1 FX-70 Epoxy Method Installation Guide Timber Pile Steel Pile Concrete Pile 1300 STRONGTIE

2 Timber Pile-Epoxy Method I: Surface Preparation 1. Surface must be at least 4 C prior to application. 2. Consult a qualified engineer in cases when section loss exceeds 25 percent. 3. All wood surfaces to be covered with pile jackets shall be thoroughly cleaned of oil, grease, dirt, and any other deleterious material which would prevent proper bonding. 4. FX-70 jacket placement should not proceed until pile cleaning has been approved by the Engineer of Record or Owner s Representative. II: Jacket preparation: 1. All submerged jackets should be installed by certified professional divers. All jackets must be sealed appropriately to prevent grout leakage during installation. 2. FX-Spacers, standoffs and pumping ports are shipped unattached to be field installed. 3. FX-Spacers to be adhered to the inside of the jacket using an Simpson Strong-Tie recommended flexible adhesive suitable for bonding fibreglass to fibreglass. Please contact Simpson Strong-Tie for further details. 4. Installation and positioning of FX-Spacers and/or Pumping Ports is unique to each application. III: Jacket positioning: 1. Prepare a cartridge of FX-763 Low-Modulus Trowel-Grade Epoxy per manufacturer s published instructions and place a bead of epoxy into the female portion of the tongue-and-groove joint. 2. Spread jacket open and place around pile. 3. Allow jacket to return to original shape engaging interlocking joint and secure with ratchet straps if necessary. 4. Set jacket at proper elevation positioning jacket so there is minimum 46 cm of undamaged pile inside the jacket above and below the damaged area. 5. To secure the interlocking joint, install self-drilling, self-tapping type-316 stainless steel screws into the tongue-and-groove joint every 15 cm on centre. 6. Install external bracing. 7. Install FX-Backer Rod to create a temporary bottom seal; bottom seal may be installed prior to placing jacket. 8. If using a compactible fill material, a temporary bottom seal may not be necessary, contact Simpson Strong-Tie for more information 2 Simpson Strong Tie FX70-AU17-EPOXYMETHODS-IG 2017 Simpson Strong Tie Company Inc.

3 Timber Pile-Epoxy Method IV: FX-70-6MP Multi-Purpose Marine Epoxy Grout: 1. Prepare FX-70-6MP per manufacturer s published instructions: a. For optimal product performance, condition individual components to 21 C and stir liquid components thoroughly prior to use. Proportion Component A and Component B at a 2A:1B ratio by volume in a clean pail. Mix thoroughly with a low-speed ( rpm) drill and mixing paddle for 2 3 minutes, scraping unmixed material from sides and bottom of mixing container as needed, taking care to prevent air entrapment. Continue mixing, and slowly add Component C to avoid clumping at a rate of kg per 11.4 L unit of epoxy, scraping the sides and bottom as needed. Mix for approximately 2 3 minutes or until a uniform consistency is achieved. *For mixing in a 20 L pail, combine 3.8 L of Component A and 1.9 L of Component B in a clean mixing vessel with a slow-speed ( rpm) drill and mixing paddle for a minimum of 2 minutes. While continuing to mix, slowly add (1) 22.7 kg bag of FX-70-6 MP C Component, scraping sides and bottom of pail as needed to ensure thorough mixing. Mix until FX-70-6 MP C Component is fully wetted and a uniform consistency is achieved. V: Bottom Seal Application: 1. Mix FX-70-6MP per manufacturer s published instructions (refer to section IV). 2. Place FX-70-6MP into the bottom 15 cm of the annular void by pouring or pumping. 3. If pouring, a specially fabricated funnel or flexible traffic cone may be helpful. 4. Allow seal to cure in accordance with published cure schedule before proceeding with repair. VI: Filler Grout Application 1. Mix FX-70-6MP per manufacturer s published instructions. Grout may be poured, pumped, or placed by tremie method. 2. To pour: a. FX-70-6MP can be poured from the top of jacket through standing water. 3. For tremie applications: a. Ensure the hose extends to the bottom of the jacket. Fill the jacket until the grout reaches the top of the jacket, allowing water to displace from the top of the jacket. Depending on the depth of the pour and size of the jacket, the tremie hose may need to be retracted as the jacket fills to maintain flow. 4. To pump: a. Contact Simpson Strong-Tie for injection port installation instructions suitable for your application. b. Begin by pumping FX-70-6MP into the lowest port. Grout shall be continuously injected until the grout reaches the top of the jacket. c. At the Contractor s option, multiple levels of grout ports may be installed to minimize the pumping pressure. For this method, injection shall begin at the lowest port and continue until the grout appears at the port above the injected port. When this occurs, close the injected port and continue injection at the port where grout appears. The injection process shall be continuous, except for brief interruptions when the injector is moved from port to port, until the grout reaches the top of the jacket. FX70-AU17-EPOXYMETHODS-IG 2017 Simpson Strong Tie Company Inc. Simpson Strong Tie 3

4 Timber Pile-Epoxy Method VII: Epoxy Bevel Construction: Prior to bevel installation, allow FX-70-6MP Multi-Purpose Marine Epoxy Grout to set for a minimum of 6 hours at 21 C. 1. Prepare FX-763 Trowel-Grade Epoxy Mortar per manufacturer s published instructions: a. For optimal product performance, condition individual components to 21 C. Proportion Component A and Component B at a 2A:1B ratio by volume in a clean pail. Mix thoroughly with a low-speed ( rpm) drill and mixing paddle for 2 3 minutes, scraping unmixed material from sides and bottom of mixing container as needed, taking care to prevent air entrapment. Continue mixing, and slowly add one part FX-701 filler by volume per part of mixed epoxy, scraping the sides and bottom as needed. Mix for approximately 2 3 minutes or until FX-701 is thoroughly wetted. 2. Immediately construct bevel with FX-763, taking care to construct slope which will not allow water to pond. VIII: Completion of work: 1. Remove external bracing after all materials have fully cured in accordance with published cure schedules. 2. Clean exterior surfaces of jackets of any filler material or other extraneous material deposited on the pile jackets. IX: Suggested tool list: 1. Equipment to properly prepare the pile surface chosen by contractor and Engineer of Record 2. PPE gloves, safety glasses, respirators etc. 3. Generator 4. EDT22S manual dispensing tool 5. Ratchet straps 6. Small drill and hex tex adapter to set self-tapping stainless steel screws in interlocking joint. 7. Slow-speed mixing drill and mixing paddle 8. Clean measuring vessels 9. Clean 20 litre buckets for mixing 10. Mortar Mixer (stationary drum with moving blades) 11. Pump equipment (Please contact Simpson Strong-Tie for further information) 12. Various hand tools shovel, hammer, trowels etc. 4 Simpson Strong Tie FX70-AU17-EPOXYMETHODS-IG 2017 Simpson Strong Tie Company Inc.

