SUPPLY CHAIN CAPACITY REPORT

Size: px
Start display at page:

Download "SUPPLY CHAIN CAPACITY REPORT"

Transcription

1 UKCS DECOMMISSIONING SUPPLY CHAIN CAPACITY REPORT March 218 Produced by 1

2 CONTENTS EXECUTIVE SUMMARY 4 1 Introduction 8 2 Study findings 2.1 Overall UKCS demand Platform wells P&A Subsea wells P&A Subsea infrastructure removal Topside removal Substructure removal Onshore remediation, dismantling and recycling 29 3 Conclusions 32 4 Recommendations for future studies 33 Appendix Project methodology and approach 34 ABBREVIATIONS CAR Controlled Activities Regulations (License) CNS Central North Sea CoP Cessation of Production CSV Construction Support Vessels DSV Dive Support Vessels EIS East Irish Sea HLV Heavy Lift Vessel IS Irish Sea LWIV Light Well Intervention Vessel MDU Modular Drilling Units MSV Multipurpose Support Vessel NNS Northern North Sea OGA Oil & Gas Authority P&A PBDR PPC PWG ROVSV RSA SE SNS SSCV Te UKCS WML WoS Plugging & Abandonment Platform Based Drilling Rigs Pollution Prevention and Control (Licence) Project Work Group ROV Support Vessel Radioactive Substance Authorisation Scottish Enterprise Southern North Sea Semi-submersible Crane Vessel Metric Tonne United Kingdom Continental Shelf Waste Management License West of Shetland 2 Decommissioning Supply Chain Capacity Report

3 ACKNOWLEDGEMENTS We would like to acknowledge the Project Work Group (PWG) for their guidance and valuable contributions: Robert McCaig Babcock International Group Heather Woods Decom North Sea Angela McKenzie Decom North Sea Bill Cattanach Oil & Gas Authority Sylvia Buchan Oil & Gas Authority Karen Craig Scottish Enterprise Davi Quintiere Slalom Willem van Es Wood We would also like to thank the industry subject matter experts who contributed to the analysis and the participating companies for taking the time to respond to the survey, providing valuable data to assist with conducting an analysis of supply vs demand for 217. ACKNOWLEDGEMENTS Finally, we would like to thank Decom North Sea, Scottish Enterprise and the Oil & Gas Authority, for commissioning this report. DISCLAIMER This report has been commissioned by, and is intended for, Decom North Sea, Scottish Enterprise and the Oil & Gas Authority, and has been produced by Accenture (UK) Limited (referred to in this report as Accenture or we ). This report has been prepared for information purposes and the information contained in it is based upon data from third party sources, including participants of the Capacity Survey that were identified as focal points by their organisations, memberships or directly by the Project Work Group, or otherwise from the participant s company website. Accenture has relied upon the information provided by participants completing the Capacity Survey in the creation of this report. Where Accenture had reason to believe such information was inaccurate or incomplete, it has taken steps to verify the accuracy of the results of the Capacity Survey, where possible. No responsibility is accepted by Accenture for any inaccuracy or error in the information contained in this Report or any action taken or not taken in reliance on this Report. 3

