CHIEF ENGINEER PROCEDURE MANAGEMENT OF OVERLAPPING DESIGN AGREEMENT

Size: px
Start display at page:

Download "CHIEF ENGINEER PROCEDURE MANAGEMENT OF OVERLAPPING DESIGN AGREEMENT"

Transcription

1 Approval Amendment Record Approval Date Version Description 30/05/ Initial issue under MTM. This procedure supersedes the Overlapping Design Agreement, Application and Transfer Log documents L2-SIG-PRO-007, L4-SIG-FOR-028 and L4-SIG- FOR-029. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 15

2 Table of Contents 1. Purpose Background Abbreviations Definitions References & Legislation Responsibilities Considerations Process Start Up Meeting & Risk Assessment Approval to undertake Overlapping Design Process Modification Process Cancellation or Rescheduling of Projects Liabilities Related Documents Appendices...9 Appendix A - Flowchart of Overlapping Design Process Appendix B - Interim Maintenance Distribution Process Appendix C As-Built Submission Process Appendix D Sample Temporary Title Block Locations Appendix E Overlapping Design Agreement Application Appendix F Overlapping Design Agreement Design Transfer Log PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 2 of 15

3 1. Purpose The purpose of this document is to highlight the process and responsibilities for an overlapping design agreement where two or more contractors are required to produce designs under concurrent or compressed timescales. This agreement is applicable for all designs relating to MTM. 2. Background Within Rail projects there are often multiple contractors involved that may require the same engineering drawings. The Public Transport Victoria s Drawing Management System (DMS) is limited to the update from only one contractor at a time via a book in / book out process. The limitation of this process is that, if a second contractor wanted to work on the same design, the first contractor who is in control of the drawings would be required to book the drawings back into DMS (relinquishing their control of the drawings) to allow for the second contractor to modify the drawings. This can be both time consuming and costly. This procedure allows for two or more contractors to mark up drawings in a controlled manner and reduce the consequences of allowing only one contractor to update drawings. Also, when more than one contractor is involved in modifying the engineering designs in the same area of the network in parallel, there is no clear line of responsibility to ensure the design updates are all incorporated in a coordinated manner. Hence, this procedure will formalise and document the process that has been informally applied by a number of projects, which has often resulted in the loss of revision control, thus allowing the drawings to be updated in a controlled manner. 3. Abbreviations AIS DMS DOT IFC MTM PTV RDE RODE VRIOGS As In Service Drawing Management System Department of Transport Issued For Construction Metro Trains Melbourne Public Transport Victoria Responsible Design Engineer Responsible Overlapping Design Engineer Victorian Rail Industry Operators Group Standards PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 3 of 15

4 4. Definitions Drawing Controller CAD File MTM staff responsible for the control of drawings booked out from DMS and allocation to the Project Manager / Design Contractors Computer Aided Design File that is required to modify drawings. This can take on numerous file types depending on the design MTM Engineering MTM Engineering responsible for ensuring compliance of all designs to be booked back into DMS Primary Contractor Project Engineer Project Manager Responsible Design Engineer (RDE) Responsible Overlapping Design Engineer (RODE) Secondary Contractor Contractor who the drawings are booked out to. Often, this is the contractor whose works must proceed before the second contractor MTM staff who assists the Project Manager in the design / testing and commissioning aspects of the Project. A Project Engineer may be required as a conduit to communicate with the Contractor The lead responsible for the deliverables for a Project. Depending on the project, there may be two Project managers one for each Design Contractor. It must be the Project Manager(s) who initiate the Overlapping Design Agreement Representative of the Contractor as a direct contact relating to the designs. In order to avoid confusion and ambiguity -there shall only be a single Responsible Design Engineer for each Contractor concerned Person appointed by MTM for the purpose of coordination and facilitation of the Overlapping Design Agreement. Contractor that requires modifications to the designs but is booked out to the Primary Contractor 5. References & Legislation WPB-MPR-00-DES-009 Regional Rail Link: Overlapping Design Process VRIOGS Standard for Signalling Design and Documentation Rev. B VRIOGS Infrastructure Drafting Standards L1-NAM-PRO-003 Infrastructure As-Built Drawings Management AS : 2006 Railway Safety Management VRIOGS Dispensation Request to DMS Rail Safety Act 2006 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 4 of 15

5 6. Responsibilities Shown below is a breakdown of the responsibilities Drawing Controller (MTM) Drawing Management System (DMS) MTM & DMS Project Manager(s) (MTM) RODE (MTM) Engineering (MTM) Project Engineer / Responsible Design Engineer (MTM / Primary Contractor) Project Engineer / Responsible Design Engineer (MTM / Secondary Contractor) Contractor Primary Contractor Secondary Contractor Figure 1: Flowchart of Responsibilities 7. Considerations An overlapping Design allows for more than one contractor to modify engineering designs. The potential consequences for this are: integrity of data can be reduced, incorrect versions of the drawings being used, confusion of responsibilities and disputes / conflict of interest from the different contractors. Thus, the use of overlapping designs should be limited to cases where delivery of the projects is within a concurrent / compressed timeframe and / or there are large financial and safety repercussions. When considering an overlapping design agreement the following preferences should follow (with 1 being most preferred.) 1. Reschedule works to remove the requirement for an overlapping design. 2. Utilize the same contractor to perform the designs where overlapping is expected. 3. Undertake an overlapping design arrangement as per this procedure, subject to approval by MTM Engineering. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 5 of 15

6 8. Process The following outlines the typical process when undertaking an Overlapping Design Agreement. 8.1 Start Up Meeting & Risk Assessment A start up meeting is required among the contractors involved and the respective MTM representatives to: Assess the feasibility and requirements for an overlapping design agreement Identify the need for the overlapping design agreement Identify the Roles and responsibilities including, but not limited to: o Drawing Controller o RODE (Who will be responsible for the coordination of the drawings between the two contractors) o Primary Contractor (The Contractor where the drawings are booked out to) Secondary Contractor (The Contractor who wants to mark up the drawings booked out to the Primary Contractor) o Agree on the timeframes and design milestones including: When will the Secondary Contractor be able to obtain the CAD files; When will the Secondary Contractor complete their changes and transfer the design back to the Primary Contractor; When will the designs be submitted to Engineering for review and As In Service (AIS) Ascertain the designs that will be affected Define who will undertake the overall re-cad ing of the AIS post commissioning (Normally this would be the Primary Contractor) Who will undertake the final certification of the re-cad ed plans (Normally the Primary Contractor) Overall Tester In Charge (TIC) if the Project commissioning dates are the same Meeting minutes should be taken and should record all the above points as a minimum A risk assessment is to be performed with all stakeholders involved in the project to discuss the risks associated with allowing more than one contractor to work on engineering designs. Note that the Overlapping Design Agreement is subject to agreement by all parties concerned and the Contractor in control of the drawing has the right to refuse undergoing the agreement if they had appropriate justifications. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 6 of 15