5 Steel Pile Epoxy Method I: Surface Preparation 1. Surface must be at least 4 C prior to application. 2. Consult a qualified engineer in cases when section loss exceeds 25 percent. 3. All steel surfaces to be covered with pile jackets shall be thoroughly cleaned of oil, grease, dirt, and any other deleterious material which would prevent proper bonding. 4. Prepare surface by sandblasting, wet blasting, wire brushing, water laser, or other approved method(s). 5. FX-70 jacket placement should not proceed until pile cleaning has been approved by the Engineer of Record or Owner s Representative. II: Jacket preparation: 1. All submerged jackets should be installed by certified professional divers. All jackets must be sealed appropriately to prevent grout leakage during installation. 2. FX-Spacers, standoffs and pumping ports are shipped unattached to be field installed. 3. FX-Spacers to be adhered to the inside of the jacket using an Simpson Strong-Tie recommended flexible adhesive suitable for bonding fibreglass to fibreglass. Please contact Simpson Strong-Tie for further details. 4. Installation and positioning of FX-Spacers and/or Pumping Ports is unique to each application III: Jacket positioning: 1. Prepare a cartridge of FX-763 Low-Modulus Trowel-Grade Epoxy per manufacturer s published instructions and place a bead of epoxy into the female portion of the tongue-and-groove joint. 2. Spread jacket open and place around pile. 3. Allow jacket to return to original shape engaging interlocking joint and secure with ratchet straps if necessary. 4. Set jacket at proper elevation positioning jacket so there is minimum 46 cm of undamaged pile inside the jacket above and below the damaged area. 5. To secure the interlocking joint, install self-drilling, self-tapping type-316 stainless steel screws into the tongue-and-groove joint every 15 cm on centre. 6. Install external bracing. 7. Install FX-Backer Rod to create a temporary bottom seal; bottom seal may be installed prior to placing jacket. If using a compactible fill material, a temporary bottom seal may not be necessary, contact Simpson Strong-Tie for more information. FX70-AU17-EPOXYMETHODS-IG 2017 Simpson Strong Tie Company Inc. Simpson Strong Tie 5

6 Steel Pile Epoxy Method IV: FX-70-6MP Multi-Purpose Marine Epoxy Grout: 1. Prepare FX-70-6MP per manufacturer s published instructions: a. For optimal product performance, condition individual components to 21 C and stir liquid components thoroughly prior to use. Proportion Component A and Component B at a 2A:1B ratio by volume in a clean pail. Mix thoroughly with a low-speed ( rpm) drill and mixing paddle for 2 3 minutes, scraping unmixed material from sides and bottom of mixing container as needed, taking care to prevent air entrapment. Continue mixing, and slowly add Component C to avoid clumping at a rate of kg per 11.4 L unit of epoxy, scraping the sides and bottom as needed. Mix for approximately 2 3 minutes or until a uniform consistency is achieved. *For mixing in a 20 L pail, combine 3.8 L of Component A and 1.9 L of Component B in a clean mixing vessel with a slow-speed ( rpm) drill and mixing paddle for a minimum of 2minutes. While continuing to mix, slowly add (1) 22.7 kg bag of FX-70-6 MP C Component, scraping sides and bottom of pail as needed to ensure thorough mixing. Mix until FX-70-6 MP C Component is fully wetted and a uniform consistency is achieved V: Bottom Seal Application: 1. Mix FX-70-6MP per manufacturer s published instructions (refer to section IV). 2. Place FX-70-6MP into the bottom 15 cm of the annular void by pouring or pumping. 3. If pouring, a specially fabricated funnel or flexible traffic cone may be helpful. 4. Allow seal to cure in accordance with published cure schedule before proceeding with repair. VI: Filler Grout Application 1. Mix FX-70-6MP per manufacturer s published instructions. Grout may be poured, pumped, or placed by tremie method. 2. To pour: a. FX-70-6MP can be poured from the top of jacket through standing water. 3. For tremie applications: a. Ensure the hose extends to the bottom of the jacket. Fill the jacket until the grout reaches the top of the jacket, allowing water to displace from the top of the jacket. Depending on the depth of the pour and size of the jacket, the tremie hose may need to be retracted as the jacket fills to maintain flow. 4. To pump: a. Contact Simpson Strong-Tie for injection port installation instructions suitable for your application. b. Begin by pumping FX-70-6MP into the lowest port. Grout shall be continuously injected until the grout reaches the top of the jacket. c. At the Contractor s option, multiple levels of grout ports may be installed to minimize the pumping pressure. For this method, injection shall begin at the lowest port and continue until the grout appears at the port above the injected port. When this occurs, close the injected port and continue injection at the port where grout appears. The injection process shall be continuous, except for brief interruptions when the injector is moved from port to port, until the grout reaches the top of the jacket. 6 Simpson Strong Tie FX70-AU17-EPOXYMETHODS-IG 2017 Simpson Strong Tie Company Inc.

7 Steel Pile Epoxy Method VII: Epoxy Bevel Construction: Prior to bevel installation, allow FX-70-6MP Multi-Purpose Marine Epoxy Grout to set for a minimum of 6 hours at 21 C. 1. Prepare FX-763 Trowel-Grade Epoxy Mortar per manufacturer s published instructions: a. For optimal product performance, condition individual components to 21 C. Proportion Component A and Component B at a 2A:1B ratio by volume in a clean pail. Mix thoroughly with a low-speed ( rpm) drill and mixing paddle for 2 3 minutes, scraping unmixed material from sides and bottom of mixing container as needed, taking care to prevent air entrapment. Continue mixing, and slowly add one part FX-701filler by volume per part of mixed epoxy, scraping the sides and bottom as needed. Mix for approximately 2 3 minutes or until FX-701 is thoroughly wetted. 2. Immediately construct bevel with FX-763, taking care to construct slope which will not allow water to pond. VIII: Completion of work: 1. Remove external bracing after all materials have fully cured in accordance with published cure schedules. 2. Clean exterior surfaces of jackets of any filler material or other extraneous material deposited on the pile jackets. IX: Suggested tool list: 1. Equipment to properly prepare the pile surface chosen by contractor and Engineer of Record 2. PPE gloves, safety glasses, respirators etc. 3. Generator 4. EDT22S manual dispensing tool 5. Ratchet straps 6. Small drill and hex tex adapter to set self-tapping stainless steel screws in interlocking joint. 7. Slow-speed mixing drill and mixing paddle 8. Clean measuring vessels 9. Clean 20 litre buckets for mixing 10. Mortar Mixer (stationary drum with moving blades) 11. Pump equipment (Please contact Simpson Strong-Tie for further information) 12. Various hand tools shovel, hammer, trowels etc. FX70-AU17-EPOXYMETHODS-IG 2017 Simpson Strong Tie Company Inc. Simpson Strong Tie 7

8 Concrete Pile Epoxy Method I: Surface Preparation 1. Surface must be at least 4 C prior to application. 2. Consult a qualified engineer in cases when section loss exceeds 25 percent. 3. All concrete surfaces to be covered with pile jackets shall be thoroughly cleaned of oil, grease, dirt, and any other deleterious material which would prevent proper bonding. 4. Prepare surface by high-pressure water blasting or other mechanical means. Repair or replace any reinforcing steel as determined by a qualified professional engineer. 5. FX-70 jacket placement should not proceed until pile cleaning has been approved by the Engineer of Record or Owner s Representative. II: Jacket preparation: 1. All submerged jackets should be installed by certified professional divers. All jackets must be sealed appropriately to prevent grout leakage during installation. 2. FX-Spacers, standoffs and pumping ports are shipped unattached to be field installed. 3. FX-Spacers to be adhered to the inside of the jacket using an Simpson Strong-Tie recommended flexible adhesive suitable for bonding fibreglass to fibreglass. Please contact Simpson Strong-Tie for further details. 4. Installation and positioning of FX-Spacers and/or Pumping Ports is unique to each application. III: Jacket positioning: 1. Prepare a cartridge of FX-763 Low-Modulus Trowel-Grade Epoxy per manufacturer s published instructions and place a bead of epoxy into the female portion of the tongue-and-groove joint. 2. Spread jacket open and place around pile. 3. Allow jacket to return to original shape engaging interlocking joint and secure with ratchet straps if necessary. 4. Set jacket at proper elevation positioning jacket so there is minimum 46 cm of undamaged pile inside the jacket above and below the damaged area. 5. To secure the interlocking joint, install self-drilling, self-tapping type-316 stainless steel screws into the tongue-and-groove joint every 15 cm on centre. 6. Install external bracing. 7. Install FX-Backer Rod to create a temporary bottom seal; bottom seal may be installed prior to placing jacket. If using a compactible fill material, a temporary bottom seal may not be necessary, contact Simpson Strong-Tie for more information 8 Simpson Strong Tie FX70-AU17-EPOXYMETHODS-IG 2017 Simpson Strong Tie Company Inc.