4 EXECUTIVE SUMMARY EXECUTIVE SUMMARY The decommissioning of oil and gas infrastructure on the United Kingdom Continental Shelf (UKCS) is an area of activity that is widely expected to increase due to the maturity of the basin. This report, prepared by Accenture and commissioned by Decom North Sea, Scottish Enterprise and the Oil & Gas Authority, sets out the findings to a study conducted to provide a high-level baseline assessment of the current decommissioning capacity to service UKCS decommissioning demand. The following six activity areas were identified for analysis: 1. Platform wells plugging and abandonment 2. Subsea wells plugging and abandonment 3. Subsea infrastructure removal 4. Topside removal 5. Substructure removal 6. Onshore remediation, dismantling and recycling. Demand data was provided by the Oil & Gas Authority (OGA). The data numbered 165 projects and their associated or potential year of Cessation of Production (CoP) which ranged from The number of platform and/or subsea wells per project and associated infrastructure tonnage for removal was also given. Capacity to meet demand, referred to as supply data, was established by collating information from a survey questionnaire issued in summer 217 to relevant companies in the supply chain that could provide key assets or equipment to carry out these six key activities. The demand and supply data were analysed to assess the extent to which the supply chain would be able to meet the need for forthcoming decommissioning projects. This created a snapshot in time and provided a baseline of current supply capacity in relation to current anticipated demand. The overall conclusion from this research is that current supply chain capacity appears sufficient, and at times, surplus, to meet estimated demand for decommissioning activities on the UKCS. The industry is, however, subject to evolving macroeconomic and market conditions and has been (and will continue to be) disrupted by forces that go far beyond supply and demand. These external forces may have a significant impact on UKCS decommissioning capacity: Oil price fluctuations Regulatory framework Increasing competition for the UK supply chain New decommissioning-centric technologies and processes 4 Decommissioning Supply Chain Capacity Report

5 Key observations for the specific activity areas were: Platform Wells P&A 84 platform wells will require P&A based on current potential CoP dates to 223. Overall there appears to be sufficient capacity in 217/18 to meet this potential demand. If activity proceeds as estimated the CNS may experience capacity constraints in 218. The NNS region is likely to be reliant on MDUs for P&A activity due to water constraints associated with jack ups. Platform-Based Drilling Rigs (PBDRs) may be reactivated to carry out platform well P&A and would help to mitigate capacity constraints. Subsea Wells P&A 462 subsea wells will require P&A based on current potential CoP dates to 223. Current supply clearly outstrips potential demand, and the backlog of pre-217 activities could easily be accommodated in the forthcoming years. Non-responses to the survey mean additional capacity is likely to exist. Subsea Infrastructure Removal 98 projects have subsea infrastructure removal requirements based on current potential CoP dates to projects relate to removal of subsea infrastructure up to 4Te, accounting for a cumulative total of 6,395Te and requiring an estimated 1,32 project days to complete. 1 projects relate to removal activities above 4Te, accounting for a cumulative total of 9,19Te and requiring an estimated 21 days to complete. Current capacity far outstrips demand for subsea infrastructure removal, and the backlog of pre-217 activities is not expected to have a significant impact. 5

6 EXECUTIVE SUMMARY Topside Removal 115 projects were identified with topside removal requirements based on CoP up to 223. The cumulative removal total was 491,335Te requiring an estimated 579 days for removal. Demand for topside removals was estimated to peak between 219 and 22. Current removal capacity is almost double decommissioning demand and the pre-217 backlog of activity is not expected to have a significant impact. Future capacity will be subject to the level of development and decommissioning projects on the UKCS and globally, as well as activities in other sectors such as offshore wind farm construction. Substructure Removal 19 projects were identified with substructure removal requirements based on CoP up to 223. Total substructure tonnage for removal was 294,74Te, requiring an estimated 1,15 vessel days. Demand for substructure removals is likely to peak between 218 and 221. Current capacity exceeds demand for removal of substructures weighing less than 4,Te. Current capacity for substructures over 4,Te appears sufficient to meet current demand. Non-responses to the survey mean vessel availability may in fact be significantly higher. Onshore Decommissioning A total of 81,66Te of infrastructure was estimated for removal from the UKCS, requiring a total of 15,241 days of onshore work Demand for onshore activities is likely to peak in and heavily concentrated on assets recovered from the CNS and SNS. 63% of quaysides and 61% of yards have laydown areas which would not be able to accommodate large platforms. Supply and demand for onshore activities were separate aspects due to different data criteria that could not be overlaid. 6 Decommissioning Supply Chain Capacity Report