7 8.2 Approval to undertake Overlapping Design Process Upon agreement by all affected Contractors at the start-up meeting and upon completion of a risk assessment, all related contractors must sign an agreement which highlights: the Contractors involved in the Overlapping Design Agreement the list of drawings required to be included in the Overlapping Design Agreement the list of drawings to be retained compliant the list of drawings to be made compliant Who will be applying for dispensation Who is the current Drawing Controller Who will be the RODE Who is the Project Manager(s) A sample template of an agreement is provided in Appendix E - Overlapping Design Agreement Application. The Project may opt to use their own form of agreement. A mark-up of the plans, highlighting each contractor s scope of works in a different color and the signed design agreement shall be submitted to DMS under Dispensation D Modification Process The processes of modifying designs are outlined below 1 : 1. The Secondary Contractor requires a design drawing from the Primary Contractor and notifies the RODE. 2. The RODE obtains a copy of the CAD file from the Primary Contractor. The copy of the CAD file will have a temporary new revision box overlaid on the existing drawing, for the purpose of the Overlapping Design Agreement. 3. The RODE logs the movement of the design. The log should contain, as a minimum,: RDE / Project Engineer providing the CAD file RDE / Project Engineer receiving the CAD file Date Reason for Change Attached list of comments & issues from the Primary Contractor The template log: Overlapping Design Agreement: Design Transfer Log can be used. The RODE shall keep all versions of the CAD files as it transfers between each contractor. This provides the ability to fall back to previous versions of the drawings, if required. 4. The RODE issues the CAD file, received from the Primary Contractor, to the Secondary Contractor. Note the Primary Contractor and the RODE shall retain a copy of the original CAD file booked out from DMS. 1 Refer to Appendix A for a flowchart of the Overlapping Design process. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 7 of 15

8 5. The Secondary Contractor works on the CAD file copy and keeps a log of any issues. All changes made by the Secondary Contractor should be identified by a separate color or any other agreed methodology. The Secondary Contractor shall ensure that their portion of the works is checked and independently reviewed (if required) prior to sending the designs back to the Primary Contractor. 6. Once the necessary works are complete the Secondary Contractor issues the CAD file copy to RODE, with the temporary revision box filled in. Examples of the temporary revision box can be seen in Appendix D Sample Temporary Title Block Locations. 7. The RODE logs the movement as per step The Primary Contractor receives the CAD file and performs any other mark ups required (with the applicable checking and independent review requirements satisfied). 9. In the event that the Commissioning works are within the same time frame only 1 Master Test Copy shall be produced (typically done by the Primary Contractor unless otherwise agreed). There should also only be a single Tester in Charge for the scope of works of the Primary and the Secondary Contractor. This must be agreed to prior to accepting the Overlapping Design Agreement. 10. In the event that the Commissioning dates are separate, each Contractor will be required to perform their own commissioning works independently (e.g. Production of Test copies, Construction Copies and Interim Maintenance copies). In this instance, the Tester in Charge may be different for each Contractor s commissioning activity. Refer to Appendix B Interim Maintenance Copies Distribution Process and Appendix C As-Built Submission Process. 11. It is the Primary Contractor s responsibility (unless otherwise agreed) to bring the drawings up to DMS Compliance or seek dispensation. 8.4 Cancellation or Rescheduling of Projects In the event that the project is cancelled or rescheduled, all drawings will be assessed by the RODE and their team with any required modifications to be carried out. 9. Liabilities Each contractor is liable for their own design. Any updates made by the Contactors on behalf of another Contractor under the Overlapping Design Agreement, does not import any liability from the Contractor requesting the change. The Overlapping Design Agreement will still require all Design Procedures to be followed for each Contractors portion of works. This includes certification, checking and independent review. 10. Related Documents Nil PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 8 of 15

9 11. Appendices Appendix A - Flowchart of Overlapping Design Process Appendix B - Interim Maintenance Distribution Process Appendix C - As-Built Submission Process Appendix D - Sample Temporary Title Block Locations Appendix E - Overlapping Design Agreement Application Appendix F - Overlapping Design Agreement Design Transfer Log PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 9 of 15

10 Appendix A - Flowchart of Overlapping Design Process PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 10 of 15

11 Appendix B - Interim Maintenance Distribution Process PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 11 of 15

12 Appendix C As-Built Submission Process PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 12 of 15

13 Appendix D Sample Temporary Title Block Locations OR PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 13 of 15

14 Appendix E Overlapping Design Agreement Application OVERLAPPING DESIGN APPLICATION The following parties agree to facilitate for Overlapping Designs. Overlapping Designs are defined as designs that require multiple contractors to modify for the same project. Reason for the Overlapping Design Agreement : The Drawing Controller who will book out the Engineering Designs shall be: Name Phone Number Signature Drawing Controller: Organisation: The Responsible Overlapping Design Engineer (RODE) shall be: Responsible Overlapping Design Engineer Organisation: Name Phone Number Signature The RODE will be required to coordinate and track all movements related to the affected Engineering Designs between differing contractors. It is the RODE's responsibility to ensure that integrity of the designs are preserved. The Primary Contractor that will provide have the Engineering Designs booked to shall be: Responsible Design Engineer Name Phone Number Signature Organisation The Primary Contractor must provide the final designs incorporating all related Contractors design modifications and comments. It is the Primary Contractors responsibility to return the plans to DMS compliance The Secondary Contractor(s) shall be: Name Phone Number Signature Responsible Design Engineer Organisation (1) Responsible Design Engineer Organisation (2) (Delete if not required) Responsible Design Engineer Organisation (3) (Delete if not required) The Secondary Contractor will not have the designs booked under their name, yet require modifications to the designs for the same project. The Following Engineering Designs will be undertaken via an Overlapping Design methodology Title File Name Drawing Number Revision Location PTV DMS Dispensation Number (if any) : Attached to this application shall be the Start Up meeting minutes and Risk Register PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 14 of 15