9 Concrete Pile Epoxy Method IV: FX-70-6MP Multi-Purpose Marine Epoxy Grout: 1. Prepare FX-70-6MP per manufacturer s published instructions: a. For optimal product performance, condition individual components to 21 C and stir liquid components thoroughly prior to use. Proportion Component A and Component B at a 2A:1B ratio by volume in a clean pail. Mix thoroughly with a low-speed ( rpm) drill and mixing paddle for 2 3 minutes, scraping unmixed material from sides and bottom of mixing container as needed, taking care to prevent air entrapment. Continue mixing, and slowly add Component C to avoid clumping at a rate of kg per 11.4 L unit of epoxy, scraping the sides and bottom as needed. Mix for approximately 2 3 minutes or until a uniform consistency is achieved. *For mixing in a 20 L pail, combine 3.8 L of Component A and 1.9 L of Component B in a clean mixing vessel with a slow-speed ( rpm) drill and mixing paddle for a minimum of 2minutes. While continuing to mix, slowly add (1) 22.7 kg bag of FX-70-6 MP C Component, scraping sides and bottom of pail as needed to ensure thorough mixing. Mix until FX-70-6 MP C Component is fully wetted and a uniform consistency is achieved. V: Bottom Seal Application: 1. Mix FX-70-6MP per manufacturer s published instructions (refer to section IV). 2. Place FX-70-6MP into the bottom 15 cm of the annular void by pouring or pumping. 3. If pouring, a specially fabricated funnel or flexible traffic cone may be helpful. 4. Allow seal to cure in accordance with published cure schedule before proceeding with repair. VI: Filler Grout Application 1. Mix FX-70-6MP per manufacturer s published instructions. Grout may be poured, pumped, or placed by tremie method. 2. To pour: a. FX-70-6MP can be poured from the top of jacket through standing water. 3. For tremie applications: a. Ensure the hose extends to the bottom of the jacket. Fill the jacket until the grout reaches the top of the jacket, allowing water to displace from the top of the jacket. Depending on the depth of the pour and size of the jacket, the tremie hose may need to be retracted as the jacket fills to maintain flow. 4. To pump: a. Contact Simpson Strong-Tie for injection port installation instructions suitable for your application. b. Begin by pumping FX-70-6MP into the lowest port. Grout shall be continuously injected until the grout reaches the top of the jacket. c. At the Contractor s option, multiple levels of grout ports may be installed to minimize the pumping pressure. For this method, injection shall begin at the lowest port and continue until the grout appears at the port above the injected port. When this occurs, close the injected port and continue injection at the port where grout appears. The injection process shall be continuous, except for brief interruptions when the injector is moved from port to port, until the grout reaches the top of the jacket. FX70-AU17-EPOXYMETHODS-IG 2017 Simpson Strong Tie Company Inc. Simpson Strong Tie 9

10 Concrete Pile Epoxy Method VII: Epoxy Bevel Construction: Prior to bevel installation, allow FX-70-6MP Multi-Purpose Marine Epoxy Grout to set for a minimum of 6 hours at 21ºC. 1. Prepare FX-763 Trowel-Grade Epoxy Mortar per manufacturer s published instructions: a. For optimal product performance, condition individual components to 21 C. Proportion Component A and Component B at a 2A:1B ratio by volume in a clean pail. Mix thoroughly with a low-speed ( rpm) drill and mixing paddle for 2 3 minutes, scraping unmixed material from sides and bottom of mixing container as needed, taking care to prevent air entrapment. Continue mixing, and slowly add one part FX-701 filler by volume per part of mixed epoxy, scraping the sides and bottom as needed. Mix for approximately 2 3 minutes or until FX-701 is thoroughly wetted. 2. Immediately construct bevel with FX-763, taking care to construct slope which will not allow water to pond. VIII: Completion of work: 1. Remove external bracing after all materials have fully cured in accordance with published cure schedules. 2. Clean exterior surfaces of jackets of any filler material or other extraneous material deposited on the pile jackets. with repair. IX: Suggested tool list: 1. Equipment to properly prepare the pile surface chosen by contractor and Engineer of Record 2. PPE gloves, safety glasses, respirators etc. 3. Generator 4. EDT22S manual dispensing tool 5. Ratchet straps 6. Small drill and hex tex adapter to set self-tapping stainless steel screws in interlocking joint. 7. Slow-speed mixing drill and mixing paddle 8. Clean measuring vessels 9. Clean 20 litre buckets for mixing 10. Mortar Mixer (stationary drum with moving blades) 11. Pump equipment (Please contact Simpson Strong-Tie for further information) 12. Various hand tools shovel, hammer, trowels etc. Simpson Strong-Tie Australia Pty Ltd 1 / 16 Kenoma Place Arndell Park NSW 2148 Phone: 1300 STRONGTIE ( ) Fax: Web: fx70.au@strongtie.com 10 Simpson Strong Tie FX70-AU17-EPOXYMETHODS-IG 2017 Simpson Strong Tie Company Inc.

11 Simpson Strong-Tie, is an international building products company based in California with multiple locations worldwide. Simpson Strong-Tie was founded in 1956 and has established itself as a trusted manufacturer of chemical, mechanical and direct-fastening solutions. The company is committed to helping customers succeed by providing exceptional code-listed products, full-service engineering and field support, product testing and training, and on-time product delivery. Simpson Strong-Tie continues to expand its offering to include a full array of concrete repair, protection and strengthening solutions. The innovative products within the guide are the result of more than 40 years of laboratory development, field study and contractor input, and have passed the rigorous performance and quality assurance testing you have come to expect from Simpson Strong-Tie. We look forward to working with you on your next project. This flyer is effective until April 30, 2019, and reflects information available as of April 1, This information is updated periodically and should not be relied upon after April 30, Contact Simpson Strong Tie for current information and limited warranty or see strongtie.com.au 2017 Simpson Strong Tie Company Inc. FX70-AU17-EPOXYMETHODS-IG 4/17 exp. 4/19 Call 1300 STRONGTIE ( )

Section 914. JOINT AND WATERPROOFING MATERIALS

Section 914. JOINT AND WATERPROOFING MATERIALS 914.01 Section 914. JOINT AND WATERPROOFING MATERIALS 914.01. General Requirements. Joint and waterproofing material for use in concrete construction must meet the requirements of this section. 914.02.

