Page 1 of 5 Revision 1.0

Size: px
Start display at page:

Download "Page 1 of 5 Revision 1.0"

Transcription

1 On February 1, 2018 the Decision Statement issued under Section 54 of the Canadian Environmental Assessment Act, 2012 () for the BP Canada Energy Group ULC ("BP") Scotian Basin Exploration Project ("Project") was published. 7.1 of the Decision Statement requires that an Implementation Schedule for the conditions contained within the Decision Statement be submitted to the Canada-Nova Scotia Offshore Petroleum Board (Board) and at least 15 days prior to the start of drilling. In accordance with 7.1, BP has developed this Implementation Schedule which focuses on the drilling of the first exploration well - Aspy D-11. The Implementation Schedule was first provided to the CNSOPB on March 29, The Implementation Schedule reflects a spud date of April 22, 2018 with an estimated end of well date of August 21, 2018 (based on 120 day drilling program). The Implementation Schedule identifies the estimated and final commencement and completion dates for each activity related to the Decision Statement condition, as well as provides sufficient detail to allow the CNSOPB to plan compliance verification activities. The Implementation Schedule has been structured by Activity Phase (Pre-spud,, Well Testing, Well Suspension/, and Phases). The timelines included in this Implementation Schedule are subject to change and are dependent on weather, other operational constraints, as well as the duration of the drilling activities for the Aspy D-11 well. As dates and information may change, BP will update this Implementation Schedule for the Aspy D-11 well as the Project progresses. *Please note, the timelines within the Implementation Schedule only consider the Aspy D-11, and do not consider the wells, which may be drilled as part of future drilling activities. Scotian Basin Exploration Project - Aspy D PRE-SPUD PHASE The Proponent shall submit an implementation schedule for conditions contained in this Decision Statement to the Board and the Agency at least 15 days prior to the start of drilling. The implementation schedule shall indicate the commencement and completion dates for each activity relating to conditions set out in this Decision Statement with sufficient detail to allow the Board to plan compliance verification activities. BP shall submit an implementation schedule for conditions contained in the Decision Statement to the Board and the Agency at least 15 days prior to the start of drilling. The implementation schedule will indicate the commencement and completion dates for each activity relating to conditions set out in the Decision Statement with sufficient detail to allow the Board to plan compliance verification activities. Pre-spud 28-Mar Mar-18 BP has developed a Project Implementation Schedule (this document) as per the requirements of this condition. The Implementation Schedule is based upon the best available information and knowledge to satisfy each condition at the time of submission. The Project Implementation Schedule was first submitted to the CNSOPB on March 28, The Proponent shall cause to be published on the Internet the reports and the executive summaries referred to in BP shall develop an Internet site to publish the following: condition 2.8, the marine mammal observation requirements referred to in condition 3.9, the Fisheries - reports and the executive summaries referred to in condition 2.8, Communications Plan referred to in condition 5.1, the wellhead abandonment strategy referred to in condition - the marine mammal observation requirements referred to in condition 3.9, 5.2, the Spill Response Plan and the well control strategies and measures referred to in condition 6.2, the net - the Fisheries Communications Plan referred to in condition 5.1, environmental benefit analysis referred to in condition 6.7, the implementation schedule referred to in condition - the wellhead abandonment strategy referred to in condition 5.2, 7.1, and any update(s) or revision(s) to the above documents, upon submission of these documents to the parties - the Spill Response Plan and the well control strategies and measures referred to in condition 6.2, referenced in the respective conditions. The Proponent shall notify Indigenous groups of the availability of these - the net environmental benefit analysis referred to in condition 6.7, documents within 48 hours of their publication. - the implementation schedule referred to in condition 7.1, Any update(s) or revision(s) to the above documents, upon submission of these documents to the parties referenced in the respective conditions. BP shall notify Indigenous groups of the availability of these documents within 48 hours of their publication. The Proponent shall conduct a pre-drill survey with qualified individual(s) at each well site to confirm the presence or absence of any unexploded ordnance or other seabed hazards. If any such ordnance or seabed hazard is detected, the Proponent shall consult with the Board prior to commencing drilling to determine an appropriate course of action. Pre-spud 9-Apr Apr-18 BP shall conduct a pre-drill survey with qualified individual(s) at the well site to confirm the presence or absence of any unexploded ordnance or other seabed hazards. If any such ordnance or seabed hazard is detected, BP shall consult with the Board prior to commencing drilling to determine an appropriate course of action. Pre-spud 14-Apr Apr-18 BP has established an external internet site for posting of items within 2.9. Canada Nova Scotia: Procedures to notify Indigenous and commercial fishers a minimum of two weeks prior to starting the drilling of each well has been developed. Initial internet posting occured on April 9, 2018 with most recent updates on April 16, Internet site will be updated as addtional information is avaiable. The pre-drill remotely operated vehicle (ROV) was conducted on April 14, A geohazard specialist completed review of the ROV footage on April 17, 2018 and determined that no unexploded ordinance or other seabed hazards were observed. 3.6 The Proponent shall conduct a pre-drill survey with qualified individual(s) at each well site to confirm the presence BP shall conduct a pre-drill survey with qualified individual(s) at the well site to confirm the presence or absence of any or absence of any aggregations of habitat-forming corals or sponges or any other environmentally sensitive aggregations of habitat-forming corals or sponges or any other environmentally sensitive features. BP shall complete the features. The Proponent shall complete the survey prior to commencing each well site drilling and shall report the survey prior to commencing each well site drilling and shall report the results of the survey for the well site to the Board results of the survey for each well site to the Board within 48 hours of the completion of each survey. within 48 hours of the completion of the survey. Pre-spud 14-Apr Apr-18 The pre-drill remotely operated vehicle (ROV) survey was conducted on April 14, 2018 and the survey report was submitted to the Board on April 16, If the survey(s) conducted in accordance with condition 3.6 confirms the presence of aggregations of habitatforming corals or sponges, or if other environmentally sensitive features are identified by a qualified individual, the or sponges, or if other environmentally sensitive features are identified by a qualified individual, BP shall move the drilling If the survey conducted in accordance with condition 3.6 confirms the presence of aggregations of habitat-forming corals Proponent shall move the drilling unit to avoid affecting them, unless not technically feasible. If not technically unit to avoid affecting them, unless not technically feasible. If not technically feasible, BP shall consult with the Board prior feasible, the Proponent shall consult with the Board prior to commencing drilling to determine an appropriate to commencing drilling to determine an appropriate course of action, including any additional mitigation measures, to the course of action, including any additional mitigation measures, to the Board s satisfaction. Board s satisfaction. Pre-spud 14-Apr Apr-18 The pre-drill remotely operated vehicle (ROV) survey conducted on April 14, 2018 did not depict the presence of aggregations of habitat-forming corals or sponges, or if other environmentally sensitive features The Proponent shall develop and implement, in consultation with Fisheries and Oceans Canada and the Board, BP shall develop and implement, in consultation with Fisheries and Oceans Canada and the Board, follow-up requirements follow-up requirements to verify the accuracy of the environmental assessment as it pertains to underwater noise to verify the accuracy of the environmental assessment as it pertains to underwater noise levels. As part of the levels. As part of the development of these follow-up requirements, the Proponent shall determine how development of these follow-up requirements, BP shall determine how underwater noise levels will be monitored through underwater noise levels will be monitored through field measurement by the Proponent during the drilling field measurement by BP during the drilling program and shall provide that information to the Board at least 30 days prior program and shall provide that information to the Board at least 30 days prior to the start of the drilling program. If to the start of the drilling program. If drilling occurs between January 1 and April 30, BP shall consult with Fisheries and drilling occurs between January 1 and April 30, the Proponent shall consult with Fisheries and Oceans Canada Oceans Canada and the Board prior to drilling to determine if additional monitoring of underwater noise levels and adverse and the Board prior to drilling to determine if additional monitoring of underwater noise levels and adverse environmental effects caused by the drilling unit in Northern Bottlenose Whale (Hyperoodon ampallatus ) critical habitat is environmental effects caused by the drilling unit in Northern Bottlenose Whale (Hyperoodon ampallatus ) critical required. habitat is required. Pre-spud 20-Feb Mar-18 Initial consultation occurred between BP, the Board and DFO on February 20, 2018 to seek input on the development and scope of an acoustic monitoring plan to address underwater sound levels and environmental effects to the Northern Bottlenose Whale critical habitat area should drilling activities commence prior to April 30. The proposed acoustic monitoring plan was submitted by BP to the Board and DFO on February 27, Changes were reflected in the draft plan and a final plan was submitted to the Board and DFO on March 19, Acoustic recorders were deployed during the period of April 14-16, The Proponent shall develop, prior to the start of the drilling program and in consultation with Indigenous groups, Environment and Climate Change Canada and the Board, follow-up requirements to verify the accuracy of the environmental assessment as it pertains to migratory birds and to determine the effectiveness of the mitigation measures implemented by the Proponent to avoid harm to migratory birds, their eggs and nests, including the mitigation measures used to comply with conditions 4.1 to 4.4. As part of the follow-up, the Proponent shall monitor the drilling unit and platform supply vessels for the presence of stranded birds. The Proponent shall implement these follow-up requirements for the duration of the drilling program. BP shall develop, prior to the start of the drilling program and in consultation with Indigenous groups, Environment and Climate Change Canada and the Board, follow-up requirements to verify the accuracy of the environmental assessment as it pertains to migratory birds and to determine the effectiveness of the mitigation measures implemented by BP to avoid harm to migratory birds, their eggs and nests, including the mitigation measures used to comply with conditions 4.1 to 4.4. As part of the follow-up, BP shall monitor the drilling unit and platform supply vessels for the presence of stranded birds. BP shall implement these follow-up requirements for the duration of the drilling program. Pre-spud 24-Jan Aug-18 BP initiated contact with Environment and Climate Change Canada-Canadian Wildlife Service (ECCC-CWS) on January 24, 2018 to determine the process for capturing and handling of stranded migratory birds. On January 25, 2018 ECCC-CWS provided the permit application for "Capture and Handling of Migratory Birds" as well as the October 2016 Procedures for handling and documenting stranded birds encountered on infrastructure offshore Atlantic Canada and guidance documents. A permit application was submitted on February 15, 2018 and subsequently a CWS Scientific Permit (permit no. SC4023) was issued on March 21, 2018 and signed on March 23, Training of nominees identified in the permit is currently on-going and being conducted by ECRC. Follow-up programs including Migratory Birds were discussed in meetings with Indigenous groups on meetings with Indigenous groups on February 2 (Sipekne'katik), February 21 (WNNB), February 6 and 23 (KMKNO) and February 26 (MTI), 2018 with an informational handout ed to each Indigenous group in advance of the meeting and the slideshow presentation ed after the meeting. Follow up with general information was provided throughout February and March. 5.1 The Proponent shall develop and implement a Fisheries Communication Plan in consultation with Indigenous and BP shall develop and implement a Fisheries Communication Plan in consultation with Indigenous and commercial fishers. commercial fishers. The Proponent shall include in the plan procedures to notify Indigenous and commercial BP shall include in the plan procedures to notify Indigenous and commercial fishers a minimum of two weeks prior to fishers a minimum of two weeks prior to starting the drilling of each well, procedures to communicate with these starting the drilling of each well, procedures to communicate with these fishers in the event of an accident or malfunction, fishers in the event of an accident or malfunction, and procedures to communicate the results of the monitoring and procedures to communicate the results of the monitoring referred to in condition 6.9. BP shall develop the plan prior to referred to in condition 6.9. The Proponent shall develop the plan prior to drilling and implement it for the duration drilling and implement it for the duration of the drilling program. of the drilling program. Pre-spud 8-Nov-17 Commencing April 3, 2018 through +2 weeks In November 2017, BP initiated communications via with Indigenous groups on the Indigenous Fisheries Communication Plan including proposed notification contact and procedures for each group and proposed frequency and content of operational updates and emergency update bulletins. This information was revisited during meetings with Indigenous groups on February 2 (Sipekne'katik), February 21 (WNNB), February 6 and 23 (KMKNO) and February 26 (MTI), 2018 with an informational handout ed to each Indigenous group in advance of the meeting and the slideshow presentation ed after the meeting. On February 20, 2018, BP initiated communications via (with an informational handout) with commercial fisheries associations, seafood producer associations and the Aquaculture Association of Nova Scotia on the Fisheries Communication Plan including proposed notification contacts and proposed frequency and content of operational updates and emergency update bulletins. The appropriate communication method with Indigenous and commercial fishers in accordance with the Fisheries Communication Plan was completed by March 7, Plan procedures to notify Indigenous and commercial fishers a minimum of two weeks prior to starting the drilling has been shared and confirmed with each group. Page 1 of 5 Revision 1.0