15 Appendix F Overlapping Design Agreement Design Transfer Log OVERLAPPING DESIGN DESIGN TRANSFER LOG # Vault New / Existing File Name Drawing Number Title Drawing Revision Location Name Drawing Controller Primary Contractor Secondary Contractor Date of Request Date of Transfer From Transfer To Reason for Design Change Designs Received Name Company Name Company # Overlapping Design Agreement Design Transfer Log to be maintained by RODE for record and keeping track of the status of drawings PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 15 of 15

ENGINEERING DRAWINGS MANAGEMENT POLICY (IFC/AS BUILTS)

ENGINEERING DRAWINGS MANAGEMENT POLICY (IFC/AS BUILTS) Approval Amendment Record Approval Date Version Description 15/10/2015 1 This policy takes precedence over L1-NAM-PRO-003 Infrastructure As Built Drawing Management due to business restructures. New Content

More information

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN Approval Amendment Record Approval Date Version Description 01/04/2014 1 Initial Issue under MTM PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 7 Table of Contents

More information

TYPE APPROVAL PROCEDURE

TYPE APPROVAL PROCEDURE Approval Amendment Record Approval Date Version Description 15/06/2012 1 Initial issue under MTM. Replaces Connex documents cml- 8.13-PR-002 & cml-8.21-po-168 30/11/2012 2 Document revised and updated

More information

Earthing Requirements for HV Transmission Structures

Earthing Requirements for HV Transmission Structures Engineering Standard Electrical MEST 000002-07 Earthing Requirements for Transmission Structures Version: 1 Issued: February 2015 Owner: Engineering Approved By: Patrick Kelly Head of Electrical Engineering

More information

Drawing Management Standard

Drawing Management Standard Record Number: R0000393979 Version Number: 1.0 Date: December 2015 Authorisations Action Name and title Date Prepared by TasNetworks 23/12/2015 Reviewed by David King With input from Rick Stevens, Jeshua

More information

For the purposes of this document, the Engineering Consultant shall be referred to as the Engineer.

For the purposes of this document, the Engineering Consultant shall be referred to as the Engineer. SPEC-0002 1/8 1.0 PURPOSE This specification describes the requirements and procedure for requesting new drawing numbers, requesting drawing files for revision, and submitting drawings for archiving. This

More information

Herts Valleys Clinical Commissioning Group. Review of NHS Herts Valleys CCG Constitution

Herts Valleys Clinical Commissioning Group. Review of NHS Herts Valleys CCG Constitution Herts Valleys Clinical Commissioning Group Review of NHS Herts Valleys CCG s constitution Agenda Item: 14 REPORT TO: HVCCG Board DATE of MEETING: 30 January 2014 SUBJECT: Review of NHS Herts Valleys CCG

More information

ELECTRICAL NETWORKS SPECIFICATION TECHNICAL SPECIFICATION FOR A 230V/110V AND 400V/110V TRANSFORMER

ELECTRICAL NETWORKS SPECIFICATION TECHNICAL SPECIFICATION FOR A 230V/110V AND 400V/110V TRANSFORMER Approval Amendment Record Approval Date Version Description 03/05/2017 1 Initial issue PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 13 Table of Contents 1. Purpose...

More information

1 SERVICE DESCRIPTION

1 SERVICE DESCRIPTION DNV GL management system ICP Product Certification ICP 4-6-3-5-CR Document number: ICP 4-6-3-5-CR Valid for: All in DNV GL Revision: 2 Date: 2017-05-05 Resp. unit/author: Torgny Segerstedt Reviewed by:

More information

MESP TECHNICAL SPECIFICATION FOR AN ESSENTIAL SERVICES SUPPLY STEP UP TRANSFORMER

MESP TECHNICAL SPECIFICATION FOR AN ESSENTIAL SERVICES SUPPLY STEP UP TRANSFORMER Engineering Specification TECHNICAL SPECIFICATION FOR AN ESSENTIAL Version: 3 Issued: 14 October 2016 Owner: Chief Engineer Approved By: Andrew Russack Head of Engineering - Electrical PRINTOUT MAY NOT

More information

DESIGN PRACTICE NOTE GENERAL OCS SPECIFICATION UPDATE

DESIGN PRACTICE NOTE GENERAL OCS SPECIFICATION UPDATE Approval Amendment Record Approval Date Version Description 22/03/2017 1 Initial Issue PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 11 Table of Contents 1. Purpose...

More information

Statement on variation of 900 MHz and 1800 MHz Wireless Telegraphy Act licences

Statement on variation of 900 MHz and 1800 MHz Wireless Telegraphy Act licences Statement on variation of 900 MHz and 1800 MHz Wireless Telegraphy Act licences Statement Publication date: 06 January 2011 Contents Section Page 1 Executive summary 1 2 Introduction 2 3 Assessment of

More information

Signalling Documentation and Drawings

Signalling Documentation and Drawings Discipline: Engineering (Signalling) Category: Standard Signalling Documentation and Drawings SCP 06 Applicability New South Wales CRIA (NSW CRN) Primary Source RIC Standard SC 00 23 00 00 SP Version 3.0

More information

Electrical Procedure No E032. Procedure No: ELE 032

Electrical Procedure No E032. Procedure No: ELE 032 Procedure No: ELE 032 Procedure Title: Date of Procedure: Responsible Person(s) Safety Isolation of Low Voltage Networks and Systems for work to be carried out by third parties. i.e. Non University personnel.

More information

WP197 Capacity Market Metering Test

WP197 Capacity Market Metering Test WP197 Capacity Market Metering Test EMRS Working Practice Public Version: 4.0 Date: 20 July 2018 Table of Contents Change Amendment Record 4 1. Introduction 5 1.1 Scope and Purpose 5 1.2 Main Users and

More information

CHAPTER 14: TRAFFIC SIGNAL STANDARDS Introduction and Goals Administration Standards Standard Attachments 14.