More information

PURE GP. Adhesives GENERAL INFORMATION SECTION CONTENTS. Epoxy Injection Adhesive Anchoring System

PURE GP. Adhesives GENERAL INFORMATION SECTION CONTENTS. Epoxy Injection Adhesive Anchoring System General Information GENERAL INFORMATION PURE GP Epoxy Injection Adhesive Anchoring System PRODUCT DESCRIPTION The Pure GP is a two-component adhesive anchoring system. The system includes injection adhesive

More information

Construction. Sika Grouting Systems. Properties of Grout. Grouting Considerations

Construction. Sika Grouting Systems. Properties of Grout. Grouting Considerations Machinery and equipment which have precise tolerances for alignment, or require uniform support, cannot be placed directly onto finished concrete surfaces. Both the concrete surface and the machine base

More information

1. INTRODUCTION 2. REFERENCE SPECIFICATIONS. Page -1- Bonding and Grouting

1. INTRODUCTION 2. REFERENCE SPECIFICATIONS. Page -1- Bonding and Grouting Page -1-1. INTRODUCTION 1.1 Scope This specification covers non-shrink and epoxy grouting of structural column base plates and equipment bases, Portland cement grout for minor elements and bonding agents

More information

CVO/169897A OCTOBER 29, GROUT

CVO/169897A OCTOBER 29, GROUT SECTION 03600 GROUT PART 1 GENERAL 1.1 REFERENCES A. The following is a list of standards which may be referenced in this section: 1.2 SUBMITTALS 1. ASTM International (ASTM): a. C230, Standard Specification

More information

PIVOT DOOR 3400P INSTALLATION INSTRUCTIONS

PIVOT DOOR 3400P INSTALLATION INSTRUCTIONS Table of Contents I. Tools, Sealant Requirements, Anchor Recommended Table...1 II. Opening, Frame & Panel Verification...2-3 III. Frame Assembly...4 IV. Frame Installation...5-7 V. Glazing Instructions...8

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION Sheet 1 of 7 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION SECTION 502 PORTLAND CEMENT CONCRETE PAVEMENT (NON-QC/QA) Page 500-20, subsection 502.2.

More information

SURFACE CASTING METHOD: For Molds & Core Boxes. Presented by: Hapco Inc.

SURFACE CASTING METHOD: For Molds & Core Boxes. Presented by: Hapco Inc. SURFACE CASTING METHOD: For Molds & Core Boxes Presented by: Hapco Inc. RAPIDFIL Detailed Specifications STEP 1 SPACER LAYER Apply a layer of ¼ foam to create a uniform ¼ thickness around the pattern.

More information

AMENDMENTS Manual of STANDARD SPECIFICATIONS. Adopted by Standard Specifications Committee. Amendment. No. 6. Published by

AMENDMENTS Manual of STANDARD SPECIFICATIONS. Adopted by Standard Specifications Committee. Amendment. No. 6. Published by AMENDMENTS to 2012 Manual of STANDARD SPECIFICATIONS Adopted by Standard Specifications Committee Amendment No. 6 Published by Utah LTAP Center Utah State University 8305 Old Main Hill Logan UT 84322-8205

More information

SPECTRALOCK PRO Premium Grout*

SPECTRALOCK PRO Premium Grout* SPECTRALOCK PRO Premium Grout* How to Grout TDS-1008 For most ceramic tile, glass tile, porcelain tile and natural stone Floors and walls Interior and exterior Residential and commercial Easy to Install,

More information

SERIES 3070-T MULTI-SLIDE ASSEMBLY & INSTALLATION INSTRUCTIONS

SERIES 3070-T MULTI-SLIDE ASSEMBLY & INSTALLATION INSTRUCTIONS Table of Contents I. Care and Maintenance...2 II. Tools / Material & Sealant Requirements...2 III. Assembly and Installation...2 IV. Glazing Assembly...3 V. Panel Assembly...3 1. X Panel...3 2. O Panel...4

More information

1. Architectural precast concrete cladding units.

1. Architectural precast concrete cladding units. SECTION 034500 - PRECAST ARCHITECTURAL CONCRETE PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Architectural precast concrete cladding units. 1.2 DEFINITION A. Design Reference

More information

PREMIUM CONCRETE COUNTERTOP MIX INSTALLATION INSTRUCTIONS

PREMIUM CONCRETE COUNTERTOP MIX INSTALLATION INSTRUCTIONS PREMIUM CONCRETE COUNTERTOP MIX INSTALLATION INSTRUCTIONS High Strength Fast Setting Pourable Helpful Items: TCC Materials February 09 Version 2.0 Tools Required: Concrete mixer or ½ drill (600 RPM or

More information

Aluminum Clad Wood Window 1/2 Reinforced Field Mulling and Stacking Supplement

Aluminum Clad Wood Window 1/2 Reinforced Field Mulling and Stacking Supplement Aluminum Clad Wood Window 1/2 Reinforced Field Mulling and Stacking Supplement 1 Aluminum Clad Wood Window 1/2 Reinforced Field Mulling and Stacking Supplement The following instructions are a supplement

More information

Hilti HIT-1 / HIT-1 CE Adhesive Anchor System

Hilti HIT-1 / HIT-1 CE Adhesive Anchor System Concrete Hilti HIT-1 / HIT-1 CE Adhesive Anchor System Injection mortar system Benefits Hilti HIT-1 / HIT-1 CE 300 ml foil tube cartridge Mixer HIT PM HIT-V rods Dispenser: - chemical injection fastening

More information

RELINER INSIDE DROP SYSTEM SPECIFICATIONS

RELINER INSIDE DROP SYSTEM SPECIFICATIONS 1. PRODUCT NAME RELINER INSIDE DROP SYSTEM U.S. Patent 6074130 Canadian Patent # 2269565 All RELINER Products are proudly made in the U.S.A. 2. MANUFACTURER RELINER /Duran Inc. 53 Mount Archer Rd. Lyme

More information

Silicoflex Joint Sealing System

Silicoflex Joint Sealing System Silicoflex Joint Sealing System SILICOFLEX GLAND ON WOODEN REEL P-200 Primer (A and B Components) Single Component Silicone Locking Adhesive Page 1 Preformed Silicone Gland Sizing Chart (5 Different Sizes)

More information

I n s t a l l a t i o n I n s t r u c t i o n s S E N T I N E L S E R I E S 1 50 SLIDING GLASS DOORS

I n s t a l l a t i o n I n s t r u c t i o n s S E N T I N E L S E R I E S 1 50 SLIDING GLASS DOORS I n s t a l l a t i o n I n s t r u c t i o n s S E N T I N E L S E R I E S 1 50 SLIDING GLASS DOORS Page 2-9: Installation Instructions, Figures 1, 2, & 3 Page 10-12: Figures A-1, A-2, & A-3: Installation

More information

SECTION MASONRY ANCHORAGE AND REINFORCEMENT. Display hidden notes to specifier. (Don't know how? Click Here)

SECTION MASONRY ANCHORAGE AND REINFORCEMENT. Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 04080 MASONRY ANCHORAGE AND REINFORCEMENT Display hidden notes to specifier. (Don't know how? Click Here) A. Post installed masonry anchors. B. Miscellaneous

More information

SERIES 4070-T GENERAL ASSEMBLY AND INSTALLATION INSTRUCTIONS

SERIES 4070-T GENERAL ASSEMBLY AND INSTALLATION INSTRUCTIONS Table of Contents I. Care and Maintenance... 2 II. Tools / Materials, Sealant Requirements, & Anchor Instructions... 2 III. Structure Verification & Sub-Sillpan Installation... 3 1. Opening Verification...3

More information

IGGA Guide Specification: Dowel Bar Retrofit (DBR) Introduction

IGGA Guide Specification: Dowel Bar Retrofit (DBR) Introduction IGGA Guide Specification: Dowel Bar Retrofit (DBR) Introduction This standard developed by the International Grooving and Grinding Association (IGGA) specifies the procedures for construction of dowel

More information

OXDALE PRODUCT LTD OPERATING AND MAINTENANCE MANUAL SE400 LOG SPLITTER KEEP FOR FUTURE USE

OXDALE PRODUCT LTD OPERATING AND MAINTENANCE MANUAL SE400 LOG SPLITTER KEEP FOR FUTURE USE OXDALE PRODUCT LTD OPERATING AND MAINTENANCE MANUAL SE400 LOG SPLITTER KEEP FOR FUTURE USE 1 CONTENTS Safety 3 Labels 6 Quick Guide 7 In Depth Instructions 9 Warranty Information 16 Technical Specifications

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS SECTION 39 - MANHOLES TABLE OF CONTENTS Section Page 39-1 GENERAL... 39.1 39-2 PRECAST CONCRETE MANHOLES... 39.1 39-2.01 Precast Concrete Sewer Manholes... 39.1 39-2.02 Precast Concrete Storm Drain Manholes...