2 Scotian Basin Exploration Project - Aspy D The Proponent shall prepare and submit a Spill Response Plan and well control strategies and measures to the Board for acceptance at least 90 days prior to drilling. The well control strategies and measures referred to in condition 6.2 shall include the drilling of a relief well in the event that well control cannot be re-established following a sub-sea well blowout. BP shall prepare and submit a Spill Response Plan and well control strategies and measures to the Board for acceptance at least 90 days prior to drilling. Pre-spud 1-Nov Nov-17 The well control strategies and measures referred to in condition 6.2 shall include the drilling of a relief well in the event that well control cannot be re-established following a sub-sea well blowout. Pre-spud 8-Nov-17 8-Mar-18 The draft Spill Response Plan was submitted to the Board on November 2, Lessons learned from the December 6-7, 2017 demonstration capability exercise and comments received from the Board were incorporated and the final Spill Response Plan was submitted to the Board on February 13, In addition, the following well control strategies include: - ROV intervention system for emergency BOP activation (initial submittal November 17, 2017), - Capping and containment response (initial submittal November 1, 2017), - Relief well (initial submittal November 8, 2017). Plans are living documents and may be updated as required. A well-specific Relief Well Plan has been developed in support of the project. The initial Relief Well Plan was submitted to the Board on November 8, A final Relief Well Plan was submitted to the Board on March 8, The Spill Response Plan shall include: procedures to respond to a spill of any substance that may cause adverse environmental effects (e.g. spill containment and recovery); measures for wildlife response, protection and rehabilitation (e.g. collection and cleaning of marine mammals, migratory birds, sea turtles and species at risk) and measures for shoreline protection and clean-up. The Spill Response Plan shall include: - procedures to respond to a spill of any substance that may cause adverse environmental effects (e.g. spill containment and recovery); - measures for wildlife response, protection and rehabilitation (e.g. collection and cleaning of marine mammals, migratory birds, sea turtles and species at risk) and measures for shoreline protection and clean-up. Pre-spud 2-Nov-17 The draft Spill Response Plan was submitted to the Board on November 2, Lessons learned from the December 6-7, 2017 demonstration capability exercise and comments received from the Board were incorporated and the final Spill Response Plan was submitted to the Board on February 13, The draft Wildlife Response Plan was submitted to the Board on November 3, The final Wildlife Response Plan was submitted to the Board on February 13, Plans are living documents and may be updated as required. A demonstration capability exercise was conducted on December 6-7, The Spill Response Plan was updated and submitted to the CNSOPB on February 13, The Proponent shall conduct an exercise of the Spill Response Plan prior to the commencement of drilling and adjust the plan to the satisfaction of the Board to address any deficiencies identified during the exercise. BP shall conduct an exercise of the Spill Response Plan prior to the commencement of drilling and adjust the plan to the satisfaction of the Board to address any deficiencies identified during the exercise. Pre-spud 6-Dec-17 7-Dec The Proponent shall undertake a net environmental benefit analysis to consider use of dispersants against other spill response options to identify those techniques that will provide for the best opportunities to minimize environmental consequences, and provide it to the Board for review at least 90 days prior to drilling. BP shall undertake a net environmental benefit analysis to consider use of dispersants against other spill response options to identify those techniques that will provide for the best opportunities to minimize environmental consequences, and provide it to the Board for review at least 90 days prior to drilling. Pre-spud 30-Aug Nov-17 A draft net environmental benefit analysis (i.e. spill impact mitigation assessment) was submitted to the CNSOPB on August 30, A Science Table meeting was held on September 6, 2017 in Montreal. A net environmental benefit analysis (i.e. spill impact mitigation assessment) final report was submitted to the CNSOPB on November 20, The final report is available on the BP Nova Scotia website as per Condiiton The Proponent shall consult with Indigenous groups during the development of the Spill Response Plan and well control strategies and measures, and provide the approved versions to Indigenous groups. BP shall consult with Indigenous groups during the development of the Spill Response Plan and well control strategies and measures, and provide the approved versions to Indigenous groups. Pre-spud 14-Sep Mar-18 BP's spill response and well control strategies and measures, including an outline of the Table of Contents for the Spill Response Plan, were presented in meetings with Indigenous groups on September 14, 2017 (KMKNO), February 2 (Sipekne'katik), 21 (WNNB) and 26 (MTI), Hard copies of the Spill Response Plan (as submitted to the CNSOPB) were provided to each group in February and March Indigenous groups consultation will continue throughout the project. A demonstration capability exercise was conducted December 6-7, 2017 with specific identified Indigenous groups invited to attend and participate. The identified groups participated in the exercise. DRILLING PHASE 2.5 The Proponent shall submit the information identified in condition 2.4 to the Board prior to the implementation of each follow-up requirement. The Proponent shall update that information in consultation with Indigenous groups during the implementation of each follow-up requirement, and shall provide the updated information to the Board and to Indigenous groups within 30 days of the information being updated. BP shall submit the information identified in condition 2.4 to the Board prior to the implementation of each follow-up requirement. BP shall update that information in consultation with Indigenous groups during the implementation of each follow-up requirement, and shall provide the updated information to the Board and to Indigenous groups within 30 days of the information being updated. 2-Feb-18 Information about BP's proposed follow-up and monitoring programs were presented in meetings with Indigenous groups on February 2 (Sipekne'katik), February 21 (WNNB), February 23 (KMKNO) and February 26 (MTI), Content of the meetings included discussion around: methodology, location, frequency, timing and duration of monitoring; the scope, content and frequency of reporting of results; levels of environmental change relative to baseline conditions that may require adaptive management; and additional mitigation measures to be implemented if warranted. Prior to meetings, informational handouts were distributed via and copies of handouts and slide presentations were provided after the meetings. This information was also provided to the Agency and the Board on February 26, As of March 22, 2018 no feedback has been received by Indigenous groups. Consultation will continue through implementation of the follow-up programs and analysis of results with updates made to the programs as applicable. 2.6 The Proponent shall, where follow-up is a requirement of a condition set out in this Decision Statement: undertake monitoring and analysis according to the information determined pursuant to condition 2.4 to verify the accuracy of the environmental assessment as it pertains to the particular condition and/or to determine the effectiveness of any mitigation measure(s); determine whether modified or additional mitigation measures are required based on the monitoring and analysis undertaken pursuant to condition 2.6.1; if modified or additional mitigation measures are required pursuant to condition 2.6.2, implement these mitigation measures in a timely manner and monitor them pursuant to condition BP shall, where follow-up is a requirement of a condition set out in this Decision Statement: - undertake monitoring and analysis according to the information determined pursuant to condition 2.4 to verify the accuracy of the environmental assessment as it pertains to the particular condition and/or to determine the effectiveness of any mitigation measure(s); - determine whether modified or additional mitigation measures are required based on the monitoring and analysis undertaken pursuant to condition 2.6.1; - if modified or additional mitigation measures are required pursuant to condition 2.6.2, implement these mitigation measures in a timely manner and monitor them pursuant to condition Apr-18 BP is planning on conducting the following follow-up programs: Measure the concentration of synthetic-based drilling fluids retained on discharged drilling cuttings Collect drill waste deposition information after drilling of the first well is complete to verify the drill waste deposition modeling predictions Underwater noise level (Acoustic Monitoring Plan) Migratory bird monitoring on the MODU and platform supply vessels following the CWS Scientific Permit (permit no. SC4023) conditions If additional mitigation measures are required after analysis, BP shall engage in further consultation. BP shall consult with each Indigenous group with analysis of the follow-up results and the selection of any modified or additional mitigation measures. 2.7 For each condition where follow-up requirements include consultation with Indigenous groups, the Proponent shall discuss with each Indigenous group opportunities for their participation in the analysis of the follow-up results and the selection of any modified or additional mitigation measures, as set out pursuant to condition 2.6. For each condition where follow-up requirements include consultation with Indigenous groups, BP shall discuss with each Indigenous group opportunities for their participation in the analysis of the follow-up results and the selection of any modified or additional mitigation measures, as set out pursuant to condition Jan The Proponent shall treat all waste material discharged from offshore drilling into the marine environment in adherence with the Offshore Waste Treatment Guidelines, issued jointly by the National Energy Board, the Canada-Newfoundland and Labrador Offshore Petroleum Board and the Canada-Nova Scotia Offshore Petroleum Board, and in accordance with the requirements of the Fisheries Act, the Migratory Birds Convention Act, 1994 and any other applicable legislation. BP shall treat all waste material discharged from offshore drilling into the marine environment in adherence with the Offshore Waste Treatment Guidelines, issued jointly by the National Energy Board, the Canada-Newfoundland and Labrador Offshore Petroleum Board and the Canada-Nova Scotia Offshore Petroleum Board, and in accordance with the requirements of the Fisheries Act, the Migratory Birds Convention Act, 1994 and any other applicable legislation. BP developed an Environmental Protection Plan (EPP) with consideration of all material discharged from offshore drilling activities with inclusion of the Offshore Waste Treatment Guidelines. EPP drafts have been submitted to the Board on October 25, 2017, February 19, 2018 and April 3, A final EPP will was submitted on April 12, The EPP is a living document and may be updated as required. 3.2 The Proponent shall dispose of spent or excess synthetic-based drilling muds that cannot be re-used at an approved on-shore facility in Canada. BP shall dispose of spent or excess synthetic-based drilling muds that cannot be re-used at an approved on-shore facility in Canada. 22-Apr-18 Synthetic-based drilling muds (SBM) have been identified in the Environmental Protection Plan (EPP). unused SBM are planned to be shipped to shore upon completion of the drilling activities. 3.3 The Proponent shall apply the Offshore Chemical Selection Guidelines for & Production Activities on Frontier Lands, issued jointly by the National Energy Board, the Canada- Newfoundland and Labrador Offshore Petroleum Board and the Canada-Nova Scotia Offshore Petroleum Board, to select lower toxicity chemicals that would be used and discharged into the marine environment, including drilling fluid constituents, and shall submit any necessary risk justification as per Step 10 of the Guidelines to the Board for acceptance prior to use. BP shall apply the Offshore Chemical Selection Guidelines for & Production Activities on Frontier Lands, issued jointly by the National Energy Board, the Canada- Newfoundland and Labrador Offshore Petroleum Board and the Canada- Nova Scotia Offshore Petroleum Board, to select lower toxicity chemicals that would be used and discharged into the marine environment, including drilling fluid constituents, and shall submit any necessary risk justification as per Step 10 of the Guidelines to the Board for acceptance prior to use. 22-Apr-18 Chemical selection process is ongoing. Any chemical products deemed as requiring a "Step 10" of the Guidelines risk justification shall be submitted to the CNSOPB. 3.4 The Proponent shall treat all discharges from platform supply vessels into the marine environment in accordance with the Fisheries Ac t and the International Maritime Organization s International Convention for the Prevention of Pollution from Ships. BP shall treat all discharges from platform supply vessels into the marine environment in accordance with the Fisheries Act and the International Maritime Organization s International Convention for the Prevention of Pollution from Ships. platform supply vessels shall have a third-party certificate for International Oil Pollution Prevention (IOPP) and International Sewage Pollution Prevention (ISPP). Page 2 of 5 Revision 1.0