CHAPTER 14: TRAFFIC SIGNAL STANDARDS Introduction and Goals Administration Standards Standard Attachments 14. 14.00 Introduction and Goals 14.01 Administration 14.02 Standards 14.03 Standard Attachments 14.1 14.00 INTRODUCTION AND GOALS The purpose of this chapter is to outline the City s review process for traffic

More information

MESP TECHNICAL SPECIFICATION FOR AN AUXILIARY OR ESSENTIAL SERVICES AND AUXILIARY TRANSFORMER FOR USE IN A RAILWAY SUBSTATION

MESP TECHNICAL SPECIFICATION FOR AN AUXILIARY OR ESSENTIAL SERVICES AND AUXILIARY TRANSFORMER FOR USE IN A RAILWAY SUBSTATION Engineering Specification Head of Electrical Engineering MESP 050100-01 TECHNICAL SPECIFICATION FOR AN AUXILIARY OR ESSENTIAL SERVICES AND AUXILIARY TRANSFORMER FOR USE IN A RAILWAY SUBSTATION Version:

More information

Fiscal 2007 Environmental Technology Verification Pilot Program Implementation Guidelines

Fiscal 2007 Environmental Technology Verification Pilot Program Implementation Guidelines Fifth Edition Fiscal 2007 Environmental Technology Verification Pilot Program Implementation Guidelines April 2007 Ministry of the Environment, Japan First Edition: June 2003 Second Edition: May 2004 Third

More information

Section Meetings Section Material and Equipment. None Required

Section Meetings Section Material and Equipment. None Required January 2000 Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK PART 2 PRODUCTS The General Conditions of the Contract, General Requirements and Supplemental

More information

The Corporation of the City of Nelson Office of the Finance and Purchasing Manager Telephone : (250) Fax : (250)

The Corporation of the City of Nelson Office of the Finance and Purchasing Manager Telephone : (250) Fax : (250) The Office of the Finance and Purchasing Manager Telephone : (250) 352-8204 Fax : (250) 352-6594 REQUEST FOR PREQUALIFICATIONS RADIO COMMUNICATIONS INFRASTRUCTURE UPGRADE CONTRACTOR SERVICES 2018-PRQ-01

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM TECHNICAL MEMORANDUM Design Submittal and Review Protocol In-progress and Draft 15% Design Submittals TM 0.7 Prepared by: Signed document on file 4 Jun 2009 Ken Jong, PE, Engineering Manager Date Checked

More information

Specification For. Asset Information Pr8701

Specification For. Asset Information Pr8701 Specification For Asset Pr8701 Written Direction Control Document Sponsor Document Owner Subject Matter Expert References Infrastructure Technical Standards Committee Manager, Capital Delivery, SIS Network

More information

SATELLITE NETWORK NOTIFICATION AND COORDINATION REGULATIONS 2007 BR 94/2007

SATELLITE NETWORK NOTIFICATION AND COORDINATION REGULATIONS 2007 BR 94/2007 BR 94/2007 TELECOMMUNICATIONS ACT 1986 1986 : 35 SATELLITE NETWORK NOTIFICATION AND COORDINATION ARRANGEMENT OF REGULATIONS 1 Citation 2 Interpretation 3 Purpose 4 Requirement for licence 5 Submission

More information

Definition of Bulk Electric System Phase 2

Definition of Bulk Electric System Phase 2 Definition of Bulk Electric System Phase 2 NERC Industry Webinar Peter Heidrich, FRCC, Standard Drafting Team Chair June 26, 2013 Topics Phase 2 - Definition of Bulk Electric System (BES) Project Order

More information

Level 1 VRQ Qualifications in Photo Imaging (7512) Assessment pack

Level 1 VRQ Qualifications in Photo Imaging (7512) Assessment pack Level 1 VRQ Qualifications in Photo Imaging (7512) Assessment pack www.cityandguilds.com May 2012 Version 1.1 About City & Guilds City & Guilds is the UK s leading provider of vocational qualifications,

More information

(Non-legislative acts) DECISIONS

(Non-legislative acts) DECISIONS 4.12.2010 Official Journal of the European Union L 319/1 II (Non-legislative acts) DECISIONS COMMISSION DECISION of 9 November 2010 on modules for the procedures for assessment of conformity, suitability

More information

Consultation on Amendments to Industry Canada s Antenna Tower Siting Procedures

Consultation on Amendments to Industry Canada s Antenna Tower Siting Procedures February 2014 Consultation on Amendments to Industry Canada s Antenna Tower Siting Procedures Aussi disponible en français Contents 1. Intent... 1 2. Mandate... 1 3. Policy... 1 4. Background... 1 5. Review

More information

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014)

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014) DRAFT UFGS- 01 XX XX (FEB 2014) ------------------------ Drafting Activity: USACE UNIFIED FACILITIES GUIDE SPECIFICATION SECTION TABLE OF CONTENTS DIVISION 01 GENERAL REQUIREMENTS SECTION 01 XX XX (FEB

More information

2. As such, Proponents of Antenna Systems do not require permitting of any kind from the Town.

2. As such, Proponents of Antenna Systems do not require permitting of any kind from the Town. Subject: Antenna Systems Policy Number: Date Developed: 2008/09 Date Approved: April 8, 2009 Lead Department: Planning and Development Date Modified: (if applicable) November 26, 2014 A. PROTOCOL STATEMENT:

More information

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 013300 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

Road signs Specifications

Road signs Specifications AS 1743:2018 AS 1743:2018 Road signs Specifications This Australian Standard was prepared by Committee MS-012, Road Signs and Traffic Signals. It was approved on behalf of the Council of Standards Australia

More information

Intimate Communications Hub Interface Specification Report to Secretary of State

Intimate Communications Hub Interface Specification Report to Secretary of State Intimate Communications Hub Interface Specification Report to Secretary of State DCC V1.0 28/02/14 Page 1 of 14 Executive Summary 1. DCC is required in accordance with the terms of its Licence to produce,

More information

AS/NZS :2014

AS/NZS :2014 AS/NZS 4024.1100:2014 Australian/New Zealand Standard Safety of machinery Part 1100: Application guide AS/NZS 4024.1100:2014 AS/NZS 4024.1100:2014 This joint Australian/New Zealand standard was prepared

More information

Control Command & Signalling. Standards Brief Sept Professional Head [S&C] 11/11/2014

Control Command & Signalling. Standards Brief Sept Professional Head [S&C] 11/11/2014 Control Command & Signalling Standards Brief Sept 2014 Professional Head [S&C] 11/11/2014 1 General This presentation gives headline details of the September 2014 Signalling Standards Brief It contains

More information

Working Drawing Manual

Working Drawing Manual Working Drawing Manual 2012 Table of Contents Section 1 Working Drawing Types... 1 1.1 General... 1 Section 2 Processing Steps... 1 2.1 Project Manager... 1 2.2 Engineering Document Unit... 2 2.3 Contractor...