More information

Umbrella Inserts and Stubby Screens

Umbrella Inserts and Stubby Screens ADHESIVE ANCHORING SPECIALISTS Umbrella Inserts and High Performance Adhesive Systems for Fastening to Hollow Base Materials DESCRIPTION/ADVANTAGES Hollow Block Fastening with A7+ Adhesive Umbrella Inserts

More information

CGI Series 560 SGD Installation Instructions

CGI Series 560 SGD Installation Instructions CGI Series 560 SGD Installation Instructions Read these instructions completely before beginning to install. Become familiar with what type of installation will be required. This door can be installed

More information

CertainTeed INSTALLATION GUIDE SIMTEK FENCE PRODUCTS. Fence Installation Guide 3', 4' & 6' High

CertainTeed INSTALLATION GUIDE SIMTEK FENCE PRODUCTS. Fence Installation Guide 3', 4' & 6' High CertainTeed INSTALLATION GUIDE SIMTEK FENCE PRODUCTS Fence Installation Guide 3', 4' & 6' High INSTALLATION GUIDE These instructions are designed to assist both professional installers and do-it-yourselfers

More information

Technical Data February, 2016

Technical Data February, 2016 Technical Data February, 2016 Product Description 3M DP-600 is a non-sag, grey, rapid setting, two-component polyurethane. It is packaged as 1:1 ratio liquids in a duo-pak cartridge. With the squeeze of

More information

Umbrella Inserts and Stubby Screens

Umbrella Inserts and Stubby Screens ADHESIVE ANCHORING SPECIALISTS Umbrella Inserts and Stubby Screens High Performance Adhesive Systems for Fastening to Hollow Base Materials DESCRIPTION/ADVANTAGES Hollow Block Fastening with A7 Adhesive

More information

SECTION PRECAST CONCRETE SECTIONAL MANHOLES

SECTION PRECAST CONCRETE SECTIONAL MANHOLES SECTION 02545 PRECAST CONCRETE SECTIONAL MANHOLES PART 1 - GENERAL 1.01 SUMMARY A. Section Includes: 1. Precast reinforced concrete cylindrical sectional manholes, complete with openings, inserts, hardware,

More information

SB-WM-ART1-M-BL. Weatherproof Universal Single-Arm Articulating Mount for Medium Displays INSTALLATION MANUAL

SB-WM-ART1-M-BL. Weatherproof Universal Single-Arm Articulating Mount for Medium Displays INSTALLATION MANUAL SB-WM-ART1-M-BL Weatherproof Universal Single-Arm Articulating Mount for Medium Displays INSTALLATION MANUAL WARNING The maximum weight of this wall mount is 90 lbs (41 kg). Use with heavier than the maximum

More information

WINDOW REPLACEMENT INSTRUCTIONS FOR CASEMENT, DOUBLE-HUNG AND CLAD FRAME WINDOWS USING FRAME SCREWS

WINDOW REPLACEMENT INSTRUCTIONS FOR CASEMENT, DOUBLE-HUNG AND CLAD FRAME WINDOWS USING FRAME SCREWS WINDOW REPLACEMENT INSTRUCTIONS FOR CASEMENT, DOUBLE-HUNG AND CLAD FRAME WINDOWS USING FRAME SCREWS These instructions were tested developed for replacing windows in wood-frame wall construction systems

More information

POLY-TUFF SYSTEMS INTERNATIONAL

POLY-TUFF SYSTEMS INTERNATIONAL POLY-TUFF SYSTEMS INTERNATIONAL 2250 E. Tropicana Ave Suite 19-600 Las Vegas, NV 89119 Phone: (866) 977-8833 Fax: (800) 804-0182 Email: sales@polytuffus.com Web: www.polytuffus.com APPLICATION GUIDE FOR

More information

H O O P RAC K. Simple Security

H O O P RAC K. Simple Security H O O P RAC K Simple Security The Hoop Rack is a proven design that provides high security and easy bike parking. The Hoop Rack uses thick pipe construction and the full radius of the bend makes the Hoop

More information

CUTTING THE PIPE: BLUE DUCT Pipe can be easily cut using a Circular Saw or Reciprocal Saw. Trim all edges as necessary.

CUTTING THE PIPE: BLUE DUCT Pipe can be easily cut using a Circular Saw or Reciprocal Saw. Trim all edges as necessary. Installation Instructions In the past it has been IMPOSSIBLE to install an air and water tight underground system. BLUE DUCT (AKDUCT ) has produced a user friendly system that will reduce the amount of

More information

PENSTOCK VALVES. Performance through Excellence

PENSTOCK VALVES. Performance through Excellence VALVES & MANUFACTURING (1988) LTD. PENSTOCK VALVES Performance through Excellence SLIDEGATES WEIR GATES STOP LOGS SLIDEGATES PRECISION FACE SEALING VALVES WEIR GATES STOP LOGS SLIDEGATES Actuation Installation

More information

CHEMSET Reo 502 EF TECHNICAL DATA SHEET. Extra Heavy Duty Pure Epoxy Anchoring Adhesive

CHEMSET Reo 502 EF TECHNICAL DATA SHEET. Extra Heavy Duty Pure Epoxy Anchoring Adhesive Date of Issue: September 9, 2015 Extra Heavy Duty Pure Epoxy Anchoring Adhesive Chemset Reo 502EF is a high performance Pure Epoxy anchoring adhesive specially designed for concrete structural connections

More information

SECTION EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING

SECTION EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING SECTION 230516 - EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

PURE 150-PRO EPOXY ADHESIVE ANCHOR

PURE 150-PRO EPOXY ADHESIVE ANCHOR ONLINE ANCHOR DESIGN SOFTWARE PURE 150-PRO EPOXY ADHESIVE ANCHOR Fully featured and easy to use interface Easy 5 step anchor design with 3D modelling of fastening Professional specification of DEWALT fastenings

More information

SECTION STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 05 12 00 - STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

B. Installation Instructions. Provide installation instructions, including any special equipment, to address the following.

B. Installation Instructions. Provide installation instructions, including any special equipment, to address the following. SAMPLING AND TESTING. The Sampling and Testing requirements contained in -03 shall apply. MARKING. The Marking requirements contained in -03 shall apply. FINAL PRODUCTION INSPECTION. The Final Production

More information

COMPLETE REVISION December Process Industry Practices Structural. PIP STS03601 Epoxy Grout Specification

COMPLETE REVISION December Process Industry Practices Structural. PIP STS03601 Epoxy Grout Specification COMPLETE REVISION December 2010 Process Industry Practices Structural PIP STS03601 Epoxy Grout Specification PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process industry

More information

Note. Returns are blocks / mouldings that have finished sides suitable for doors and windows as shown below. Surround return.

Note. Returns are blocks / mouldings that have finished sides suitable for doors and windows as shown below. Surround return. Installation detail. More than a wall finish, it s a complete thermally insulated interlocking stone cladding system. To get started you will need... Electric/battery power drill, a 100mm or 125mm angle

More information

SECTION SITE FURNISHINGS FOR CFCRT. 1. American Society for Testing and Materials (ASTM).