3 Scotian Basin Exploration Project - Aspy D The Proponent shall apply Fisheries and Oceans Canada s Statement of Canadian Practice with Respect to the Mitigation of Seismic Sound in the Marine Environment during the planning and the conduct of vertical seismic surveys. In doing so the Proponent shall establish a safety zone of a minimum radius of 650 metres from the seismic sound source. BP shall apply Fisheries and Oceans Canada s Statement of Canadian Practice with Respect to the Mitigation of Seismic Sound in the Marine Environment during the planning and the conduct of vertical seismic surveys. In doing so BP shall establish a safety zone of a minimum radius of 650 metres from the seismic sound source. The Proponent shall develop, in consultation with Fisheries and Oceans Canada and the Board, a marine mammal BP shall develop, in consultation with Fisheries and Oceans Canada and the Board, a marine mammal monitoring plan that monitoring plan that shall be submitted to the Board at least 30 days prior to the commencement of any vertical shall be submitted to the Board at least 30 days prior to the commencement of any vertical seismic survey. BP shall seismic survey. The Proponent shall implement the plan during the conduct of vertical seismic surveys. As part of implement the plan during the conduct of vertical seismic surveys. As part of the plan, BP shall develop and implement the plan, the Proponent shall develop and implement marine mammal observation requirements, including the marine mammal observation requirements, including the use of passive acoustic monitoring or equivalent technology and use of passive acoustic monitoring or equivalent technology and visual monitoring by marine mammal observers visual monitoring by marine mammal observers throughout vertical seismic surveys. BP shall submit the results of the throughout vertical seismic surveys. The Proponent shall submit the results of the activities undertaken as part of activities undertaken as part of the marine mammal observation requirements to the Board within 30 days of the end of the marine mammal observation requirements to the Board within 30 days of the end of the vertical seismic the vertical seismic surveys. surveys. 25-Jul-18 Near 1-May-18 End of VSP BP has retained third-party services support for marine mammal observations and passive acoustic monitoring during the vertical seismic profiling (VSP) anticipated near the end of drilling activities. BP has retained third-party services support for marine mammal observations and passive acoustic monitoring during the vertical seismic profiling anticipated near the end of drilling activities. A plan is being developed and will be submitted to the Board at least 30 days prior to any VSP related activities The Proponent shall implement measures to prevent or reduce the risks of collisions between platform supply vessels and marine mammals and sea turtles, including: requiring platform supply vessels to use established shipping lanes, where they exist; implementing a maximum speed limit of 12 knots for platform supply vessels, reducing speed limit to ten knots when within the Project area, and to seven knots when marine mammals or sea turtles are observed or reported within 400 metres of a platform supply vessel, except if not feasible for safety reasons; prohibiting platform supply vessels from entering critical habitat for the North Atlantic Right Whale (Eubalaena glacialis ) and Northern Bottlenose whale (Hyperoodon ampullatus ) as defined in Fisheries and Oceans Canada s Recovery Strategy for the North Atlantic Right Whale (Eubalaena glacialis) in Atlantic Canadian Waters and Fisheries and Oceans Canada s Recovery Strategy for the Northern Bottlenose Whale (Hyperoodon ampullatus ), Scotian Shelf population, in Atlantic Canadian Waters, except if not feasible for safety reasons; prohibiting platform supply vessels from operating within a radius of two kilometres from Sable Island, except if not feasible for safety reasons. BP shall implement measures to prevent or reduce the risks of collisions between platform supply vessels and marine mammals and sea turtles, including: - requiring platform supply vessels to use established shipping lanes, where they exist; - implementing a maximum speed limit of 12 knots for platform supply vessels, reducing speed limit to ten knots when within the Project area, and to seven knots when marine mammals or sea turtles are observed or reported within 400 metres of a platform supply vessel, except if not feasible for safety reasons; - prohibiting platform supply vessels from entering critical habitat for the North Atlantic Right Whale (Eubalaena glacialis ) and Northern Bottlenose whale (Hyperoodon ampullatus ) as defined in Fisheries and Oceans Canada s Recovery Strategy for the North Atlantic Right Whale (Eubalaena glacialis) in Atlantic Canadian Waters and Fisheries and Oceans Canada s Recovery Strategy for the Northern Bottlenose Whale (Hyperoodon ampullatus ), Scotian Shelf population, in Atlantic Canadian Waters, except if not feasible for safety reasons; - prohibiting platform supply vessels from operating within a radius of two kilometres from Sable Island, except if not feasible for safety reasons. BP has incorporated these prevention measures into the following: (1) required regulatory induction (project onboarding) training, and (2) the project Marine Operations Manual The Proponent shall report any collisions of a platform supply vessel with marine mammals or sea turtles to the Board, to Fisheries and Oceans Canada s Canadian Coast Guard Regional Operations Centre, and any other BP shall report any collisions of a platform supply vessel with marine mammals or sea turtles to the Board, to Fisheries and Oceans Canada s Canadian Coast Guard Regional Operations Centre, and any other relevant authorities as soon as relevant authorities as soon as reasonably practicable but no later than 24 hours following the collision, and notify reasonably practicable but no later than 24 hours following the collision, and notify Indigenous groups in writing. Indigenous groups in writing. The Proponent shall develop and implement follow-up requirements to verify the accuracy of the predictions BP shall develop and implement follow-up requirements to verify the accuracy of the predictions made during the made during the environmental assessment as it pertains to fish and fish habitat, including marine mammals and environmental assessment as it pertains to fish and fish habitat, including marine mammals and sea turtles, and to sea turtles, and to determine the effectiveness of mitigation measures identified under conditions 3.1 to As determine the effectiveness of mitigation measures identified under conditions 3.1 to As part of these follow-up part of these follow-up requirements, the Proponent shall: requirements, BP shall: measure the concentration of synthetic-based drilling fluids retained on discharged drilling cuttings as - measure the concentration of synthetic-based drilling fluids retained on discharged drilling cuttings as described in described in the Offshore Waste Treatment Guidelines to verify that the discharge meets the limits set out in the the Offshore Waste Treatment Guidelines to verify that the discharge meets the limits set out in the Guidelines and in Guidelines and in accordance with the requirements of the Fisheries Act and report the results to the Board; accordance with the requirements of the Fisheries Act and report the results to the Board; collect drill waste deposition information after drilling of the first well is complete to verify the drill waste - collect drill waste deposition information after drilling of the first well is complete to verify the drill waste deposition deposition modeling predictions and report the information collected to the Board. modeling predictions and report the information collected to the Board. 6-May-18 BP has included the regulatory agency reporting requirement within the project Incident Reporting and Investigation Procedure. Indigenous groups will be notified in writing. BP has included follow-up requirements that are identified to meet these conditions within the Environmental Protection Plan. Refer to The Proponent shall conduct Designated Project activities in a manner that protects migratory birds and avoids harming, killing or disturbing migratory birds or destroying, disturbing or taking their nests or eggs. In this regard, the Proponent shall take into account Environment and Climate Change Canada s Avoidance Guidelines. The Proponent s actions when taking into account the Avoidance Guidelines shall be in compliance with the Migratory Birds Convention Act, 1994 and with the Species at Risk Act. BP shall conduct Designated Project activities in a manner that protects migratory birds and avoids harming, killing or disturbing migratory birds or destroying, disturbing or taking their nests or eggs. In this regard, BP shall take into account Environment and Climate Change Canada s Avoidance Guidelines. BP's actions when taking into account the Avoidance Guidelines shall be in compliance with the Migratory Birds Convention Act, 1994 and with the Species at Risk Act. 24-Jan-18 BP initiated contact with Environment and Climate Change Canada-Canadian Wildlife Service (ECCC-CWS) on January 24, 2018 to determine the process for capturing and handling of stranded migratory birds. On January 25, 2018 ECCC-CWS provided the permit application for "Capture and Handling of Migratory Birds" as well as the October 2016 Procedures for handling and documenting stranded birds encountered on infrastructure offshore Atlantic Canada and guidance documents. A permit application was submitted on February 15, 2018 and subsequently a CWS Scientific Permit (permit no. SC4023) was issued on March 21, 2018 and signed on March 23, Training of nominees identified in the permit is currently on-going and being conducted by ECRC. 4.4 The Proponent shall require supply helicopters to fly at altitudes greater than 300 metres above sea level, and at lateral distances greater than two kilometres from active migratory birds colonies and Sable Island, except for approach and landing maneuvers and if not feasible for safety reasons. BP shall require supply helicopters to fly at altitudes greater than 300 metres above sea level, and at lateral distances greater than two kilometres from active migratory birds colonies and Sable Island, except for approach and landing maneuvers and if not feasible for safety reasons. BP has incorporated the mitigation measures into the required regulatory induction (project on-boarding) training. In addition, Canadian Helicopters have included it their route guide The Proponent shall take all reasonable measures to prevent accidents and malfunctions that may result in adverse environmental effects and shall implement emergency response procedures and contingency plans developed in relation to the Designated Project in the event of an accident or malfunctions. In the event of a spill or unplanned release of oil or any other substance that may cause adverse environmental effects, the Proponent shall notify the Board and any other relevant authorities as soon as possible and implement its Spill Response Plan, including: monitoring the adverse environmental effects of the spill on components of the marine environment to be accepted by the Board until specific endpoints identified in consultation with expert government departments are achieved. As applicable, monitoring may include: sensory testing of seafood for taint, and chemical analysis for oil concentrations and any other contaminants, as applicable; measuring levels of contamination in recreational and commercial fish species with results integrated into a human health risk assessment to determine the fishing area closure status; monitoring for marine mammals, sea turtles and birds for visible signs of contamination or oiling and reporting results to the Board. BP shall take all reasonable measures to prevent accidents and malfunctions that may result in adverse environmental effects and shall implement emergency response procedures and contingency plans developed in relation to the Designated Project in the event of an accident or malfunctions. In the event of a spill or unplanned release of oil or any other substance that may cause adverse environmental effects, BP shall notify the Board and any other relevant authorities as soon as possible and implement its Spill Response Plan, including: - monitoring the adverse environmental effects of the spill on components of the marine environment to be accepted by the Board until specific endpoints identified in consultation with expert government departments are achieved. As applicable, monitoring may include: - sensory testing of seafood for taint, and chemical analysis for oil concentrations and any other contaminants, as applicable; - measuring levels of contamination in recreational and commercial fish species with results integrated into a human health risk assessment to determine the fishing area closure status; - monitoring for marine mammals, sea turtles and birds for visible signs of contamination or oiling and reporting results to the Board. At time of incident, if occurs To be determined in consultation with regulatory agencies / experts BP has put measures in place to prevent an incident and has developed a comprehensive suite of project-specific emergency response plans and other contingency plans including technical and activity based contingency plans/documents designed to meet incident and emergency response scenarios that may arise during the project. These plans include: Environmental Protection Plan Incident Management Plan Spill Response Plan Wildlife Response Plan Spill Impact Mitigation Assessment (i.e. "net environmental benefit analysis") ROV Intervention System for Emergency BOP Activation Plan Capping and Containment Response Plan Relief Well Plan These plans have been submitted to the CNSOPB. Many of the plans have undergone review and have been updated accordingly. These plans are living documents and may be updated as required. Refer to incident/spill notification procedures with the Incident Management Plan and Spill Response Plan. Latest version of (Oil) Spill Response Plan is located on the BP Nova Scotia website (reference 2.9 above). Page 3 of 5 Revision 1.0