More information

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Coordination. B. Preconstruction meeting. C. Progress meetings. D. Preinstallation conferences. E. Requests for information (RFI). F. Coordination drawings.

More information

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES DIVISION 1 GENERAL REQUIREMENTS SECTION 01 33 00 PART 1 - GENERAL 1.1 SUMMARY A. This section includes administrative and procedural requirements for submittals required for performance of the work, including

More information

UK Film Council Strategic Development Invitation to Tender. The Cultural Contribution of Film: Phase 2

UK Film Council Strategic Development Invitation to Tender. The Cultural Contribution of Film: Phase 2 UK Film Council Strategic Development Invitation to Tender The Cultural Contribution of Film: Phase 2 1. Summary This is an Invitation to Tender from the UK Film Council to produce a report on the cultural

More information

Procedures for the management of satellite network filings

Procedures for the management of satellite network filings Procedures for the management of satellite network filings Reference: MCA/O/16-2656 Publication Date: 28 December 2016 Valletta Waterfront, Pinto Wharf, Floriana FRN1913, Malta. Tel: (+356) 2133 6840 Fax:

More information

Governing Council. Inventions Policy. October 30, 2013

Governing Council. Inventions Policy. October 30, 2013 University of Toronto Governing Council Inventions Policy October 30, 2013 To request an official copy of this policy, contact: The Office of the Governing Council Room 106, Simcoe Hall 27 King s College

More information

L1-CHE-SPE-273 SIGNALLING AND COMMUNICATIONS CABLE APPLICATION GUIDELINES

L1-CHE-SPE-273 SIGNALLING AND COMMUNICATIONS CABLE APPLICATION GUIDELINES Engineering Specification Signalling L1-CHE-SPE-273 SIGNALLING AND COMMUNICATIONS CABLE APPLICATION GUIDELINES Version: 1 ENGINEERING SPECIFICATION SIGNALLING AND COMMUNICATIONS CABLE APPLICATION GUIDELINES

More information

MINISTRY OF AGRICULTURE, LIVESTOCK & FISHERIES STATE DEPARTMENT OF FISHERIES AND BLUE ECONOMY

MINISTRY OF AGRICULTURE, LIVESTOCK & FISHERIES STATE DEPARTMENT OF FISHERIES AND BLUE ECONOMY MINISTRY OF AGRICULTURE, LIVESTOCK & FISHERIES STATE DEPARTMENT OF FISHERIES AND BLUE ECONOMY KENYA MARINE FISHERIES AND SOCIO-ECONOMIC DEVELOPMENT PROJECT (KEMFSED) TERMS OF REFERENCE For an Individual

More information

THE USE OF A SAFETY CASE APPROACH TO SUPPORT DECISION MAKING IN DESIGN

THE USE OF A SAFETY CASE APPROACH TO SUPPORT DECISION MAKING IN DESIGN THE USE OF A SAFETY CASE APPROACH TO SUPPORT DECISION MAKING IN DESIGN W.A.T. Alder and J. Perkins Binnie Black and Veatch, Redhill, UK In many of the high hazard industries the safety case and safety

More information

Estates Development & Projects

Estates Development & Projects Estates Development & Projects Production Guidelines for the Building Fabric Manual (incorporating Health & Safety File) Guidance for the Technical Author REVISION 10.2 Issue Date 09/2017 Contents Part

More information

Weather and Environmental Services - QMS Manual

Weather and Environmental Services - QMS Manual 1.0 SECTION ONE - INTRODUCTION 1.1 Purpose Reference.: Page 1 of 5 This process provides a new, changed or acquired off the shelf design, process, procedure, methodology or technology that addresses a

More information

New approach for lighting Regulations

New approach for lighting Regulations (Proposal for discussion to the members of GRE) New approach for lighting Regulations Why a new approach? UNECE/GRE Role: GRE manages 41 Regulations. Many of them use the same test requirements. Furthermore

More information

MEASURES TO INCREASE THE EFFICIENCY OF CIF COMMITTEES. CTF-SCF/TFC.11/7/Rev.1 January 27, 2014

MEASURES TO INCREASE THE EFFICIENCY OF CIF COMMITTEES. CTF-SCF/TFC.11/7/Rev.1 January 27, 2014 MEASURES TO INCREASE THE EFFICIENCY OF CIF COMMITTEES CTF-SCF/TFC.11/7/Rev.1 January 27, 2014 I. INTRODUCTION 1. At the May 2013 CIF Committee meetings, the CIF Administrative Unit was requested to give

More information

VCE Systems Engineering: Administrative information for Schoolbased Assessment in 2019

VCE Systems Engineering: Administrative information for Schoolbased Assessment in 2019 VCE Systems Engineering: Administrative information for Schoolbased Assessment in 2019 Units 3 and 4 School-assessed Task The School-assessed Task contributes 50 per cent to the study score and is commenced

More information

Delivery of Developer Funded Infrastructure A New Model

Delivery of Developer Funded Infrastructure A New Model A New Delivery Model for Developer Works Hunter Water has a clear role in supporting the delivery of the Government 2036 vision, as articulated in the recently released Hunter Regional Plan. In consultation

More information

Contents EUROPEAN UNION AGENCY FOR RAILWAYS. Accompanying Report Practical arrangements for safety certification ERA-REC-126/ACR V 1.

Contents EUROPEAN UNION AGENCY FOR RAILWAYS. Accompanying Report Practical arrangements for safety certification ERA-REC-126/ACR V 1. Contents 1. Executive summary... 3 2. Introduction... 4 2.1. Purpose and scope... 4 2.2. Background... 4 3. Workgroups... 5 4. Working method... 5 5. Content of the practical arrangements... 7 5.1. Objective...