SECTION SITE FURNISHINGS FOR CFCRT. 1. American Society for Testing and Materials (ASTM). PART 1 - GENERAL 1.1 SECTION INCLUDES A. Benches. B. Trash receptacles. C. Bike storage. 1.2 REFERENCE STANDARDS A. Including but not limited to: 1. American Society for Testing and Materials (ASTM). 1.3

More information

PREPARATION & TOOL CHECKLIST

PREPARATION & TOOL CHECKLIST INSTRUCTION MANUAL RAILING PRODUCTS BEGIN TO AGE AS SOON AS THEY ARE EXPOSED TO NATURE. BUILDINGS EXPERIENCE AGING FACTORS DIFFERENTLY, SO IT IS DIFFICULT TO PREDICT HOW LONG RAILING PRODUCTS WILL LAST.

More information

SECTION BULLET- RESISTANT DOORS

SECTION BULLET- RESISTANT DOORS 1 SECTION 08 3950 BULLET- RESISTANT DOORS PART 1- GENERAL 1.01 SUMMARY A. This Section Includes: 1. Bullet- resistant steel door and frame systems. 2. Door hardware for bullet- resistant steel door and

More information

American Institute of Timber Construction 7012 South Revere Parkway Suite 140 Centennial, CO Phone: 303/ Fax: 303/

American Institute of Timber Construction 7012 South Revere Parkway Suite 140 Centennial, CO Phone: 303/ Fax: 303/ American Institute of Timber Construction 7012 South Revere Parkway Suite 140 Centennial, CO 80112 Phone: 303/792-9559 Fax: 303/792-0669 404.1. SCOPE STANDARD FOR RADIALLY REINFORCING CURVED GLUED LAMINATED

More information

SECTION ARCHITECTURAL PRECAST CONCRETE

SECTION ARCHITECTURAL PRECAST CONCRETE PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Column covers. 1.2 SUBMITTALS A. Design Mixtures: For each precast concrete mixture. Include compressive strength and waterabsorption

More information

Brick, blockwork and concrete walls are also suitable providing the surfaces are flush without excessively wide mortar joints.

Brick, blockwork and concrete walls are also suitable providing the surfaces are flush without excessively wide mortar joints. Data Sheet: (sheet 1 of 8) August 2016 1. Substrate suitability and recommended preparation All material must be installed in environmentally controlled conditions. Allow the SureProtect Pure PVC-u sheet

More information

Operating and Maintenance Instructions

Operating and Maintenance Instructions !! Operating and Maintenance Instructions Keep for future reference PTO400 Log Splitter 1 Index INDEX...2 SAFETY...3 LABELS..4 QUICK GUIDE including storage and transport... 5 IN DEPTH INSTRUCTIONS...

More information

INTEX Millwork Solutions SECTION EXTERIOR PVC PERGOLAS (IBC Compliant)

INTEX Millwork Solutions SECTION EXTERIOR PVC PERGOLAS (IBC Compliant) SECTION 066030 EXTERIOR PVC PERGOLAS (IBC Compliant) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and other Contract Documents, listed in the agreement between the Owner and Contractor, apply to

More information

2 Repair Spalled Joint Faces/Refill Old Blockouts

2 Repair Spalled Joint Faces/Refill Old Blockouts www.emseal.com BEJS SYSTEM INSTALL DATA - BEJS SYSTEM APRIL 2018, PAGE 1 OF 6 INSTALLD AT DO NOT OPEN ANY PACKAGES or install this material until all members of your crew have read and understand these

More information

Estate EXTERNAL HALYARD GROUND SET FLAGPOLE INSTALLATION INSTRUCTIONS

Estate EXTERNAL HALYARD GROUND SET FLAGPOLE INSTALLATION INSTRUCTIONS Estate EXTERNAL HALYARD GROUND SET FLAGPOLE INSTALLATION INSTRUCTIONS Read these instructions completely before any installation is started. Pay close attention to all safety concerns. In the unlikely

More information

MODERN PERGOLA INSTALLATION GUIDE. When only the best will do.

MODERN PERGOLA INSTALLATION GUIDE. When only the best will do. MODERN PERGOLA INSTALLATION GUIDE When only the best will do. TOOLS LIST Drill(s) 3/8" Magnetic Driver (s) 12" Drill Extension #2 Square Drive bit for Drill or Driver Level Tape Measure Hammer Drill if

More information

.1 Comply with the General Conditions of the Contract, Supplementary General Conditions and the requirements of Division 1.

.1 Comply with the General Conditions of the Contract, Supplementary General Conditions and the requirements of Division 1. PAGE 1 PART 1 GENERAL 1.1 REFERENCE.1 Comply with the General Conditions of the Contract, Supplementary General Conditions and the requirements of Division 1. 1.2 RELATED WORK SPECIFIED ELSEWHERE.1 Installation

More information

Installation Instructions

Installation Instructions EMSEAL, LLC 120 Carrier Drive Toronto, ON M9W 5R1 PH : 416-740-2090, FX : 416-740-0233 EMSEAL JOINT SYSTEMS, LTD 25 Bridle Lane Westborough, MA 01581 PH: 508-836-0280, FX: 508-836-0281 www.emseal.com EMSEAL

More information

Installation Instructions. Tools Needed. Tape measure. Level. Shovel or Post hole digger. Concrete. Drill. Stakes. Mallet or hammer.

Installation Instructions. Tools Needed. Tape measure. Level. Shovel or Post hole digger. Concrete. Drill. Stakes. Mallet or hammer. Installation Guide EcoStone Fence 1330 West 400 North Orem, UT 84057 Toll Free 1.866.648.9336 Tel. 1.801.655.5236 Fax 1.801.655.5240 www.ecostonefence.com Installation Instructions Introduction. These

More information

BRUSH APPLICATION INSTRUCTIONS

BRUSH APPLICATION INSTRUCTIONS QUALITY MARINE EQUIPMENT SINCE 1981 Antifouling Paint For Metal Under The Waterline BRUSH APPLICATION INSTRUCTIONS www.antifoulingpaint.net TABLE OF CONTENTS Humidity & Drying Metal Surfaces... 1 Coverage

More information

Essex County College - West Essex Campus Addition And Renovations dlb # / SECTION EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING

Essex County College - West Essex Campus Addition And Renovations dlb # / SECTION EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING SECTION 230516 - EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING PART I - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

Repairs. Chapter 10 Repairs 10. 1

Repairs. Chapter 10 Repairs 10. 1 10 Repairs Chapter 10 Repairs 10. 1 Repairs As an installer, you will probably be called upon to repair damage to a resilient floor. Here are some of the most common problems and the recommended repairs

More information

Installation Guide. Tools Recommended:

Installation Guide. Tools Recommended: Installation Guide GenStone products are designed to provide a realistic look of stone or rock at a fraction of the installed cost. To achieve this, we have engineered the time and hassle out of installation

More information

INSTALLATION GUIDE PermaTrak. Patented Product: U.S. Patent #5,906,084 #8,302,362 #8,522,505 #8,839,588 #9,096,975

INSTALLATION GUIDE PermaTrak. Patented Product: U.S. Patent #5,906,084 #8,302,362 #8,522,505 #8,839,588 #9,096,975 INSTALLATION GUIDE 2009-2017 PermaTrak. Patented Product: U.S. Patent #5,906,084 #8,302,362 #8,522,505 #8,839,588 #9,096,975 Table of Contents Project Overview Forward, Acceptability Criteria, Safety,

More information

FLUOROPOLYMER COATED DUCT FOR CAUSTIC ENVIRONMENTS

FLUOROPOLYMER COATED DUCT FOR CAUSTIC ENVIRONMENTS DIVISION 23 FLUOROPOLYMER COATED DUCT FOR CAUSTIC ENVIRONMENTS Part I General 1.1 Related Documents A. All terms and general provisions of contract, General and Supplementary Conditions, and Specification

More information

Premium Solar Star Greenhouse

Premium Solar Star Greenhouse Premium Solar Star Greenhouse Assembly Instructions SKU# 104901 2006 ClearSpan All rights reserved. Reproduction without permission is prohibited. Revision date: March 2006g Contact your sales representative

More information

IMPORTANT: This product cannot perform its intended function if not properly installed.