4 Scotian Basin Exploration Project - Aspy D In the event of a sub-sea well blowout, the Proponent shall, in addition to condition 6.9, begin the immediate mobilization of at least one capping stack and associated equipment to the project area to stop the spill. In the event of a sub-sea well blowout, BP shall, in addition to condition 6.9, begin the immediate mobilization of at least one capping stack and associated equipment to the project area to stop the spill. 2 Capping and containment is addressed within the BP Spill Response Plan and BP Capping and Containment Response Plan In the event of accidents and malfunctions, the Proponent shall comply with the Compensation Guidelines Respecting Damages Relating to Offshore Petroleum Activity issued jointly by the Canada-Newfoundland and Labrador Offshore Petroleum Board and the Canada-Nova Scotia Offshore Petroleum Board. In the event of accidents and malfunctions, BP shall comply with the Compensation Guidelines Respecting Damages Relating to Offshore Petroleum Activity issued jointly by the Canada-Newfoundland and Labrador Offshore Petroleum Board and the Canada-Nova Scotia Offshore Petroleum Board. 7-Mar-18 BP to act in a responsible manner for the life of the proposed work. Evidence of financial responsibility was submitted to the Board on March 7, Resources will be put in place prior to the CNSOPB issuing an Operations Authorization. Issuance of Operations Authorization to evidence that financial responsibility and resources are in place. WELL TESTING PHASE The Proponent shall notify the Board at least 30 days in advance of planned flaring to determine whether the flaring would occur during a period of migratory bird vulnerability and how the Proponent plans to avoid adverse environmental effects on migratory birds. 4.2 BP shall notify the Board at least 30 days in advance of planned flaring to determine whether the flaring would occur during a period of migratory bird vulnerability and how BP plans to avoid adverse environmental effects on migratory birds. Well Testing N/A N/A No flaring (well testing) for the exploration well. 4.3 The Proponent shall implement measures to avoid harming, killing or disturbing migratory birds, including: BP shall implement measures to avoid harming, killing or disturbing migratory birds, including: restricting flaring to the minimum required to characterize the wells hydrocarbon potential and as necessary - restricting flaring to the minimum required to characterize the wells hydrocarbon potential and as necessary for the for the safety of the operation; safety of the operation; minimizing flaring during night time and during periods of migratory bird vulnerability; - minimizing flaring during night time and during periods of migratory bird vulnerability; operating a water-curtain barrier around the flare during flaring. - operating a water-curtain barrier around the flare during flaring. Well Testing N/A N/A No flaring (well testing) for the exploration well. WELL SUSPENSION/ABANDONMENT PHASE The Proponent shall, within 90 days after each well is suspended and/or abandoned, submit to the Board and the Agency a report, including an executive summary of the report in both official languages. The Proponent shall document in the report: the activities undertaken by the Proponent to comply with each of the conditions set out in this Decision Statement; how the Proponent complied with condition 2.1; for conditions set out in this Decision Statement for which consultation is a requirement, how the Proponent considered any views and information that the Proponent received during or as a result of the consultation; the follow-up information referred to in conditions 2.4 and 2.5; the results of the follow-up requirements identified in conditions 3.12, 3.13 and 4.5; any modified or additional mitigation measures implemented or proposed to be implemented by the Proponent, as determined under condition BP shall, within 90 days after each well is suspended and/or abandoned, submit to the Board and the Agency a report, including an executive summary of the report in both official languages. The Proponent shall document in the report: - the activities undertaken by the Proponent to comply with each of the conditions set out in this Decision Statement; - how the Proponent complied with condition 2.1; - for conditions set out in this Decision Statement for which consultation is a requirement, how the Proponent considered any views and information that the Proponent received during or as a result of the consultation; - the follow-up information referred to in conditions 2.4 and 2.5; - the results of the follow-up requirements identified in conditions 3.12, 3.13 and 4.5; - any modified or additional mitigation measures implemented or proposed to be implemented by the Proponent, as determined under condition Apr-18 BP will compile the final report, due 90 days after the Aspy D-11 well is abandoned. It will include an executive summary in both official languages. The final report will address all items outlined within The Proponent shall develop a well abandonment plan, including a wellhead abandonment strategy, and submit it BP shall develop a well abandonment plan, including a wellhead abandonment strategy, and submit it to the Board for to the Board for acceptance at least 30 days prior to abandonment of each well. If the Proponent proposes that a acceptance at least 30 days prior to abandonment of the well. If BP proposes that a wellhead be abandoned on the wellhead be abandoned on the seafloor in a manner that may interfere with Indigenous and commercial fisheries, seafloor in a manner that may interfere with Indigenous and commercial fisheries, BP shall develop the wellhead the Proponent shall develop the wellhead abandonment strategy in consultation with Indigenous and commercial abandonment strategy in consultation with Indigenous and commercial fishers. fishers. 23-Mar Mar-18 The well abandonment plan has been including in Section 10 of the Aspy D-11 Approval to Drill a Well submitted to the Board on March 23, The well abandonment strategy has been posted to the BP Nova Scotia website as part of The proponent shall provide Indigenous groups with the results of the pre-drill surveys referred to in condition 3.6 and the results of the activities undertaken as part of the marine mammal observation requirements referred to in condition 3.9 within 90 days after each well is suspended and/or abandoned. BP shall provide Indigenous groups with the results of the pre-drill surveys referred to in condition 3.6 and the results of the activities undertaken as part of the marine mammal observation requirements referred to in condition 3.9 within 90 days after each well is suspended and/or abandoned. 22-Apr-18 Acknowledged. No action until 90 days after well suspended or abandoned. 2.1 ALL PHASES The Proponent shall ensure that its actions in meeting the conditions set out in this Decision Statement are BP shall ensure that its actions in meeting the conditions set out in this Decision Statement are considered in a careful and considered in a careful and precautionary manner, promote sustainable development, are informed by the best precautionary manner, promote sustainable development, are informed by the best information and knowledge available at information and knowledge available at the time the Proponent takes action, including community and Indigenous the time BP takes action, including community and Indigenous traditional knowledge, are based on methods and models traditional knowledge, are based on methods and models that are recognized by standard-setting bodies, are that are recognized by standard-setting bodies, are undertaken by qualified individuals, and have applied the best available undertaken by qualified individuals, and have applied the best available economically and technically feasible economically and technically feasible technologies. technologies. 30-May-16 BP is working to meet all the conditions in this Decision Statement and is drawing on its own expertise operating in various offshore regions around the globe, the local expertise and lessons learned in Atlantic Canada by other operators and regulators, and community and traditional knowledge provided by stakeholders and Indigenous groups to understand the best information and knowledge available including best management practices, industry standards, recognized methods and models, and available economically and technically feasible technologies. BP will operate in a careful and precautionary manner and, where applicable, will look for opportunities to promote sustainable development in their operations. BP incorporated community and Indigenous traditional knowledge to meet conditions set out in the Decision Statement. The Traditional Use Study was informed by the best information and knowledge available and based on methods and models that have been recognized and promoted by Indigenous communities in the region. 2.2 The Proponent shall, where consultation is a requirement of a condition set out in this Decision Statement: provide a written notice of the opportunity for the party or parties being consulted to present their views and information on the subject of the consultation; provide sufficient information on the scope and the subject matter of the consultation and a reasonable period of time to permit the party or parties being consulted to prepare their views and information; undertake impartial consideration of all views and information presented by the party or parties being consulted on the subject matter of the consultation; advise in a timely manner the party or parties being consulted on how the views and information received have been considered by the Proponent. BP shall, where consultation is a requirement of a condition set out in this Decision Statement: - provide a written notice of the opportunity for the party or parties being consulted to present their views and information on the subject of the consultation; - provide sufficient information on the scope and the subject matter of the consultation and a reasonable period of time to permit the party or parties being consulted to prepare their views and information; - undertake impartial consideration of all views and information presented by the party or parties being consulted on the subject matter of the consultation; - advise in a timely manner the party or parties being consulted on how the views and information received have been considered by BP. 3-Nov-17 In advance of receiving the Decision Statement, BP started making arrangements to consult with Indigenous groups on proposed conditions. Requests for meetings were sent to the KMKNO, Sipekne'katik First Nation, Millbrook First Nation, the Mi'kmaq First Nations of Prince Edward Island represented by the Mi'kmaq Confederacy of Prince Edward Island (MCPEI), the Mi'kmaq First Nations in New Brunswick represented by Mi'gmawe'l Tplu'taqnn Incorporated (MTI), the First Nations represented by the Wolastoqey Nation in New Brunswick (WNNB), and Woodstock First Nation in January BP met with all groups indicating a desire to meet including the KMKNO on February 6, 2018 and February 23, 2018, Sipekne'katik First Nation on February 2, 2018, WNNB (and Woodstock First Nation) on February 21, 2018 and MTI on February 26, In advance of these meetings, a draft agenda and informational handouts were distributed via . As part of follow-up after the meetings, presentation slides were ed to each group and any outstanding questions addressed. Informational handouts were also ed to MCPEI and Millbrook First Nation. Consultation will continue through the drilling program (including sharing of follow-up program results) and views and information received will be considered, with consulted parties advised on how their views and information have been considered. BP has continued to consult with non-indigenous fishers via the Fisheries Advisory Committee (FAC) since the planning phases of the project. Refer to response provided in 5.1. Page 4 of 5 Revision 1.0