More information

BG6 Design Framework for Building Services

BG6 Design Framework for Building Services BG6 Design Framework for Building Services Why? What? How? Martin Ronceray 01 Oct 2018 BSRIA Values 2 BSRIA Sustainable Construction Group 3 Why? The purpose 4 Purpose of BG6 Details of limitations not

More information

CARRA PUBLICATION AND PRESENTATION GUIDELINES Version April 20, 2017

CARRA PUBLICATION AND PRESENTATION GUIDELINES Version April 20, 2017 CARRA PUBLICATION AND PRESENTATION GUIDELINES Version April 20, 2017 1. Introduction The goals of the CARRA Publication and Presentation Guidelines are to: a) Promote timely and high-quality presentation

More information

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES STANDARD SPECIFICATIONS SECTION 01330 SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 DESCRIPTION A. Section includes general requirements and procedures related to preparation and transmittal of Submittals to

More information

SECTION ADMINISTRATIVE REQUIREMENTS

SECTION ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Progress meetings. D. Construction progress schedule. E. Coordination drawings. SECTION 013000

More information

CONSULTANT ACCREDITATION SCHEME WATER SUPPLY

CONSULTANT ACCREDITATION SCHEME WATER SUPPLY CONSULTANT ACCREDITATION SCHEME WATER SUPPLY DESIGN DRAWING CRITERIA AND CHECKLIST Produced by SA Water Reticulation Networks Jan 2015 Pg. 1 of 8 Jan 2015 Contact Information Details For both water design

More information

Art Display Policy SUBJECT: Policy No: Date: October 17, Revision Date: October Number of Pages: 7

Art Display Policy SUBJECT: Policy No: Date: October 17, Revision Date: October Number of Pages: 7 SUBJECT: Art Display Policy Policy No: 2016-20 Date: October 17, 2016 Revision Date: October 2020 Number of Pages: 7 PURPOSE: To establish the conditions and context within which Innisfil Public Library

More information

Table of Contents...2. Copyright notice...3 Disclaimer Introduction... 4

Table of Contents...2. Copyright notice...3 Disclaimer Introduction... 4 Public Record Office Victoria PROS 11/07 Capture Standard Specification 2 Digitisation: Image Requirements Version Number: 1.1 Issue Date: 01/01/2010 Expiry Date: 02/01/2015 State of Victoria 2009 Version

More information

DNVGL-CG-0214 Edition September 2016

DNVGL-CG-0214 Edition September 2016 CLASS GUIDELINE DNVGL-CG-0214 Edition September 2016 The content of this service document is the subject of intellectual property rights reserved by ("DNV GL"). The user accepts that it is prohibited by

More information

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS Page: 4-1 4.0 URD Process and Documentation Requirements 4.1 Process Steps The process of developing underground distribution facilities in a residential area consists of 10 major steps, which are summarized

More information

Consultation on the licensing of spectrum in the 800 MHz and 900 MHz bands

Consultation on the licensing of spectrum in the 800 MHz and 900 MHz bands Consultation on the licensing of spectrum in the 800 MHz and 900 MHz bands 22 October 2015 Contents 1. Introduction... 3 1.1 Request for spectrum in the 800MHz and 900MHz bands... 3 1.2 Consultation structure...

More information

RULES AND REGULATIONS. Title 58 - RECREATION PENNSYLVANIA GAMING CONTROL BOARD [58 PA. CODE CH. 525] Table Game Internal Controls

RULES AND REGULATIONS. Title 58 - RECREATION PENNSYLVANIA GAMING CONTROL BOARD [58 PA. CODE CH. 525] Table Game Internal Controls RULES AND REGULATIONS Title 58 - RECREATION PENNSYLVANIA GAMING CONTROL BOARD [58 PA. CODE CH. 525] Table Game Internal Controls The Pennsylvania Gaming Control Board (Board), under its general authority

More information

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia BULLETIN NO. 6 TO THE PLANS AND SPECIFICATIONS FOR JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia EwingCole Architects.Engineers.Interior Designers.Planners

More information

Radiocommunication Facility Review Protocol

Radiocommunication Facility Review Protocol Radiocommunication Facility Review Protocol 1.0 PURPOSE 1.1 The purpose of this protocol is to outline the guidelines and review process through which Radiocommunication Facilities are evaluated within

More information

NATS Swanwick. Interface Agreement. Owners: General Manager Swanwick. General Manager XXX

NATS Swanwick. Interface Agreement. Owners: General Manager Swanwick. General Manager XXX NATS Swanwick Interface Agreement between Swanwick And XXX Airport Owners: General Manager Swanwick General Manager XXX APPROVED BY Title Name Signature Date General Manager LTC Swanwick General Manager

More information

LICENCE. for WEB LINKS. Check if this document is current Find similar documents StandardsWatch (info and login) Visit our website

LICENCE. for WEB LINKS. Check if this document is current Find similar documents StandardsWatch (info and login) Visit our website LICENCE for Licensee: Date: Conditions of use: Click here for full conditions of Licence WEB LINKS Check if this document is current Find similar documents StandardsWatch (info and login) Visit our website

More information

00-General Drawings. Doc. no.: NA-00-STS002

00-General Drawings. Doc. no.: NA-00-STS002 Gæðaskjal (GSK) GSK-1773 Date of issue: 24.11.2016 Revision no.:2.0 Responsible: Einar Friðgeir Björnsson Editor: Rafn Magnús Jónsson 00-General Drawings Doc. no.: NA-00-STS002 This standard technical

More information

REPORT OF DIRECTOR OF CITY OPERATIONS AGENDA ITEM: 7 PORTFOLIO: TRANSPORT, PLANNING & SUSTAINABILITY (COUNCILLOR RAMESH PATEL)

REPORT OF DIRECTOR OF CITY OPERATIONS AGENDA ITEM: 7 PORTFOLIO: TRANSPORT, PLANNING & SUSTAINABILITY (COUNCILLOR RAMESH PATEL) CITY OF CARDIFF COUNCIL CYNGOR DINAS CAERDYDD CABINET MEETING: 14 JULY 2016 CARDIFF STATUE AND MONUMENT PROTOCOL REPORT OF DIRECTOR OF CITY OPERATIONS AGENDA ITEM: 7 PORTFOLIO: TRANSPORT, PLANNING & SUSTAINABILITY

