M C S O L U T I O N S Y O U R S O U R C E F O R T O P Q U A L I T Y T E S T E Q U I P M E N T w w w. h v t e c h n o l o g i e s. c o m Company
More informationHigh Voltage Diagnostics Sarl 4, Rue de Lac CH 1897 Le Bouveret Switzerland
High Voltage Diagnostics Sarl 4, Rue de Lac CH 1897 Le Bouveret Switzerland Company HV Diagnostics Sarl is a Swiss based company in the field of high voltage test equipment for cable testing and diagnosis.
More informationTECHIMP Power Transformer Monitoring
TECHIMP Power Transformer Monitoring Kontakt: Martin Hesse Techimp Germany GmbH i.g. E-Mail: mhesse@techimp.com Tel.: +49 5724 391 007 Mobil: +49 170 2364 735 PD Monitoring of Power Transformers Power
More informationThe importance of partial discharge testing throughout the development and operation of power transformers
The importance of partial discharge testing throughout the development and operation of power transformers Ulrike Broniecki OMICRON Energy Solutions GmbH, Berlin Power transformers are exposed to intense
More informationEffective February 2017 Supersedes January 2012 (CP1122)
File Ref: Cat. Sec. CA235013EN CT235003EN Supersedes January 2012 (CP1122) COOPER POWER SERIES UltraSIL Polymer-Housed VariSTAR Type US, UH, and UX Station Class Surge Arresters Certified Test Report Certification
More informationCHAPTER 2. v-t CHARACTERISTICS FOR STANDARD IMPULSE VOLTAGES
23 CHAPTER 2 v-t CHARACTERISTICS FOR STANDARD IMPULSE VOLTAGES 2.1 INTRODUCTION For reliable design of power system, proper insulation coordination among the power system equipment is necessary. Insulation
More informationField Experiences. Partial Discharge Diagnosis on MV Cables. Philipp Legler. XVI. Szigetelésdiagnosztikai Konferencia (
Field Experiences Partial Discharge Diagnosis on MV Cables Philipp Legler Technical Support Applications Engineer (Megger Site Germany) XVI. Szigetelésdiagnosztikai Konferencia (19. - 20.10.2016, Sümeg)
More informationOff-Line Field Diagnostics for MV and HV Oil-Paper Insulated Cables
163 24 th Nordic Insulation Symposium on Materials, Components and Diagnostics Off-Line Field Diagnostics for MV and HV Oil-Paper Insulated Cables Sarajit Banerjee, Ali Naderian Kinectrics Inc., Toronto,
More informationSMART CABLE GUARD A TOOL FOR ON-LINE MONITORING AND LOCATION OF PD S AND FAULTS IN MV CABLES ITS APPLICATION AND BUSINESS CASE
SMART CABLE GUARD A TOOL FOR ON-LINE MONITORING AND LOCATION OF PD S AND FAULTS IN MV CABLES ITS APPLICATION AND BUSINESS CASE Fred STEENNIS Paul WAGENAARS Denny HARMSEN DNV GL the Netherlands DNV GL the
More informationCharacteristics of Insulation Diagnosis and Failure in Gas Turbine Generator Stator Windings
J Electr Eng Technol Vol. 9, No. 1: 280-285, 2014 http://dx.doi.org/10.5370/jeet.2014.9.1.280 ISSN(Print) 1975-0102 ISSN(Online) 2093-7423 Characteristics of Insulation Diagnosis and Failure in Gas Turbine
More informationNPS/002/016 Technical Specification for 33 kv Cable Joints and Terminations
Version: 3.1 Date of Issue: September 2016 Page: 1 of 21 NPS/002/016 Technical Specification for 33 kv Cable Joints and Terminations 1. Purpose The purpose of this document is to detail the technical requirements
More informationUHF PD-DIAGNOSIS AT HIGH VOLTAGE CABLE TERMINATIONS INTERNATIONAL CASE STUDIES
UHF PD-DIAGNOSIS AT HIGH VOLTAGE CABLE TERMINATIONS INTERNATIONAL CASE STUDIES D. Götz*, H.T. Putter* *Megger Germany INTRODUCTION High voltage termintions are essential components in high voltage cable