7 Conclusions Overall, the research revealed that with current market conditions there appears to be sufficient supply chain capacity to meet the short/medium term demand expected for decommissioning activities on the UKCS. However, this could quickly change should there be a significant upturn in investment across the basin and subject to the extent of utilisation of the UK supply chain by other industries. It can therefore be concluded that the sector currently has a window of opportunity, where unit rates for equipment and services are likely to be lower than historical norms, providing prospects for relatively low-cost decommissioning should mechanisms be found to bring currently deferred work to the market. Given the cyclical nature of the oil and gas sector, it is highly likely that these conditions will not last. Thus, a focus on ensuring that project approval and commencement decisions are made swiftly can be expected to maximise the opportunities to take advantage of such market conditions in future. This will need to include regulatory submission and approval, conceptual and detailed engineering, procurement and contracting, and timely access to capital. Please see Page 33 for a full list of recommendations for improvement to future studies. 7

8 INTRODUCTION 1 INTRODUCTION The UK oil and gas industry is undergoing a transition, as it strives to adapt to lower oil prices and improve the competitiveness of the United Kingdom Continental Shelf (UKCS), amidst increasing basin maturity. This is critical for securing future developments, maximising economic recovery from existing fields and for decommissioning the infrastructure once production has ceased. With decommissioning activity widely expected to increase over the next ten years the aim is to ensure the supply chain has the necessary capacity to meet decommissioning demand safely and cost efficiently. This report, prepared by Accenture and commissioned by Decom North Sea, Scottish Enterprise and the Oil & Gas Authority, sets out the findings to a study conducted to provide a high-level assessment of the current decommissioning capacity to service UKCS decommissioning demand. It aims to generate greater understanding of supply and demand factors to create visibility and alignment of planning and investment decisions. The Oil & Gas Authority has set a target for the industry of reducing decommissioning costs to 39 billion (a 35% reduction on current estimates).1 Delivering these efficiencies will undeniably present challenges, but importantly, opportunities too. The UK, compared to other oil and gas producing nations, is most advanced in its thinking and leadership around decommissioning. From the regulatory approach, the experience gained, and learning disseminated; these attributes provide the impetus to become a world-leader in decommissioning. Achieving that will require an efficient and effective UK supply chain which is prepared for and flexible to meet decommissioning demand growth in the UKCS and internationally. The study utilised data, provided by the OGA, on projects that had already ceased production or had potential cessation of production (CoP) dates to 223 demand data. A survey questionnaire was issued to relevant companies in the supply chain to determine market availability of critical assets or equipment supply data - to carry out the following six activities: 1. Platform wells plugging and abandonment 2. Subsea wells plugging and abandonment 3. Subsea infrastructure removal 4. Topside removal 5. Substructure removal 6. Onshore remediation, dismantling and recycling. The availability of people, services and secondary equipment supplementing these activities was generally considered to have no current critical constraints, therefore did not form part of the study. The demand and supply data were analysed to assess the extent to which supply capacity would be able to meet the need for forthcoming decommissioning projects (see Appendix for detailed approach). This created a snapshot in time and provided a baseline of current supply capacity in relation to current estimated demand. Figure 1 - Decommissioning Market Levers Guidance Requirements Government/ Regulator Standards Incentives Moderator Decom Supply Chain Operators License to operate Innovation Investments Plans/execution Collaboration - Alliance Innovation Service Capability Demand Market Service Capacity Service Providers Cost-effective offer Innovation Supply Collaboration - Integration (source: OGA, Decom North Sea, Accenture) 1Oil & Gas Authority, UKCS Decommissioning 217 Cost Estimate Report 8 Decommissioning Supply Chain Capacity Report

9 2 STUDY FINDINGS 2.1 OVERALL UKCS DEMAND Initial analysis of the data provided by the OGA enabled a broad picture of estimated decommissioning requirements to be drawn. From a total of 165 projects, with estimated cessation of production dates up to 223, a breakdown based on UKCS location and activity was discerned. A visual representation of the data is shown in Figure 2. Figure 2 Aggregate UKCS decommissioning demand (based on CoP to 223) SUPPLY AND DEMAND ANALYSIS It is important to note that the demand data shown is indicative, due to largely being based on potential cessation of production (CoP) dates which are subject to market conditions and susceptible to change. 29