IMPORTANT: This product cannot perform its intended function if not properly installed. www.emseal.com HORIZONTAL COLORSEAL INSTALL DATA - HORIZONTAL COLORSEAL FEBRUARY 2015, PAGE 1 OF 3 INSTALLD AT DO NOT OPEN ANY PACKAGES or install this material until all members of your crew have read

More information

To: New York State Department of Transportation ENGINEERING INSTRUCTION. Approved:

To: New York State Department of Transportation ENGINEERING INSTRUCTION. Approved: To: New York State Department of Transportation ENGINEERING INSTRUCTION Title: PRECAST CONCRETE PAVEMENT SLAB SYSTEMS STANDARD SPECIFICATION Distribution: Manufacturers (18) Local Govt. (31) Agencies (32)

More information

SECTION PRECAST CONCRETE STRUCTURES

SECTION PRECAST CONCRETE STRUCTURES SECTION 02605 PRECAST CONCRETE STRUCTURES PART 1 GENERAL 1.01 DESCRIPTION A. CONTRACTOR shall provide all professional services, labor, materials, equipment and incidentals as shown, specified and required

More information

Quality Marine Equipment Since Antifouling Paint For Metal Under The Waterline SPRAY. Application Instructions.

Quality Marine Equipment Since Antifouling Paint For Metal Under The Waterline SPRAY. Application Instructions. Quality Marine Equipment Since 1981 Antifouling Paint For Metal Under The Waterline SPRAY Application Instructions www.antifoulingpaint.net Thank you for selecting Velox Plus Antifouling Paint to protect

More information

SECTION BONDED TERRAZZO FLOORING

SECTION BONDED TERRAZZO FLOORING SECTION 09 66 13.19 BONDED TERRAZZO FLOORING THIS GUIDE SPECIFICATION HAS BEEN PREPARED BY THE NATIONAL TERRAZZO AND MOSAIC ASSOCIATION, INC., AND IS DISTRIBUTED FOR USE BY ITS MEMBERS AND DESIGN PROFESSIONALS.

More information

Installation of Desert Aire FreshAire Evacuator Bench System

Installation of Desert Aire FreshAire Evacuator Bench System Installation of Desert Aire FreshAire Evacuator Bench System Unpack Evacuator and check for shipping damage. If there is damage, immediately notify shipper and contact Paddock Evacuator. Confirm that all

More information

General description: Two-component high-build, high solids surface tolerant universal epoxy coating. For painting on steel and galvanized steel substrates. Certified for systems category C5I High ISO 12944.

More information

b. B aluminum and aluminum-alloy extruded bar, rod, wire, shape and tube

b. B aluminum and aluminum-alloy extruded bar, rod, wire, shape and tube MODEL 240I SECTION 08120 FLUSH ALUMINUM DOORS AND FRAMES PART I GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required to deliver and install aluminum doors, frames,

More information

INSTALLATION INSTRUCTIONS FOR BALCO, INC. TWO COMPONENT STAIR NOSINGS

INSTALLATION INSTRUCTIONS FOR BALCO, INC. TWO COMPONENT STAIR NOSINGS 2626 South Sheridan PO Box 17249 Wichita, Kansas 67217 Phone: (316) 945-9328 Fax: (316) 945-0789 INSTALLATION INSTRUCTIONS FOR BALCO, INC. TWO COMPONENT STAIR NOSINGS 2008, Balco, Inc. 05/14/08 INSTALLATION

More information

Zip Block MODEL ZB INSTALLATION INSTRUCTIONS

Zip Block MODEL ZB INSTALLATION INSTRUCTIONS Zip Block MODEL ZB 100-400 INSTALLATION INSTRUCTIONS 12BT EXPOSED SURFACE SEAL WIDTH Zip Block SEAL 3/4" ± 1/8" [19.05mm ± 3.18mm] BLOCKOUT EDGE 3 1/2" [88.90mm] MAXIMUM BLOCKOUT NOMINAL JOINT WIDTH EPOXY

More information

ClearView Panels Mil 3 Finished Sides with Grommets 1 Hem Side Mil 3 Finished Sides with Grommets 1 Hem Side DESCRIPTION

ClearView Panels Mil 3 Finished Sides with Grommets 1 Hem Side Mil 3 Finished Sides with Grommets 1 Hem Side DESCRIPTION ClearView Panels Photo may show a different but similar model. 2006 FarmTek All Rights Reserved. Reproduction is prohibited without permission. Revision date: November 2006rp STK# DESCRIPTION 105659 16

More information

INSTALLATION INSTRUCTIONS - INSTRUCCIONES DE INSTALACION FOR HURRICANESHIELD IMPACT-RESISTANT DOUBLE-HUNG, SINGLE-HUNG AND SIMULATED-HUNG

INSTALLATION INSTRUCTIONS - INSTRUCCIONES DE INSTALACION FOR HURRICANESHIELD IMPACT-RESISTANT DOUBLE-HUNG, SINGLE-HUNG AND SIMULATED-HUNG 2008 Pella Corporation Part Number: 80ED0101 INSTALLATION INSTRUCTIONS - INSTRUCCIONES DE INSTALACION FOR HURRICANESHIELD IMPACT-RESISTANT DOUBLE-HUNG, SINGLE-HUNG AND SIMULATED-HUNG Instrucciones en español

More information

INSTALLATION GUIDE HEALTH & SAFETY NATURAL VARIANCES & WEATHERING. Ekodeck Should Not: Warnings

INSTALLATION GUIDE HEALTH & SAFETY NATURAL VARIANCES & WEATHERING. Ekodeck Should Not: Warnings INSTALLATION GUIDE INSTALLATION GUIDE To achieve a safe and long lasting Ekodeck installation, it is read the following guide in full. The installation guide is intended to be viewed along with the Ekodeck

More information

Engineered Hardwood Flooring Installation Instructions

Engineered Hardwood Flooring Installation Instructions Engineered Hardwood Flooring Installation Instructions 1 Important Information before You Begin 1.1 Installer/Owner Responsibility Carefully inspect all materials before installation. Materials installed

More information

INSTRUCTIONS FOR USING ITW PHILADELPHIA RESINS 1500LFH

INSTRUCTIONS FOR USING ITW PHILADELPHIA RESINS 1500LFH INSTRUCTIONS FOR USING ITW PHILADELPHIA RESINS 1500LFH --- Super Alloy Black 1500LFH is a liquid, injectable low friction material. The objective of these instructions is to allow the exact casting of

More information

TOOLS ARDEX TILING ACCESSORIES

TOOLS ARDEX TILING ACCESSORIES ARDEX TILING ACCESSORIES TOOLS All of our tiling trade tools are of the highest quality and have been tested and approved by experienced professionals. TILING TROWELS All of our trade trowels are of the

More information

PURE150-PRO CHEMICAL ANCHOR

PURE150-PRO CHEMICAL ANCHOR PURE150-PRO CHEMICAL ANCHOR www.dewalt.com/anchors FAST CURING & HIGH STRENGTH ADHESION. The Pure150-PRO is a two-component high strength epoxy adhesive anchoring system designed for bonding steel elements