More informationComparison of CAN/CSA C88.1, IEEE C /01 & IEC 60137
ITEM Power factor (tanδ) & Capacitance Measurement Dry 1-minute Power frequency with partial discharge measurement CAN/CSA C88.1-96 IEEE C57.19.00/01 IEC 60137 Requirement Requirement Requirement Clause
More informationSpecialists in HV and MV test and diagnostics. Testing in Substations
Specialists in HV and MV test and diagnostics Testing in Substations Testing in Substations Testing in Substations At 4fores we specialize in the diagnosis and measurement of all types of existing technologies
More informationField Measurement of Transmission Cable Dissipation Factor
Workshop 2000, Alexandria, Virginia, 13 & 14 September 2000 paper No.: 1 Field Measurement of Transmission Cable Dissipation Factor John H. Cooper, Power Delivery Consultants, Inc. Abstract This presentation
More informationASTA TEST REPORT NO: HEATSHRINK TERMINATIONS 3 CORE 12kV PILC AND XLPE
ASTA TEST REPORT NO: 2212 HEATSHRINK TERMINATIONS 3 CORE 12kV PILC AND XLPE UNIVERSAL 12kV HEATSHRINK JOINT TO SUIT 3 CORE XLPE / PILC CABLES INLINE OR TRANSITION RECORD OF PROVING TESTS Page 1 of 6 Laboratory
More informationInsulating oil testing
Insulating oil testing Insulating liquids are an important component of many electrical devices. Highly refined mineral oils, silicone oils, vegetable oils (natural ester) and synthetic ester ensure smooth
More informationLV DC DISTRIBUTION NETWORK WITH DISTRIBUTED ENERGY RESOURCES: ANALYSIS OF POSSIBLE STRUCTURES
LV DC DISTRIBUTION NETWORK WITH DISTRIBUTED ENERGY RESOURCES: ANALYSIS OF POSSIBLE STRUCTURES Alessandro AGUSTONI Enrico BORIOLI Morris BRENNA * Giuseppe SIMIOLI Enrico TIRONI * Giovanni UBEZIO * Politecnico
More informationInsulation Assessment of Oil Impregnated Paper Condenser Bushings using Dielectric Frequency Response Technique
Indian Journal of Science and Technology, Vol 10(21), DOI: 10.17485/ijst/2017/v10i21/114368, June 2017 ISSN (Print) : 0974-6846 ISSN (Online) : 0974-5645 Insulation Assessment of Oil Impregnated Paper
More informationPERMANENT ON-LINE MONITORING OF MV POWER CABLES BASED ON PARTIAL DISCHARGE DETECTION AND LOCALISATION AN UPDATE
PERMANENT ON-LINE MONITORING OF MV POWER CABLES BASED ON PARTIAL DISCHARGE DETECTION AND LOCALISATION AN UPDATE Fred STEENNIS, KEMA, (the Netherlands), fred.steennis@kema.com Peter VAN DER WIELEN, KEMA,
More informationCoherence and time-frequency analysis of impulse voltage and current measurements
Coherence and time-frequency analysis of impulse voltage and current measurements Jelena Dikun Electrical Engineering Department, Klaipeda University, Klaipeda, Lithuania Emel Onal Electrical Engineering
More informationModeling insulation in high-voltage substations
38 ABB REVIEW DESIGNED FOR SAFETY DESIGNED FOR SAFETY Modeling insulation in high-voltage substations The goal of insulation coordination is to determine the dielectric strength of transformers and other
More informationEVALUATION AND COMPARISON OF ON-LINE PD DETECTION METHODS FOR HIGH-VOLTAGE POWER CABLE
EVALUATION AND COMPARISON OF ON-LINE PD DETECTION METHODS FOR HIGH-VOLTAGE POWER CABLE Ju-Chu Hsieh 1, Cheng-Chi Tai 1, Ching-Chau Su 1, Chien-Yi Chen 1, Ting-Cheng Huang 1, Yu-Hsun Lin 2 1 Department
More informationUnderground System Design TADP 547
Underground System Design TADP 547 Industry Standards, Specifications and Guides Presentation 6.4 Instructor: Frank Frentzas Industry Organizations Several professional organizations develop standards