10 STUDY FINDINGS Importantly, only a few projects have firm timescales, and many are still in their early planning stages. The projects also include several with uncompleted activities associated with facilities that ceased production prior to 217. These have been deferred, creating a backlog that will need to be rescheduled in coming years, and which appear in the demand analysis as activities expected in years To enable analysis of demand and supply data, the number of days potentially required to carry out each activity was calculated, as shown in Figure 3. Figure 3 Aggregate UKCS decommissioning demand days (based on CoP to 223) Decommissioning Activity Number Demand Days* Platform Wells P&A 84 29,4 Subsea Wells P&A ,7 Subsea Infrastructure Removal <4Te Subsea Infrastructure Removal >4Te 88 1, Topside Removal Substructures Removal 19 1,15 Onshore Dismantling (tonnes) 81,66 15,241 * A detailed explanation of the methodology and assumptions employed is provided in the Appendix. The overall demand data was then analysed per decommissioning activity against supply data from the survey questionnaire. 1 Decommissioning Supply Chain Capacity Report

11 2.2 Platform wells P&A To assess demand for platform wells P&A, the potential demand days for each year was estimated based on potential CoP dates through to 223. To do so, assumptions were made that P&A activities would be carried out in the same year as CoP and that the duration of P&A for each platform well would be 32 days, and for installations with more than 1 wells, 1 in every 1 would require an additional 1 days. The results are shown in Figure 4. The analysis provides a view of likely commencement, volume and duration of P&A activities in each region. Figure 4 UKCS platform wells P&A potential demand days by region ( ) 1, 9, 8, 7, 6, 5, 4, 3, 2, 1, SUPPLY AND DEMAND ANALYSIS CNS IS (including EIS) NNS SNS For the 84 platform wells identified, P&A is estimated to require a total of 29,4 days. Importantly, 93% of this demand relates to the CNS and SNS regions, with little activity required in the IS (including EIS) and NNS and none in the WoS. The concentration revealed as many as 77% of platform wells related to just 3% of projects. In the CNS, there are 13 multi-well projects covering a total of 385 wells. Indeed, one CNS project covers as many as 142 wells. In the SNS there are 9 multi-well projects covering 192 wells and in the NNS a single multi-well project covers a total of 42 wells. These multi-well projects provide opportunity to reduce costs by leveraging continuous improvement and forging collaborative projects and innovative commercial arrangements. The data shows a clear peak of overall platform P&A demand in 218. It should be noted that several abandonments, relating to data for , will need to be rescheduled with the potential impact of pushing P&A activity into later years which may have the effect of creating further peaks in demand. 211

12 On the supply side, a total of 53 jack-ups and 5 Modular Drilling Units (MDU) were identified as presently able to operate in the UKCS. These figures were derived from the survey, which achieved a response rate of over 6% (see Appendix for details). The potential availability of these assets for each UKCS region is set out in Figure 5. Figure 5 Number of available drilling rigs/units by type and region STUDY FINDINGS Types Total Count Qty that can operate in CNS Qty that can operate in IS (including EIS) Qty that can operate in NNS Qty that can operate in SNS Jack-up MDU Total Vessels 58 A key issue identified concerned availability of jack-ups, which was assessed based on the water depth each asset could operate in. This led to the conclusion that jack-ups are generally not suitable for NNS operations, meaning this region would be dependent on MDUs. However, rig availability would be dependent on a broader set of factors including geographical area, operational constraints, services provided by the asset, platform configuration and project specifics. To assess the supply chain s current capacity to meet likely future demand, the survey results were used to calculate the maximum number of potential available days for each asset type over 217/18. This resulted in 6,761 days for Jack-up rigs and 931 days for MDUs. It should be noted that this represents maximum capacity and does not account for work conducted simultaneously in multiple regions, or for potential increases in demand elsewhere such as exploration and production drilling. This snapshot of current availability was compared against potential demand. The results for the whole of the UKCS are shown in Figure 6. Figure 6 UKCS platform wells P&A demand vs supply ( ) 1, 9, Potential Total Demand Potential Maximum Supply ( ) 8, 7, 6, 5, 4, 3, 2, 1, 6, Jack-up MDU 12 Decommissioning Supply Chain Capacity Report