Scotian Basin Exploration Project - Aspy D11 CEAA Condition #

Scotian Basin Exploration Project - Aspy D11 CEAA Condition # On February 1, 2018 the Decision Statement issued under Section 54 of the Canadian Environmental Assessment Act, 2012 () for the BP Canada Energy Group ULC ("BP") Scotian Basin Exploration Drilling Project

More information

to BP Canada Energy Group ULC c/o Anita Perry, Regional Manager, Atlantic Canada

to BP Canada Energy Group ULC c/o Anita Perry, Regional Manager, Atlantic Canada Decision Statement Issued under Section 54 of the Canadian Environmental Assessment Act, 2012 to BP Canada Energy Group ULC c/o Anita Perry, Regional Manager, Atlantic Canada 10 th Floor Founders Square

More information

Draft Potential Conditions

Draft Potential Conditions Draft Potential Conditions The following potential conditions in relation to the Shelburne Basin Venture Exploration Drilling Project (the Designated Project) are being considered by the Canadian Environmental

More information

Campaign 1: Cheshire Well (#1) 01-Jun Jul-21

Campaign 1: Cheshire Well (#1) 01-Jun Jul-21 On June 15, 2015, Shell received the Decision Statement Issued under Section 54 of the Canadian Environmental Assessment Act, 2012 () for the Shelburne Basin Venture Exploration Drilling Project (the Project).

More information

Campaign 1: Monterey Jack (#2)

Campaign 1: Monterey Jack (#2) On June 15, 2015, Shell received the Decision Statement Issued under Section 54 of the Canadian Environmental Assessment Act, 2012 (CEAA) for the Shelburne Basin Venture Exploration Drilling Project (the

More information

Campaign 1: Cheshire Well (#1) 01-Jun Sep-16

Campaign 1: Cheshire Well (#1) 01-Jun Sep-16 On June 15, 2015, Shell received the Decision Statement Issued under Section 54 of the Canadian Environmental Assessment Act, 2012 () for the Shelburne Basin Venture Exploration Project (the Project).

More information

Campaign 1: Cheshire (Well #1) 01-Jun Sep-16

Campaign 1: Cheshire (Well #1) 01-Jun Sep-16 On June 15, 2015, Shell received the Decision Statement Issued under Section 54 of the Canadian Environmental Assessment Act, 2012 () for the Shelburne Basin Venture Exploration Project (the Project).

More information

Scotian Basin Exploration Drilling Project: Timeline

Scotian Basin Exploration Drilling Project: Timeline Scotian Basin Exploration Drilling Project: Timeline When it comes to exploratory drilling programs that an operator proposes to conduct, the Canada- Nova Scotia Offshore Petroleum Board (CNSOPB) goes

More information

Written Comment: Sydney Basin and Orpheus Graben Areas

Written Comment: Sydney Basin and Orpheus Graben Areas December 23, 2015 Written Comment: Sydney Basin and Orpheus Graben Areas Based on the draft Strategic Environmental Assessment 202 Brownlow Ave. Suite A305, Cambridge 1 Dartmouth, NS B3B 1T5 (902) 425-4774

More information

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015 Well Control Contingency Plan Guidance Note (version 2) 02 December 2015 Prepared by Maritime NZ Contents Introduction... 3 Purpose... 3 Definitions... 4 Contents of a Well Control Contingency Plan (WCCP)...

More information

Oil & Gas Activity in the Canadian Arctic and Eastern Canada Activity

Oil & Gas Activity in the Canadian Arctic and Eastern Canada Activity Oil & Gas Activity in the Canadian Arctic and Eastern Canada Activity Keith Landra - Chief Safety Officer with contributions by: Paul Alexander, Chief Safety Officer, Robert Normore, Chief Safety Officer,

More information

WHITE ROSE OILFIELD COMPREHENSIVE STUDY REPORT SUBMITTED BY:

WHITE ROSE OILFIELD COMPREHENSIVE STUDY REPORT SUBMITTED BY: WHITE ROSE OILFIELD COMPREHENSIVE STUDY REPORT SUBMITTED BY: HUSKY OIL OPERATIONS LIMITED (AS OPERATOR) SUITE 801, SCOTIA CENTRE 235 WATER STREET ST. JOHN S, NF, A1C 1B6 TEL: (709) 724-3900 FAX: (709)

More information

Report of the Commissioner of the Environment and Sustainable Development

Report of the Commissioner of the Environment and Sustainable Development Fall 2012 Report of the Commissioner of the Environment and Sustainable Development CHAPTER 1 Atlantic Offshore Oil and Gas Activities Office of the Auditor General of Canada The Report is available on

More information

NEXEN ENERGY ULC Eastern Newfoundland Offshore Geophysical, Geochemical, Environmental and Geotechnical Program ( )

NEXEN ENERGY ULC Eastern Newfoundland Offshore Geophysical, Geochemical, Environmental and Geotechnical Program ( ) NEXEN ENERGY ULC Eastern Newfoundland Offshore Geophysical, Geochemical, Environmental and Geotechnical Program (2018-2027) Environmental Assessment Project Description Submitted by: 801-7th Avenue SW

More information

Click to edit Master title style APPEA AWIC UPDATE. Self Audit Checklist Source Control First Response

Click to edit Master title style APPEA AWIC UPDATE. Self Audit Checklist Source Control First Response APPEA AWIC UPDATE Click to edit Mutual Master Aid subtitle style Self Audit Checklist Source Control First Response Presenter: Tom Nolan Perth 1st 4 th March, 2010 2012 WHAT IS APPEA? The Australian Petroleum

More information

Otway Gas Development Seabed Assessment and Drilling Program

Otway Gas Development Seabed Assessment and Drilling Program Otway Gas Development Seabed Assessment and Drilling Program 2018 2019 Information Sheet The unique geological characteristics of the Otway Basin mean it is an abundant source of natural gas which has

More information

RE: 13UN034 City of Iqaluit New Landfill and Waste Transfer Station NIRB Screening

RE: 13UN034 City of Iqaluit New Landfill and Waste Transfer Station NIRB Screening Environmental Protection Operations Directorate Prairie & Northern Region 5019 52 nd Street, 4 th Floor File: 6200 000 001/009 P.O. Box 2310 NIRB File: 13UN034 Yellowknife, NT X1A 2P7 January 10, 2019

More information

Advancing Global Deepwater Capabilities

Advancing Global Deepwater Capabilities Advancing Global Deepwater Capabilities BP s Commitment The Deepwater Horizon incident was a tragic accident that took 11 lives and impacted thousands of people and the Gulf environment Going forward,

More information

Aboriginal Consultation and Environmental Assessment Handout CEAA November 2014

Aboriginal Consultation and Environmental Assessment Handout CEAA November 2014 Introduction The Government of Canada consults with Aboriginal peoples for a variety of reasons, including: statutory and contractual obligations, policy and good governance, building effective relationships

More information

4 Briefing. Responsible investor

4 Briefing. Responsible investor Issue Responsible investor 4 Briefing Wednesday 8 th February 2012 In 2010, we accepted all 26 recommendations made by the Bly Report our internal investigation into the Deepwater Horizon incident. BP

More information

Scoping of Impact Assessment in Canada Are We Losing our Focus?