More information

Demand Side Response Methodology (DSR) for Use after a Gas Deficit Warning (GDW) Background. Draft Business Rules

Demand Side Response Methodology (DSR) for Use after a Gas Deficit Warning (GDW) Background. Draft Business Rules Demand Side Response Methodology (DSR) for Use after a Gas Deficit Warning (GDW) Draft Business Rules Version 0.1 Following the broad consensus of Workgroup 0504 meeting 3 (WG3), held on the 10 September

More information

(A Sample Letter of Agreement for manuscript preparation) (Sample) Letter of Agreement

(A Sample Letter of Agreement for manuscript preparation) (Sample) Letter of Agreement lifewriters.ca Toll-free: 800.864.9152 Assisted memoirs, family stories, and corporate histories Email: info@lifewriters.ca (A Sample Letter of Agreement for manuscript preparation) Mr. John Doe 850 Eighth

More information

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER.

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER. SECTION 01300 - PART 1 - GENERAL 1.1 GENERAL A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER. B. Unless otherwise noted, within 14 days after the date of commencement as stated in

More information

Representation - Draft Modification Report UNC A 0636B 0636C 0636D Updating the parameters for the NTS Optional Commodity Charge

Representation - Draft Modification Report UNC A 0636B 0636C 0636D Updating the parameters for the NTS Optional Commodity Charge Representation - Draft Modification Report UNC 0636 0636A 0636B 0636C 0636D Updating the parameters for the NTS Optional Commodity Charge Responses invited by: 5pm on 14 June 2018 To: enquiries@gasgovernance.co.uk

More information

INTERNAL AUDIT DIVISION

INTERNAL AUDIT DIVISION INTERNAL AUDIT DIVISION Report Number: 2012-001 FINAL REPORT Review of Cobb County 800 MHz Operations February 3, 2012 Latona Thomas, CPA, Manager Barry Huff, Staff Auditor I Table of Contents Transmittal

More information

An interpretation of NHS England s Primary Care Co-commissioning: Regional Roadshows questions and answers Rachel Lea, Beds & Herts LMC Ltd

An interpretation of NHS England s Primary Care Co-commissioning: Regional Roadshows questions and answers Rachel Lea, Beds & Herts LMC Ltd An interpretation of NHS England s Primary Care Co-commissioning: Regional Roadshows questions and answers Rachel Lea, Beds & Herts LMC Ltd 2. Joint Commissioning Arrangements 2.1 One option for CCGs is

More information

https://www.icann.org/en/system/files/files/interim-models-gdpr-compliance-12jan18-en.pdf 2

https://www.icann.org/en/system/files/files/interim-models-gdpr-compliance-12jan18-en.pdf 2 ARTICLE 29 Data Protection Working Party Brussels, 11 April 2018 Mr Göran Marby President and CEO of the Board of Directors Internet Corporation for Assigned Names and Numbers (ICANN) 12025 Waterfront

More information

Air Monitoring Directive Chapter 9: Reporting

Air Monitoring Directive Chapter 9: Reporting Air Monitoring Directive Chapter 9: Reporting Version Dec 16, 2016 Amends the original Air Monitoring Directive published June, 1989 Title: Air Monitoring Directive Chapter 9: Reporting Number: Program

More information

PROFESSIONAL PHOTOGRAPHY SERVICES AND RELATED PRODUCTS 2019 LEGISLATIVE SESSION

PROFESSIONAL PHOTOGRAPHY SERVICES AND RELATED PRODUCTS 2019 LEGISLATIVE SESSION State of Nevada Legislative Counsel Bureau 401 S. Carson Street Carson City, NV 89701 775.684.6800 (Phone) 775.684.6600 (Fax) REQUEST FOR PROPOSAL for: PROFESSIONAL PHOTOGRAPHY SERVICES AND RELATED PRODUCTS

More information

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS DIVISION 1 - GENERAL REQUIREMENTS SECTION 01300 - SUBMITTALS PART 1 - GENERAL 1.1 STIPULATIONS A. The section "Special Requirements" forms a part of this section by this reference thereto and shall have

More information

Level 2 VRQ Qualifications in Photo Imaging (7512)

Level 2 VRQ Qualifications in Photo Imaging (7512) Level 2 VRQ Qualifications in Photo Imaging (7512) Assessment pack www.cityandguilds.com September 2012 Version 3.0 About City & Guilds City & Guilds is the UK s leading provider of vocational qualifications,

More information

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules. 45-day Formal Comment Period with Initial Ballot June July 2014

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules. 45-day Formal Comment Period with Initial Ballot June July 2014 Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

The following draft Agreement supplements, but does not replace, the MOU by and between the Bureau of Land Management (BLM) and the California

The following draft Agreement supplements, but does not replace, the MOU by and between the Bureau of Land Management (BLM) and the California The following draft Agreement supplements, but does not replace, the MOU by and between the Bureau of Land Management (BLM) and the California Department of Fish and Wildlife (CDFW), which was entered

More information

Primary IVF Conditions for Registration For Assisted Reproductive Treatment Providers under the Assisted Reproductive Treatment Act 2008

Primary IVF Conditions for Registration For Assisted Reproductive Treatment Providers under the Assisted Reproductive Treatment Act 2008 Primary IVF Conditions for Registration For Assisted Reproductive Treatment Providers under the Assisted Reproductive Treatment Act 2008 Effective: 1 June 2018 Contents SECTION 1: Background... 3 SECTION

More information

Privacy Policy SOP-031

Privacy Policy SOP-031 SOP-031 Version: 2.0 Effective Date: 18-Nov-2013 Table of Contents 1. DOCUMENT HISTORY...3 2. APPROVAL STATEMENT...3 3. PURPOSE...4 4. SCOPE...4 5. ABBREVIATIONS...5 6. PROCEDURES...5 6.1 COLLECTION OF

More information

RESOLUTION MEPC.290(71) (adopted on 7 July 2017) THE EXPERIENCE-BUILDING PHASE ASSOCIATED WITH THE BWM CONVENTION

RESOLUTION MEPC.290(71) (adopted on 7 July 2017) THE EXPERIENCE-BUILDING PHASE ASSOCIATED WITH THE BWM CONVENTION RESOLUTION MEPC.290(71) (adopted on 7 July 2017) RESOLUTION MEPC.290(71) (adopted on 7 July 2017) ANNEX 12 RESOLUTION MEPC.290(71) (adopted on 7 July 2017) MEPC 71/17/Add.1 Annex 12, page 1 THE MARINE