13 Figure 6 shows that, in general, available supply throughout 217/18 outstrips likely demand in every year except 218. However, the backlog of activities from pre-217 is likely to alter demand in subsequent years. At a regional level, the picture is much the same. In regions like the IS (including EIS) and the SNS, there appears to be sufficient capacity to meet current potential platform wells P&A demand, including in 218. The only immediate area of concern is the CNS, where demand appears to outstrip available supply in 218 (see Figure 7). The CNS may experience capacity constraints in 218 given this likely demand for platform wells P&A. Figure 7 CNS platform wells P&A demand vs supply ( ) 6, 5, 4, 3, 2, 1, Potential CNS Demand Potential Supply ( ) 3, STUDY FINDINGS Jack-up MDU The analysis however did not account for P&A that could be undertaken using existing platform-based drilling rigs (PBDR). There are examples of PBDR being refurbished to carry out P&A, however, maintenance and refurbishment can be costly and possibly prohibitive. It is recommended that future studies incorporate this parameter. Summary For platform wells P&A activity across the whole of the UKCS, there appears to be more than enough current capacity to meet likely future demand. However, areas of concern were identified in two regions: the CNS and NNS. Key observations and recommendations 84 platform wells will require P&A based on current potential CoP dates to 223 Overall there appears to be sufficient capacity in 217/18 to meet this potential demand If activity proceeds as estimated the CNS may experience capacity constraints in 218 The NNS region is likely to be reliant on MDUs for P&A activity due to water depth constraints associated with jack ups Platform-Based Drilling Rigs (PBDRs) may be reactivated to carry out platform well P&A and would help to mitigate capacity constraints. This parameter did not form part of the analysis and is recommended for inclusion in future studies. 213

14 2.3 Subsea wells P&A To assess demand for subsea wells P&A, the potential demand days for each year was estimated based on potential CoP dates through to 223. The assumptions made were that P&A activities would be carried out four years after CoP, except for the SNS where it was assumed activity would take place after two years. SUPPLY AND DEMAND ANALYSIS The duration of P&A for each subsea well was estimated as 32 days, and for fields with more than 1 wells, 1 in every 1 would require an additional 1 days. The results are shown in Figure 8. The analysis provides a view of likely commencement, volume and duration of P&A activities in each region. It should be noted that a small number of subsea abandonments relating to will need to be rescheduled which will marginally alter subsequent demand. Figure 8 UKCS subsea wells P&A potential demand days by region ( ) Potential Total No of Days by Region 4,5 4, 3,5 3, 2,5 2, 1,5 1, CNS NNS SNS WoS For the 462 subsea wells identified, P&A was estimated to require a total of 17,7 days. Figure 8 shows subsea well P&A activity increasing over the coming years, potentially peaking around 224. Demand is concentrated in the CNS and NNS regions, representing 81%. The remaining activity is equally split between the SNS and WoS and none expected in the IS (including the EIS). Nearly half (43%) of subsea wells relate to just 9% of projects. In the CNS there are 6 multi-well projects covering 114 wells. The NNS has 3 projects covering 37 wells and the WoS region has a single project covering 46 wells. These multi-well projects provide opportunity to reduce costs by entering into collaborative ventures, innovative commercial arrangements, and leveraging continuous improvement. On the supply side, a total of 118 vessels/rigs were identified with current capacity to undertake subsea wells P&A in the UKCS. This figure was derived from the survey, to which nearly two thirds responded (54 from a total of 86 companies contacted). The potential availability of these assets in each region is set out in Figure 9. It should be noted that availability was assessed based on the water depth each could operate in but this is likely to be dependent on a broader set of factors including geographical area, operational constraints, services provided by the asset, platform configuration and project specifics. 14 Decommissioning Supply Chain Capacity Report