More information

Installa on Guide: Fence Distributors. YourNextFence.com

Installa on Guide: Fence Distributors. YourNextFence.com YourNextFence.com Plan Your Fence each line by dividing the length of each line in inches by 96. Round any remainder up. 2 Calculate Materials * For standard single gates (46 1/4 opening) : (1) small Trex

More information

Install Manual GC Max-Span Ground System Piles, Portrait, Bottom Mount Configuration

Install Manual GC Max-Span Ground System Piles, Portrait, Bottom Mount Configuration Install Manual GC Max-Span Ground System Piles, Portrait, Bottom Mount Configuration CONTENTS I II III IV V VI VII VIII IX GENERAL SAFETY PRECAUTIONS AND RESPONSIBILITY OF INSTALLER MATERIALS AND TOOLS

More information

Hynds Tool Range. Built Trade Tough

Hynds Tool Range. Built Trade Tough Hynds Tool Range Built Trade Tough P3 HYNDS TOOL RANGE BROCHURE 2017 Contents Insulated Non-Conductive Range P4-5 Shovels, Spades & Rakes P6-8 Wheelbarrow P8 Pliers & Shears P9 Wrenches P10 Allen Keys

More information

SB-WM-ART2-L-BL SB-WM-ART2-XL-BL

SB-WM-ART2-L-BL SB-WM-ART2-XL-BL SB-WM-ART2-L-BL SB-WM-ART2-XL-BL Weatherproof Universal Dual-Arm Articulating Mount for Large TVs INSTALLATION MANUAL WARNING The maximum weight of this wall mount is 150 lbs (68.04 kg). Use with heavier

More information

Pristine Precise Perfection

Pristine Precise Perfection Pristine Precise Perfection EB TY Premium Hidden Deck Fastening System For Premium Timber Deck Applications Stainless Steel Reinforced EB- GUIDE EB-TY Premium Hidden Deck-Fastening System Optimise Your

More information

INTERIOR. Checkrail. Flashing tape

INTERIOR. Checkrail. Flashing tape Pella Corporation 2007 Part Number: 808F0100 INSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACION FOR PELLA PRECISION FIT DOUBLE-HUNG VENT WINDOW PARA LA VENTANA DE GUILLOTINA CON HOJA PRACTICABLE PRECISION

More information

Installation Instructions for Engineered Wood Flooring

Installation Instructions for Engineered Wood Flooring Installation Instructions for Engineered Wood Flooring PLEASE READ THESE INSTRUCTIONS IN THEIR ENTIERTY BEFORE BEGINNING THE INSTALLATION. Installer s / Owners Responsibility As a natural product, hardwood

More information

Designed for Building Designed for Living

Designed for Building Designed for Living Designed for Building Designed for iving decorative hardware Add Beauty and Strength to Your Custom Outdoor iving Structures ith Outdoor Accents, a new line of decorative timber connectors and fasteners

More information

Installation Instructions for Viking Hearth Engineered Wood Flooring

Installation Instructions for Viking Hearth Engineered Wood Flooring Installation Instructions for Viking Hearth Engineered Wood Flooring 4.16.15 PLEASE READ THESE INSTRUCTIONS IN THEIR ENTIERTY BEFORE BEGINNING THE INSTALLATION. Installer s / Owners Responsibility As a

More information

ASSEMBLY INSTRUCTIONS GL75. BASE SIZE: 2.190m x 1.520m

ASSEMBLY INSTRUCTIONS GL75. BASE SIZE: 2.190m x 1.520m ASSEMBLY INSTRUCTIONS GL75 BASE SIZE: 2.190m x 1.520m CONGRATULATIONS ON PURCHASING A DURATUF GUARDIAN SHED. BEFORE YOU BEGIN THE ASSEMBLY PLEASE NOTE SOME IMPORTANT POINTS: BEFORE YOU START: Read all

More information

HOME STRENGTHENING GUIDE HOW TO ECONOMICALLY STRENGTHEN YOUR HOUSE AGAINST EARTHQUAKES AND HURRICANES

HOME STRENGTHENING GUIDE HOW TO ECONOMICALLY STRENGTHEN YOUR HOUSE AGAINST EARTHQUAKES AND HURRICANES HOME STRENGTHENING GUIDE HOW TO ECONOMICALLY STRENGTHEN YOUR HOUSE AGAINST EARTHQUAKES AND HURRICANES Grenville W Phillips II BSc, BEng, MASc, MURP, CEng, FIStructE, FCIHT, MAPM, MCSCE, MBAPE Chartered

More information

Assembled Patio Door Installation Guide 2-Panel Patio Door with Non-Welded Frame

Assembled Patio Door Installation Guide 2-Panel Patio Door with Non-Welded Frame Assembled Patio Door Installation Guide 2-Panel Patio Door with Non-Welded Frame americancraftsmanwindows.com American Craftsman and all other marks where denoted are trademarks of Andersen Corporation

More information

SECTION SAND CUSHION TERRAZZO FLOORING

SECTION SAND CUSHION TERRAZZO FLOORING SECTION 09 66 13.13 SAND CUSHION TERRAZZO FLOORING THIS GUIDE SPECIFICATION HAS BEEN PREPARED BY THE NATIONAL TERRAZZO AND MOSAIC ASSOCIATION, INC., AND IS DISTRIBUTED FOR USE BY ITS MEMBERS AND DESIGN

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 MAY 1993 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS 422.01 SCOPE 422.02 REFERENCES 422.03 DEFINITIONS

More information

Sturdi-Wall Design Manual for SW46, SW66, SW63, SW64, SW60, SW83, SW84, and SW80 Models

Sturdi-Wall Design Manual for SW46, SW66, SW63, SW64, SW60, SW83, SW84, and SW80 Models Sturdi-Wall Design Manual for SW46, SW66, SW63, SW64, SW60, SW83, SW84, and SW80 Models Project Number ME086-05 by Brent Leatherman, P.E. Timber Tech Engineering, Inc E-Mail: bl@timbertecheng.com January

More information

Step by Step Wing Bagging

Step by Step Wing Bagging Step by Step Wing Bagging By Evan Shaw 073 589 9339 evanevshaw@gmail.com Preparing the Leading Edge 1. Cut cores. (Cutting of wing cores is covered in another article elsewhere) 2. Sand the LE to a nice

More information

Read guide from beginning to end before starting installation. Read all warnings and cautions during unit installation.

Read guide from beginning to end before starting installation. Read all warnings and cautions during unit installation. Installation Guide for E-Series/Eagle High-Performance Mullion Windows with LVL Reinforcement and Installed Using Type B Clips Thank you for choosing Andersen. Instructions are for typical, new wood-framed

More information

DULUX UNIVERSAL UNDERCOAT

DULUX UNIVERSAL UNDERCOAT TECHNICAL DATA SHEET Version 1 2015 JUNE THIS ISSUE SUPERSEDES ALL PREVIOUS PUBLICATIONS PRODUCT DESCRIPTION Intermediate coating for use under decorative topcoats, for interior and exterior use PRODUCT

More information

Installation Instructions

Installation Instructions EMSEAL, LLC 120 Carrier Drive Toronto, ON M9W 5R1 PH : 416-740-2090, FX : 416-740-0233 EMSEAL JOINT SYSTEMS, LTD 25 Bridle Lane Westborough, MA 01581 PH: 508-836-0280, FX: 508-836-0281 www.emseal.com EMSEAL

More information

A. Extent of structural precast concrete work is shown on drawings and in schedules.

A. Extent of structural precast concrete work is shown on drawings and in schedules. SECTION 03 41 00 - STRUCTURAL PRECAST CONCRETE PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 specification

More information