More information

Herefordshire CCG Patient Choice and Resource Allocation Policy

Herefordshire CCG Patient Choice and Resource Allocation Policy Reference number HCCG0004 Last Revised January 2017 Review date February 2018 Category Corporate Governance Contact Lynne Renton Deputy Chief Nurse Who should read this All staff responsible for drawing

More information

REVISIONS LTR DESCRIPTION DATE (YR-MO-DA) APPROVED. A Drawing updated to reflect current requirements. gt R. Monnin

REVISIONS LTR DESCRIPTION DATE (YR-MO-DA) APPROVED. A Drawing updated to reflect current requirements. gt R. Monnin REVISIONS LTR DESCRIPTION DATE (YR-MO-DA) APPROVED A Drawing updated to reflect current requirements. gt 03-04-04 R. Monnin Drawing updated to reflect current MIL-PRF-38535 requirements. - ro 12-03-15

More information

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

A. Action Submittals: Written and graphic information that requires Architect's responsive action. SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

PEDIGREE Publication Policy & Procedures

PEDIGREE Publication Policy & Procedures PEDIGREE Publication Policy & Procedures Table of Contents 1 PUBLICATION PRINCIPLES 2 2 PUBLICATION PROCEDURE 2 2.1 WRITING: PRELIMINARY NEGOTIATIONS 2 2.2 SUBMISSION OF MANUSCRIPT 2 2.3 ACKNOWLEDGMENTS

More information

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

PATENT AND LICENSING POLICY SUMMARY

PATENT AND LICENSING POLICY SUMMARY PATENT AND LICENSING POLICY SUMMARY Policy II-260 OBJECTIVE To define and outline the policy of the British Columbia Cancer Agency and the British Columbia Cancer Foundation concerning the development

More information

Task on the evaluation of the plasma response to the ITER ELM stabilization coils in ITER H- mode operational scenarios. Technical Specifications

Task on the evaluation of the plasma response to the ITER ELM stabilization coils in ITER H- mode operational scenarios. Technical Specifications Task on the evaluation of the plasma response to the ITER ELM stabilization coils in ITER H- mode operational scenarios Technical Specifications Version 1 Date: 28/07/2011 Name Affiliation Author G. Huijsmans

More information

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

AS/NZS 1200:2000 AS/NZS

AS/NZS 1200:2000 AS/NZS AS/NZS 1200:2015 Australian/New Zealand Standard Pressure equipment Superseding AS/NZS 1200:2000 AS/NZS 1200:2015 AS/NZS 1200:2015 This joint Australian/New Zealand standard was prepared by joint Technical

More information

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES Issue 9: May 2013 National Grid National Grid Registered Office National Grid Electricity Transmission plc Registered Office: 1-3 Strand London

More information

Patient Choice and Resource Allocation Policy. NHS South Warwickshire Clinical Commissioning Group (the CCG)

Patient Choice and Resource Allocation Policy. NHS South Warwickshire Clinical Commissioning Group (the CCG) Patient Choice and Resource Allocation Policy (the CCG) Accountable Director: Alison Walshe Director of Quality and Performance Policy Author: Sheila Browning Associate Director Continuing Healthcare Approved

More information

THE UNIVERSITY OF AUCKLAND INTELLECTUAL PROPERTY CREATED BY STAFF AND STUDENTS POLICY Organisation & Governance

THE UNIVERSITY OF AUCKLAND INTELLECTUAL PROPERTY CREATED BY STAFF AND STUDENTS POLICY Organisation & Governance THE UNIVERSITY OF AUCKLAND INTELLECTUAL PROPERTY CREATED BY STAFF AND STUDENTS POLICY Organisation & Governance 1. INTRODUCTION AND OBJECTIVES 1.1 This policy seeks to establish a framework for managing

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION PROJECT MEETINGS

2016 CDM Smith All Rights Reserved July 2016 SECTION PROJECT MEETINGS PART 1 GENERAL 1.01 REQUIREMENTS INCLUDED SECTION 01 20 00 PROJECT MEETINGS A. Construction Manager shall schedule and administer pre-construction meeting, periodic progress meetings, and specially called

More information

Investigation i of potentially contaminated sites - Code of Practice. Richard Owen Ove Arup & Partners Limited

Investigation i of potentially contaminated sites - Code of Practice. Richard Owen Ove Arup & Partners Limited The proposed changes to BS10175 Investigation i of potentially contaminated sites - Code of Practice Richard Owen Ove Arup & Partners Limited CONTENT OF THE PRESENTATION Background and Objectives Revision

More information

Measurement of Signalling Distances

Measurement of Signalling Distances Division / Business Unit: Function: Document Type: Enterprise Services Signalling Standard Measurement of Signalling Distances Applicability ARTC Network Wide SMS Publication Requirement Internal / External

More information

Guidelines. Guidelines to Applicants Wireless Public Address System Licences. Document No: 05/17R1 Date: 10 May 2017

Guidelines. Guidelines to Applicants Wireless Public Address System Licences. Document No: 05/17R1 Date: 10 May 2017 Guidelines Guidelines to Applicants Wireless Public Address System Licences Document No: 05/17R1 Date: 10 May 2017 An Coimisiún um Rialáil Cumarsáide Commission for Communications Regulation 1 Dockland

More information

CITY OF RICHMOND SUBDIVISION PLAT AND PUBLIC INFRASTRUCTURE SUBMITTAL, REVIEW AND APPROVAL PROCEDURES

CITY OF RICHMOND SUBDIVISION PLAT AND PUBLIC INFRASTRUCTURE SUBMITTAL, REVIEW AND APPROVAL PROCEDURES SUBDIVISION PLAT AND PUBLIC INFRASTRUCTURE SUBMITTAL, REVIEW AND APPROVAL PROCEDURES CITY OF RICHMOND 112 JACKSON STREET RICHMOND, TEXAS 77469 PHONE: 281-232-6871 FAX: 281-238-1215 CITY OF RICHMOND PUBLIC

More information