15 Figure 9 Number of available vessels/rigs by type and region Types Total Count Qty that can operate in CNS Qty that can operate in NNS Qty that can operate in SNS Qty that can operate in WoS LWIV Jack-up Semi-sub Supply Vessel (with Modular Spread) Total Vessels STUDY FINDINGS Based on this availability, and to assess current capacity to meet likely future demand, the results were used to calculate the maximum number of potential available days over 217/18, for each asset type by region. This resulted in total availability of 1,38 days for LWIVs, 7,69 days for Jack-up rigs, 5,697 days for Semi-Subs and 1,33 days for Supply Vessels with Modular Spreads. A snapshot of this availability compared against potential demand for the whole of the UKCS is shown in Figure 1. This shows that current supply appears to clearly outstrip projected annual demand. This does however represent maximum capacity and does not account for work conducted simultaneously in multiple regions, or for potential increases in demand elsewhere such as exploration and production drilling or other marine sectors. Figure 1 UKCS subsea wells P&A demand vs supply ( ) Potential Supply Vs Demand (Total) Potential Total Demand 8, 7, Potential Maximum Supply ( ) 7,69 6, 5, 4, 3, 2, 1, 1,38 5,697 1, LWIV Semi-sub Supply Vessel Jack-up The results for the CNS, NNS, WoS and SNS regions are set out in Figures 11 to 14. Demand in the CNS and NNS begins to 2 grow from 219 onwards although this appears to be variable. This may be smoothed significantly as project schedules are developed. Current availability does appear to be sufficient, but there may be limited capacity to undertake rig-less activity (with LWIVs and Supply Vessels with Modular Spreads) if well complexities permit this approach. Demand in the WoS and SNS regions (Figures 13 and 14) are expected to be limited. 15

16 Potential Supply Vs Demand (CNS) Figure 11 CNS subsea wells P&A demand vs supply ( ) Potential CNS Demand 6, Potential Supply ( ) 5,697 5,561 5, STUDY FINDINGS 4, 3, 2, 1, ,38 1,33 LWIV Semi-sub Supply Vessel Jack-up Figure 12 NNS subsea wells P&A demand vs supply ( ) Potential Supply Vs Demand (NNS) 6, Potential NNS Demand Potential Supply ( ) 5,697 5, 4, 3, 2, 1, 1,38 1,33 1, LWIV Semi-sub Supply Vessel Jack-up Figure 13 WoS subsea wells P&A demand vs supply ( ) 6, Potential WoS Demand Potential Supply ( ) 5,697 5, 4, 3, 2, 1, 1,38 1,33 2, LWIV Semi-sub Supply Vessel Jack-up 16 Decommissioning Supply Chain Capacity Report

17 Figure 14 SNS subsea wells P&A demand vs supply ( ) Potential Supply Vs Demand (SNS) Potential SNS Demand 8, Potential Supply ( ) 7,69 7, 6, 5, 4, 3, 2, 1, ,781 1,33 LWIV Semi-sub Supply Vessel Jack-up STUDY FINDINGS For subsea wells P&A, there appears to be sufficient capacity at present to meet current projected decommissioning demand. It also appears that the backlog of activities dating from before 217 could easily be accommodated in the forthcoming years. The survey was subject to non-responses, therefore additional capacity is likely to exist. Moreover, evolving macroeconomic and market conditions are likely to alter, and potentially reduce capacity for subsea wells P&A. Rigs or vessels may secure work associated with exploration and production activity or overseas. Equally older assets may be taken out of service and stacked and new capacity may enter the market. There is therefore currently an economic window of opportunity, but significant capacity could be moved from the basin or scrapped if not utilized which would place upward pressure on availability and costs. Key observations and recommendations 462 subsea wells will require P&A based on current potential CoP dates to 223 Despite this demand, subsea wells P&A current supply clearly exceeds potential demand, and the backlog of pre-217 activities could easily be accommodated in the forthcoming years. Non-responses mean additional capacity is likely to exist. This factor should be considered, and appropriate treatment incorporated in future studies. 217