Scoping of Impact Assessment in Canada Are We Losing our Focus? Scoping of Impact Assessment in Canada Are We Losing our Focus? Earle Hickey, M. Sc. and Heather Giddens, MES Stantec Consulting Ltd. Dartmouth, Nova Scotia Canada Introduction Scoping is a critical component

More information

SPECIES PROTECTION CONSTRUCTION Protective Radius

SPECIES PROTECTION CONSTRUCTION Protective Radius SPECIES PROTECTION Attention is directed to the existence of environmental work restrictions that require special precautions to be taken by the Contractor to protect the species of concern in conforming

More information

4 CONSULTATION WITH INTERESTED AND AFFECTED PARTIES

4 CONSULTATION WITH INTERESTED AND AFFECTED PARTIES 4 CONSULTATION WITH INTERESTED AND AFFECTED PARTIES This Chapter describes the process that was followed to notify, consult, and consider the input of Interested and Affected Parties (I&APs). Figure 4.1

More information

Further Submissions Form Proposed Coastal Plan for Taranaki

Further Submissions Form Proposed Coastal Plan for Taranaki Further Submissions Form Proposed Coastal Plan for Taranaki Your details Name: Joshua K. O Rourke Organisation: Petroleum Exploration and Production Association of New Zealand Address: Level 6, 5 Willeston

More information

EIA FOR EXPLORATION DRILLING WITHIN BLOCK ER236, OFFSHORE OF THE EAST COAST OF SOUTH AFRICA. Background Information Document. Purpose of this Document

EIA FOR EXPLORATION DRILLING WITHIN BLOCK ER236, OFFSHORE OF THE EAST COAST OF SOUTH AFRICA. Background Information Document. Purpose of this Document Background Information Document EIA FOR EXPLORATION DRILLING WITHIN BLOCK ER236, OFFSHORE OF THE EAST COAST OF SOUTH AFRICA Purpose of this Document Eni South Africa BV (Eni), and Sasol Africa Limited

More information

Gulf of St Lawrence: Industry Challenges and Response

Gulf of St Lawrence: Industry Challenges and Response Gulf of St Lawrence: Industry Challenges and Response Paul Barnes Manager, Atlantic Canada Canadian Association of Petroleum Producers October 19, 2011 History of Exploration in the Gulf of St. Lawrence

More information

3 ASSESSMENT METHODOLOGY

3 ASSESSMENT METHODOLOGY 3 ASSESSMENT METHODOLOGY Methods of effects assessment conform with the requirements of CEAA and its associated guidance documents (CEAA 1994a; 1997; 1998a; 1998b). They are generally comparable to those

More information

BETWEEN. Her Majesty the Queen in Right of Canada, as represented by the Minister of Fisheries and Oceans AND

BETWEEN. Her Majesty the Queen in Right of Canada, as represented by the Minister of Fisheries and Oceans AND Memorandum of Understanding to advance measures to benefit the recovery of the Southern Resident Killer Whale through Trans Mountain Expansion Project Conditions BETWEEN Her Majesty the Queen in Right

More information

Introductory remarks

Introductory remarks Introductory remarks This document is a draft of a permit for Gaz System to construct a natural gas pipeline on the Danish continental shelf in the Baltic Sea. It should be emphasised that it has not yet

More information

Overview of the C-NLOPB and the Can-NL Offshore Oil and Gas Industry. Sean Kelly MA, APR, FCPRS May 15, 2017

Overview of the C-NLOPB and the Can-NL Offshore Oil and Gas Industry. Sean Kelly MA, APR, FCPRS May 15, 2017 Overview of the C-NLOPB and the Can-NL Offshore Oil and Gas Industry Sean Kelly MA, APR, FCPRS May 15, 2017 Safety Moment - Working in the harshest environment in the world demands the highest regard for

More information

APPENDIX A ANNUAL COMPLIANCE REPORT CONDITION REQUIREMENTS CONDITION 4.0

APPENDIX A ANNUAL COMPLIANCE REPORT CONDITION REQUIREMENTS CONDITION 4.0 APPENDIX A ANNUAL COMPLIANCE REPORT CONDITION REQUIREMENTS CONDITION 4.0 Condition 4: Migratory Birds 4.1.1 The Proponent shall carry out all phases of the Designated Project in a manner that avoids harming

More information

SUMMARY REPORT AND RECOMMENDATIONS ON THE PREVENTION OF MARINE OIL POLLUTION IN THE ARCTIC.

SUMMARY REPORT AND RECOMMENDATIONS ON THE PREVENTION OF MARINE OIL POLLUTION IN THE ARCTIC. Arctic Council Open Access Repository Arctic Council http://www.arctic-council.org/ 1.8 Sweden Chairmanship I (May 2011 - May 2013) 4. SAO Meeting, March 2013, Stockholm, Sweden SUMMARY REPORT AND RECOMMENDATIONS

More information

Re: Amendment proposal for the Regulations Designating Physical Activities and the Prescribed Information Regulations

Re: Amendment proposal for the Regulations Designating Physical Activities and the Prescribed Information Regulations August 22, 2012 John McCauley Director, Legislative and Regulatory Affairs Canadian Environmental Assessment Agency 22nd Floor, Place Bell 160 Elgin Street Ottawa, ON K1A 0H3 RegulationsReglements2012@ceaa-acee.gc.ca

More information

NATIONAL POLICY ON OILED BIRDS AND OILED SPECIES AT RISK

NATIONAL POLICY ON OILED BIRDS AND OILED SPECIES AT RISK NATIONAL POLICY ON OILED BIRDS AND OILED SPECIES AT RISK January 2000 Environment Canada Canadian Wildlife Service Environnement Canada Service canadien de la faune Canada National Policy on Oiled Birds

More information

Encana Corporation Expression of Interest (EOI)

Encana Corporation Expression of Interest (EOI) Encana Corporation Expression of Interest (EOI) HARSH ENVIRONMENT JACK-UP, MOBILE OFFSHORE DRILLING UNIT (MODU) BIDS Category: 0420 Reference: EOI DC01 Issue Date: May 18, 2017 Closing Date: June 8, 2017

More information

New Developments in Regulation of U.S. Offshore Oil and Gas Operations

New Developments in Regulation of U.S. Offshore Oil and Gas Operations New Developments in Regulation of U.S. Offshore Oil and Gas Operations Peking University Law School and The University of Texas School of Law Carol Dinkins Partner Vinson & Elkins, LLP August 21, 2012

More information

Guide to Preparing an Application for Permit under the Marine Renewable-energy Act

Guide to Preparing an Application for Permit under the Marine Renewable-energy Act Updated February 2018 Guide to Preparing an Application for Permit under the Marine Renewable-energy Act Document Information Disclaimer The Guide to Preparing an Application for Permit under the Marine

More information

Veterans and Offshore Drilling

Veterans and Offshore Drilling Veterans and Offshore Drilling Why care, what it entails, and is it safe. Meeting begins at 3:00 PM Eastern Offshore Oil and Natural Gas Briefing Erik Milito Director, Upstream & Industry Operations American

More information

Emerging Subsea Networks

Emerging Subsea Networks FIBRE-TO-PLATFORM CONNECTIVITY, WORKING IN THE 500m ZONE Andrew Lloyd (Global Marine Systems Limited) Email: andrew.lloyd@globalmarinesystems.com Global Marine Systems Ltd, New Saxon House, 1 Winsford

More information

Roberts Bank Terminal 2 Project Field Studies Information Sheet

Roberts Bank Terminal 2 Project Field Studies Information Sheet May 2013 Port Metro Vancouver is continuing field studies in May as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project. Roberts Bank Terminal 2 Project The

More information

ENVIRONMENTAL ASSESSMENT (EA) PROCESS

ENVIRONMENTAL ASSESSMENT (EA) PROCESS ENVIRONMENTAL ASSESSMENT (EA) PROCESS THE PROJECT Emera Newfoundland & Labrador (ENL) is seeking environmental regulatory approvals to construct and operate the Maritime Link Transmission Project between

More information

Husky White Rose Development Project. New Drill Centre Construction & Operations Program. Project Description

Husky White Rose Development Project. New Drill Centre Construction & Operations Program. Project Description Husky White Rose Development Project New Drill Centre Construction & Operations Program Prepared by: Husky Oil Operations Limited 235 Water Street St. John s, NL A1C 1B6 January 13 th, 2006 HDMS ID: 003967343,

More information

Marine Renewable-energy Application

Marine Renewable-energy Application Marine Renewable-energy Application OFFICE USE ONLY Date Received: Application #: Time Received: Date of Complete Application: Received by: Processed by: Type of Application Permit (unconnected) Permit

More information

15. SUMMARY OF RECOMMENDATIONS

15. SUMMARY OF RECOMMENDATIONS Summary of Recommendations 93 15. SUMMARY OF RECOMMENDATIONS The following is a restatement of each of the Panel s recommendations as contained in the main body of the report. For ease of reference, the

More information

NTL No N06 Information Requirements for EPs, DPPs and DOCDs on the OCS Effective June 18, 2010

NTL No N06 Information Requirements for EPs, DPPs and DOCDs on the OCS Effective June 18, 2010 NTL No. 2010-N06 Information Requirements for EPs, DPPs and DOCDs on the OCS Effective June 18, 2010 Frequently Asked Questions (FAQ s) Updated July 15, 2010 Updated July 21, 2010 1. Q. What OCS areas

More information

Petroleum Safety Levy Methodology. Decision Paper

Petroleum Safety Levy Methodology. Decision Paper Petroleum Safety Levy Methodology Decision Paper DOCUMENT TYPE: REFERENCE: Decision Paper CER/14/429 DATE PUBLISHED: 7 th August 2014 VERSION 3.0 The Commission for Energy Regulation, The Exchange, Belgard

More information

HSE and Quality. Sisimiut, 10th December FING: Arctic Region Oil & Gas Seminar in Training and Education

HSE and Quality. Sisimiut, 10th December FING: Arctic Region Oil & Gas Seminar in Training and Education HSE and Quality Sisimiut, 10th December 2013 FING: Arctic Region Oil & Gas Seminar in Training and Education 1 Arctic Issues Above ground challenges FING: Arctic Region Oil & Gas Seminar in Training and

More information

Esso offshore projects

Esso offshore projects Esso offshore projects Introduction Esso Australia, a subsidiary of ExxonMobil Australia, is undertaking a program of work across some of its offshore assets, including those owned jointly by the Gippsland