18 2.4 Subsea infrastructure removal SUPPLY AND DEMAND ANALYSIS A total of 98 projects were identified with subsea infrastructure removal requirements. To assess demand for subsea infrastructure removal, the potential demand days for each year was estimated based on potential CoP dates through to 223. The assumptions made were that removal activity would take place four years after CoP, except for in the SNS where this was assumed to be two years after CoP. The duration of subsea removal activities was estimated based on the tonnage to be removed. Figure 15 shows the number of removal days to be utilised associated with subsea infrastructure, ranging from 15 days for projects with less than 5 tonnes of recovered material to a maximum of 4 days for more than 2,1 tonnes. Figure 15 Subsea infrastructure removal days by weight (Te) Subsea Tonnage , 1,1-2, >2,1 Removal Days In parallel, the analysis of supply capacity has defined vessel suitability based on a 4Te vessel capability, as this best reflects the boundary point between vessel types with differing capabilities for these activities. The results are shown in Figures 16 and 17. This gives a picture of the likely commencement, volume and duration of subsea infrastructure removal activities in each region (note that the data only accounts for actual removal operations, not preparatory work). Both graphs show demand for subsea infrastructure removal peaking between 219 and 224. Figure 16 represents 88 projects with associated subsea infrastructure removal up to 4Te. Cumulatively this accounts for 6,395Te, requiring an estimated 1,32 project days to complete. Initial demand is concentrated in the SNS region, with a shift to a focus on the CNS region from 221 onwards. The NNS and particularly the WoS area make minor contributions to the demand. A crucial point to note is that 61% of these removal projects are below 1Te. Consequently, actual demand days may be significantly more than forecast due to the potential for inefficiencies associated with small individual projects and a greater number of mobilisation/demobilisation activities. These projects would ideally be candidates for multi-operator/ multi-project decommissioning campaigns to deliver more cost-effective activities. 18 Decommissioning Supply Chain Capacity Report

19 Figure 16 UKCS subsea infrastructure removal potential demand days by region (up to 4Te) CNS NNS SNS WoS STUDY FINDINGS Figure 17 represents 1 projects with associated subsea infrastructure removal over 4Te, accounting for cumulative removal of 9,19Te with an estimated 21 days to complete. Figure 17 UKCS subsea infrastructure removal potential demand days by region (above 4Te) CNS NNS SNS WoS On the supply side, data was received from approximately 6% of companies surveyed (49 out of 78 contacted). A total of 36 vessels were identified as available for activities on subsea infrastructure up to 4Te and eight Heavy Lift Vessels (HLV) for infrastructure above 4Te. The assessment was made according to the water depth each vessel could operate in. However, it is important to note that other variables can impact this availability (operational constraints, geographical area, services provided by the vessel, project specifics) which have not been considered in this analysis. The availability breakdown for each region and activity is shown in Figures 18 and

20 Figure 18 Number of available vessels by subsea infrastructure type and region (up to 4Te) STUDY FINDINGS Types Total Available Vessels Removal of Pipelines Removal of Subsea Structures (manifolds, WHPS, concrete bases) Removal of Pipeline Stabilisation aids (mattresses) CNS NNS SNS WoS Figure 19 Number of available HLV by subsea infrastructure type and region (above 4Te) Types Total Available Vessels Removal of Pipelines Removal of Subsea Structures (manifolds, WHPS, concrete bases) Removal of Pipeline Stabilisation aids (mattresses) CNS NNS SNS WoS To assess current capacity to meet future demand, the survey results were used to calculate the maximum number of potential available days for each vessel type per region ( available vessel days see Appendix for calculation). This snapshot of current availability was compared against potential demand. While demand over the coming years was estimated at 1,32 days for projects up to 4Te) and 21 days for projects above 4Te, available supply for 217/18 was estimated to be 1,571 days for CSVs; 796 days for DSVs; 1,58 days for MSVs; 1,43 days for ROVSVs and 716 days for HLVs. The snapshot of current availability compared against potential demand for the CNS, NNS, SNS and WoS regions are set out in Figures 2 to 26. In general, there appears to be far more capacity than is required to meet current demand for subsea infrastructure removal (both for infrastructure up to 4Te and for infrastructure above 4Te). Moreover, any backlog of pre-217 activities is not expected to have a significant impact. However, it should be noted that this represents maximum capacity and does not account for work conducted simultaneously in multiple regions, or for potential increases in demand elsewhere globally. 2 Decommissioning Supply Chain Capacity Report