More information

Enabling Local Innovation. Scott Tessier, Chair and Chief Executive Officer NewLeef, October 2016

Enabling Local Innovation. Scott Tessier, Chair and Chief Executive Officer NewLeef, October 2016 Enabling Local Innovation? Scott Tessier, Chair and Chief Executive Officer NewLeef, October 2016 SAFETY MOMENT: Working in the harshest environment in the world demands the highest regard for safety Everything

More information

Construction Contracts Administration Oregon State University, 644 SW 13th Street, Corvallis, OR T F

Construction Contracts Administration Oregon State University, 644 SW 13th Street, Corvallis, OR T F Construction Contracts Administration Oregon State University, 644 SW 13th Street, Corvallis, OR 97333 T 541-737-0922 F 541-737-5546 June 29, 2017 Oregon State University Construction Contracts Administration

More information

One Ocean Oil Spill Prevention and Response Initiative: Application of Gulf of Mexico Key Findings to the Newfoundland and Labrador Region

One Ocean Oil Spill Prevention and Response Initiative: Application of Gulf of Mexico Key Findings to the Newfoundland and Labrador Region One Ocean Oil Spill Prevention and Response Initiative: Application of Gulf of Mexico Key Findings to the Newfoundland and Labrador Region Report Released October 2017 ONE OCEAN CORPORATION 155 Ridge Road

More information

Interspill UK Response Readiness. Mick Borwell Environmental Issues Director Oil & Gas UK

Interspill UK Response Readiness. Mick Borwell Environmental Issues Director Oil & Gas UK Interspill 2012 UK Response Readiness Mick Borwell Environmental Issues Director 20 April 2010 will be a date forever etched on the collective memory of the oil industry. This was the night that a massive

More information

Advancing Global Deepwater Capabilities

Advancing Global Deepwater Capabilities Advancing Global Deepwater Capabilities BP s commitments Determined to accelerate and further deploy the capabilities and practices that enhance safety in our company and the deepwater industry 200+ meetings

More information

Re: Scheduling of a Project Certificate Workshop for TMAC Resources Inc. s Phase 2 Hope Bay Belt Project week of October 29, 2018

Re: Scheduling of a Project Certificate Workshop for TMAC Resources Inc. s Phase 2 Hope Bay Belt Project week of October 29, 2018 NIRB File No.: 12MN001 NWB File No. 2AM-DOH1323 and 2AM-BOS---- October 15, 2018 To: Phase 2 Hope Bay Belt Distribution List Sent via email Re: Scheduling of a Project Certificate Workshop for TMAC Resources

More information

Industry & Govt Changes Post Macondo. Charlie Williams Chief Scientist Shell Executive Director - Center for Offshore Safety

Industry & Govt Changes Post Macondo. Charlie Williams Chief Scientist Shell Executive Director - Center for Offshore Safety Industry & Govt Changes Post Macondo Charlie Williams Chief Scientist Shell Executive Director - Center for Offshore Safety 1 Deepwater Industry Focus/Approach Joint Industry Task Force Groups Offshore

More information

Marine biological diversity of areas beyond national jurisdiction. Legal and policy framework

Marine biological diversity of areas beyond national jurisdiction. Legal and policy framework Marine biological diversity of areas beyond national jurisdiction Legal and policy framework 1. The United Nations Convention on the Law of the Sea (UNCLOS) provides the legal framework within which all

More information

clarify the roles of the Department and minerals industry in consultation; and

clarify the roles of the Department and minerals industry in consultation; and Procedures for Crown Consultation with Aboriginal Communities on Mineral Exploration Mineral Resources Division, Manitoba Science, Technology, Energy and Mines The Government of Manitoba recognizes it

More information

Goal: Effective Decision Making

Goal: Effective Decision Making Goal: Effective Decision Making Objective 1. Enhance inter-agency coordination Focus on aspects of governmental decision-making (NEPA and other existing siting/regulatory programs) related to marine energy

More information

Spill Prevention and Spill Response. Canada-Newfoundland and Labrador Offshore Petroleum Board

Spill Prevention and Spill Response. Canada-Newfoundland and Labrador Offshore Petroleum Board Spill Prevention and Spill Response BOP Stack Containment Boom Legislative Requirements Regulations Drilling and Production Regulations Certificate of Fitness Oil and Gas Debris and Spills Liability Petroleum

More information

Empire Wind Offshore Wind Farm OCS-A 0512

Empire Wind Offshore Wind Farm OCS-A 0512 Empire Wind Offshore Wind Farm OCS-A 0512 Fisheries Liaison & Outline Classification: Open Status: Draft Expiry date: 28-07-04 Page 1 of 13 Title: Empire Wind Fisheries Liaison & Outline Document no. :

More information

OCS leasing program draft PEIS comments Attachment A

OCS leasing program draft PEIS comments Attachment A Effective Oversight Requires Key Legislative, Regulatory, Enforcement and Transparency Upgrades Analysis by Lois N. Epstein, P.E. Engineer and Arctic Program Director The Wilderness Society Anchorage,

More information

AADE Houston Chapter. Group. 26 January 2011

AADE Houston Chapter. Group. 26 January 2011 AADE Houston Chapter Deepwater and Emerging Technologies Group 26 January 2011 BOEMRE Compliance Guidelines Department of Interior s Increased Safety Measures for Energy Development on the Outer Continental

More information

DNVGL-CP-0338 Edition October 2015

DNVGL-CP-0338 Edition October 2015 CLASS PROGRAMME DNVGL-CP-0338 Edition October 2015 The electronic pdf version of this document, available free of charge from http://www.dnvgl.com, is the officially binding version. FOREWORD DNV GL class

More information

RECOGNIZING also that other factors such as habitat loss, pollution and incidental catch are seriously impacting sea turtle populations;

RECOGNIZING also that other factors such as habitat loss, pollution and incidental catch are seriously impacting sea turtle populations; Conf. 9.20 (Rev.) * Guidelines for evaluating marine turtle ranching proposals submitted pursuant to Resolution Conf..6 (Rev. CoP5) RECOGNIZING that, as a general rule, use of sea turtles has not been

More information

121 W. Fireweed Lane, Suite L Street, NW Anchorage, Alaska Washington, DC Phone: (907) Phone: (202)

121 W. Fireweed Lane, Suite L Street, NW Anchorage, Alaska Washington, DC Phone: (907) Phone: (202) Alaska Oil and Gas Association American Petroleum Institute 121 W. Fireweed Lane, Suite 207 1220 L Street, NW Anchorage, Alaska 99503-2035 Washington, DC 20005 Phone: (907) 272-1481 Phone: (202)682-8000

More information

RESOLUTION MEPC.290(71) (adopted on 7 July 2017) THE EXPERIENCE-BUILDING PHASE ASSOCIATED WITH THE BWM CONVENTION

RESOLUTION MEPC.290(71) (adopted on 7 July 2017) THE EXPERIENCE-BUILDING PHASE ASSOCIATED WITH THE BWM CONVENTION RESOLUTION MEPC.290(71) (adopted on 7 July 2017) RESOLUTION MEPC.290(71) (adopted on 7 July 2017) ANNEX 12 RESOLUTION MEPC.290(71) (adopted on 7 July 2017) MEPC 71/17/Add.1 Annex 12, page 1 THE MARINE

More information

Block Offer 2014 Awards Questions and Answers... 1

Block Offer 2014 Awards Questions and Answers... 1 Block Offer 2014 Awards Questions and Answers December, 2014 Contents Block Offer 2014 Awards Questions and Answers... 1 What is a Block Offer?... 2 When did Block Offer 2014 open?... 2 How are bids assessed?...

More information

STAKEHOLDER INFORMATION

STAKEHOLDER INFORMATION SEPTEMBER 2017 2018 OFFSHORE CAMPAIGN STAKEHOLDER INFORMATION This information sheet provides an overview of Cooper Energy s proposed drilling, abandonment and pipelay activities in 2018 off the Victorian

More information

STATEMENT OF WORK Environmental Assessment for the Red Cliffs/Long Valley Land Exchange in Washington County, Utah

STATEMENT OF WORK Environmental Assessment for the Red Cliffs/Long Valley Land Exchange in Washington County, Utah I. Introduction STATEMENT OF WORK Environmental Assessment for the Red Cliffs/Long Valley Land Exchange in Washington County, Utah The Bureau of Land Management s (BLM) St. George Field Office (SGFO) requires

More information

JOINT INDUSTRY OFFSHORE OPERATING PROCEDURES TASK FORCE, JOINT INDUSTRY OFFSHORE EQUIPMENT TASK FORCE, JOINT INDUSTRY SUBSEA WELL CONTROL AND

JOINT INDUSTRY OFFSHORE OPERATING PROCEDURES TASK FORCE, JOINT INDUSTRY OFFSHORE EQUIPMENT TASK FORCE, JOINT INDUSTRY SUBSEA WELL CONTROL AND JOINT INDUSTRY OFFSHORE OPERATING PROCEDURES TASK FORCE, JOINT INDUSTRY OFFSHORE EQUIPMENT TASK FORCE, JOINT INDUSTRY SUBSEA WELL CONTROL AND CONTAINMENT TASK FORCE, and JOINT INDUSTRY OIL SPILL PREPAREDNESS

More information

Draft Myanmar Environmental Impact Assessment (EIA) Procedures: Comments 1 on aspects relevant to Offshore Oil and Gas Exploration and Production

Draft Myanmar Environmental Impact Assessment (EIA) Procedures: Comments 1 on aspects relevant to Offshore Oil and Gas Exploration and Production Draft Myanmar Environmental Impact Assessment (EIA) Procedures: Comments 1 on aspects relevant to Offshore Oil and Gas Exploration and Production Appropriate EIA phasing for Petroleum E&P Activities According

More information

RV Investigator Voyage Deliverables

RV Investigator Voyage Deliverables Voyage Deliverables April 2016 CONTENTS 1. Purpose... 1 2. Background... 1 3. Marine National Facility (MNF)... 1 4.... 1 4.1. MNF Granted Voyages (GV)... 2 4.2. MNF User-Funded Voyages (UFV)... 2 5. Governance...

More information

ACOUSTIC MONITORING PLAN

ACOUSTIC MONITORING PLAN ACOUSTIC MONITORING PLAN BP Scotian Basin Exploration Project Prepared by: JASCO Applied Sciences (Canada) Ltd. Suite 202, 32 Troop Ave. Dartmouth, NS B3B 1Z1 Canada Tel: +1-902-405-3336 Fax: +1-902-405-3337

More information

Final Prospectus and Terms of Reference for an Independent Review of the New England Fishery Management Council 2/27/18

Final Prospectus and Terms of Reference for an Independent Review of the New England Fishery Management Council 2/27/18 Final Prospectus and Terms of Reference for an Independent Review of the New England Fishery Management Council 2/27/18 The New England Fishery Management Council (NEFMC, Council) has initiated an independent

More information

Humboldt Bay Piling Removal

Humboldt Bay Piling Removal REQUEST FOR PROPOSALS Humboldt Bay Piling Removal Invitation for Proposals The Humboldt Bay Harbor, Recreation & Conservation District (District) is requesting proposals from qualified individuals/firms

More information

Passive Acoustic Monitoring for Cetaceans Across the Continental Shelf off Virginia: 2016 Annual Progress Report

Passive Acoustic Monitoring for Cetaceans Across the Continental Shelf off Virginia: 2016 Annual Progress Report Passive Acoustic Monitoring for Cetaceans Across the Continental Shelf off Virginia: Submitted to: Naval Facilities Engineering Command Atlantic under Contract No. N62470-15-D-8006, Task Order 032. Prepared

More information

Deep Panuke. 01U Issued for Use M. Thillet N. Coonan D. Riffe A. Wylde Rev Date Reason for Issue Prepared Checked Approved Approved Title

Deep Panuke. 01U Issued for Use M. Thillet N. Coonan D. Riffe A. Wylde Rev Date Reason for Issue Prepared Checked Approved Approved Title Deep Panuke 01U 2009-04-29 Issued for Use M. Thillet N. Coonan D. Riffe A. Wylde Rev Date Reason for Issue Prepared Checked Approved Approved Title 2009 Wellhead Protection Structures Installation Environmental

More information

PEPANZ submission: Managing our oceans - a discussion document on the regulations proposed under the EEZ Bill

PEPANZ submission: Managing our oceans - a discussion document on the regulations proposed under the EEZ Bill 29 June 2012 Submission on proposed EEZ regulations policy proposals Ministry for the Environment PO Box 10362 Wellington 6143 PEPANZ submission: Managing our oceans - a discussion document on the regulations

More information

Air Monitoring Directive Chapter 9: Reporting

Air Monitoring Directive Chapter 9: Reporting Air Monitoring Directive Chapter 9: Reporting Version Dec 16, 2016 Amends the original Air Monitoring Directive published June, 1989 Title: Air Monitoring Directive Chapter 9: Reporting Number: Program

More information

WHITE ROSE OILFIELD DEVELOPMENT APPLICATION

WHITE ROSE OILFIELD DEVELOPMENT APPLICATION WHITE ROSE OILFIELD DEVELOPMENT APPLICATION VOLUME 1 CANADA-NEWFOUNDLAND BENEFITS PLAN SUBMITTED BY: HUSKY OIL OPERATIONS LIMITED AS OPERATOR SUITE 801, SCOTIA CENTRE 235 WATER STREET ST. JOHN S, NF, A1C

More information

Extract of Advance copy of the Report of the International Conference on Chemicals Management on the work of its second session

Extract of Advance copy of the Report of the International Conference on Chemicals Management on the work of its second session Extract of Advance copy of the Report of the International Conference on Chemicals Management on the work of its second session Resolution II/4 on Emerging policy issues A Introduction Recognizing the

More information

AT A GLANCE. US$16.9 billion. US$52 billion. 41 million 5,299

AT A GLANCE. US$16.9 billion. US$52 billion. 41 million 5,299 APACHE AT A GLANCE Apache s oil and natural gas operations reach from the United States to Canada, Egypt s Western Desert, the North Sea, Australia and Argentina. Our global exploration program is seeking

More information

Who are IPIECA and IOGP?

Who are IPIECA and IOGP? Who are IPIECA and IOGP? IPIECA is the global association for environmental and social issues for both the upstream and downstream oil and gas industry It is a non-advocacy Association formed in 1974 following

More information

OFFSHORE HYDROCARBON EXPLORATION

OFFSHORE HYDROCARBON EXPLORATION i i I OFFSHORE HYDROCARBON EXPLORATION t. Report and Recommendations Offshore Exploration of the West Coast Environmental Assessment Panel April 1966 OFFSHORE HYDROCARBON EXPLORATION Hippa Island. Queen

More information

Canada s Ballast Water Requirements. September 2016

Canada s Ballast Water Requirements. September 2016 Canada s Ballast Water Requirements September 2016 Applicability of Canada s Regulations Ballast Water Control and Management Regulations require vessels from outside Canada s Exclusive Economic Zone (EEZ)

More information

Status of the Joint Industry. Spill Preparedness and Response

Status of the Joint Industry. Spill Preparedness and Response Status of the Joint Industry Research Program to Improve Oil Spill Preparedness and Response David Fritz BP America Latest API report providing update of activities: http://www.api.org/~/media /Files/Oil-and-Natural-

More information

The Marine Mammal Protection Act: A Looming Giant For Offshore Permitting. Ryan Steen Stoel Rives LLP October 7, 2015

The Marine Mammal Protection Act: A Looming Giant For Offshore Permitting. Ryan Steen Stoel Rives LLP October 7, 2015 The Marine Mammal Protection Act: A Looming Giant For Offshore Permitting Ryan Steen Stoel Rives LLP October 7, 2015 1 Roadmap Marine Mammal Protection Act Primer Section 101(a)(5) Incidental Take Authorizations

More information

Kinsale Area Gas Fields Decommissioning Project Information Leaflet

Kinsale Area Gas Fields Decommissioning Project Information Leaflet Kinsale Area s Decommissioning Project Information Leaflet About Kinsale Energy PSE Kinsale Energy Limited has been operating a number of gas fields in the Celtic Sea, off the County Cork coast, since

More information

Class Update on Latest Ship to Ship Transfer Plan

Class Update on Latest Ship to Ship Transfer Plan Class Update on Latest Ship to Ship Transfer Plan Binbin Li 17 May 2017 7th Forum on STS Best Practices - SNI, Singapore 2017 American Bureau of Shipping. All rights reserved Outline This presentation

More information

BAY OF BENGAL BLOCKS AD2 AND A4 CORING SURVEY PHASE 2 END OF SEASON - ENVIRONMENTAL REPORT

BAY OF BENGAL BLOCKS AD2 AND A4 CORING SURVEY PHASE 2 END OF SEASON - ENVIRONMENTAL REPORT BAY OF BENGAL BLOCKS AD2 AND A4 CORING SURVEY PHASE 2 END OF SEASON - ENVIRONMENTAL REPORT Agnes Mc Laverty Safety, Environment & Social Performance Manager Shell Myanmar Energy Pte Ltd 16 th June 2017

More information

Repsol E&P T&T Ltd is one of the upstream Repsol YPF Group of companies currently operating in more than 20 countries around the world.

Repsol E&P T&T Ltd is one of the upstream Repsol YPF Group of companies currently operating in more than 20 countries around the world. 1 INTRODUCTION 1.1 Background Repsol E&P T&T Ltd is one of the upstream Repsol YPF Group of companies currently operating in more than 20 countries around the world. Repsol E&P has become one of the major

More information

DEA Quarterly Meeting 18 November Bill Pike NISC, an IBM Company

DEA Quarterly Meeting 18 November Bill Pike NISC, an IBM Company DEA Quarterly Meeting 18 November 2010 Bill Pike NISC, an IBM Company DISCLAIMER I am an employee of NISC, an IBM company, working under contract in the U.S. Department of Energy s National Energy Technology

More information

Well Integrity Life Cycle Management for Subsea Field Development A Regulator s Perspective

Well Integrity Life Cycle Management for Subsea Field Development A Regulator s Perspective Well Integrity Life Cycle Management for Subsea Field Development A Regulator s Perspective John Kennedy, P. Eng., CRSP Director of Operations C NLOPB Who 2 C NLOPB Regulator for the Canada Newfoundland

More information

Coastal Virginia Offshore Wind partnership with Orsted. February 2018 Update

Coastal Virginia Offshore Wind partnership with Orsted. February 2018 Update Coastal Virginia Offshore Wind partnership with Orsted February 2018 Update 1 Coastal Virginia Offshore Wind Project: Lease Update Research and Commercial Lease Areas Phase 1 CVOW Lease Area (2,135 acres)

More information

An Embedded Librarian Working in the Bureau of Ocean Energy Management

An Embedded Librarian Working in the Bureau of Ocean Energy Management An Embedded Librarian Working in the Bureau of Ocean Energy Management Stephen Pomes, Librarian Bureau of Ocean Energy Management, U.S. Dept. of the Interior ASLI Conference January 2016 Table of Contents

More information

Aboriginal Consultation Framework for the Northern Gateway Pipeline Project

Aboriginal Consultation Framework for the Northern Gateway Pipeline Project Aboriginal Consultation Framework for the Northern Gateway Pipeline Project This document sets out a framework for how the federal government will rely on the Joint Review Panel process to the extent possible

More information

Annex C4.1. Minutes of Meeting with Ezemvelo KZN

Annex C4.1. Minutes of Meeting with Ezemvelo KZN Annex C4.1 Minutes of Meeting with Ezemvelo KZN ERM Suite S005 17 The Boulevard Westway Office Park Westville, 3635 Durban, South Africa Telephone: +27 31 265 0033 Fax: +27 31 265 0150 MEETING MINUTES

More information

7 Briefing. Responsible investor

7 Briefing. Responsible investor Issue Responsible investor 7 Briefing Monday, 5 th October 202 In 200, we accepted all 26 recommendations made by the Bly Report our internal investigation into the Deepwater Horizon incident. BP has committed

More information

Thematic Opportunities Under Horizon 2020 Marine Research

Thematic Opportunities Under Horizon 2020 Marine Research Thematic Opportunities Under Horizon 2020 Marine Research Karen Davison Fisheries and Oceans Canada Karen.davison@dfo-mpo.gc.ca Passport for Partnerships: Opportunities for Research and Innovation Collaboration

More information

Role of Industry Standards in improving Offshore Safety

Role of Industry Standards in improving Offshore Safety Role of Industry Standards in improving Offshore Safety Standards Background Role of Standards Standards and Regulations David Miller, PE, F. ASCE, Director, Standards 1 API Standards Background API established

More information