21 Figure 2 CNS subsea infrastructure demand vs supply (up to 4Te) 1,6 1,4 Potential CNS Demand up to 4Te 1,571 Potential Supply ( ) 1,2 1, , CSV DSV MSV ROVSV STUDY FINDINGS Figure 21 CNS subsea infrastructure demand vs supply (above 4Te) Potential CNS Demand above 4Te Potential Supply ( ) HLV In the CNS region, demand appears to peak in the period with a mix of both small (<4Te) and larger projects. Suitable vessel supply capacity appears to be good for all categories of vessel. Figure 22 NNS subsea infrastructure demand vs supply (up to 4Te) 1,6 1,4 Potential NNS Demand up to 4Te 1,571 Potential Supply ( ) 1,2 1, , CSV DSV MSV ROVSV 221

22 Figure 23 NNS subsea infrastructure demand vs supply (above 4Te) STUDY FINDINGS Potential NNS Demand above 4Te Potential Supply ( ) In the NNS region, demand appears to be limited with activity spread unevenly across the period from with large projects not expected to occur before 225. Suitable vessel supply capacity appears to be good for all categories of vessel. 411 HLV Potential Supply Vs Demand (SNS) up to 4 Te Figures 24 SNS subsea infrastructure demand vs supply (up to 4Te) 1,6 1,4 Potential SNS Demand up to 4Te 1,571 Potential Supply ( ) 1,2 1, ,58 1, CSV DSV MSV ROVSV Figures 25 SNS subsea infrastructure demand vs supply (above 4Te) 8 7 Potential SNS Demand above 4Te Potential Supply ( ) HLV 22 Decommissioning Supply Chain Capacity Report

23 In the SNS region, demand appears to be grow rapidly from 217 until declining significantly after 22. The majority of projects are small (<4Te) and suitable vessel supply capacity appears to be good for all categories of vessel. Figure 26 WoS subsea infrastructure demand vs supply (up to 4Te) Potential Supply Vs Demand (WoS) up to 4 Te 1,6 1,4 1,2 1, Potential WoS Demand up to 4Te Potential Supply ( ) 1,571 1, CSV DSV MSV ROVSV STUDY FINDINGS WoS activity is limited to a single small (<4Te) project in 224 and suitable vessel supply capacity appears to be good for all categories of vessel. Summary Current capacity was found to exceed current decommissioning demand for subsea infrastructure removal both up to and above 4Te. The backlog of pre-217 activities is not expected to have a significant impact. Furthermore, a large surplus in capacity is likely to affect contractor ability to maintain investment, representing a risk to the supply chain s ability to meet future decommissioning demand. Evolving macroeconomic and market conditions are also likely to alter capacity. A favourable shift may see assets deployed in non-decommissioning projects or overseas. Alternatively, assets may even be sold. There is therefore a current window of opportunity with over-capacity and an opportunity for activities to be executed cost-effectively. Key observations and recommendations 98 projects have subsea infrastructure removal requirements based on current potential CoP dates to projects relate to removal of subsea infrastructure up to 4Te, accounting for a cumulative total of 6,395Te and requiring an estimated 1,32 project days to complete. 1 projects relate to removal activities above 4Te, accounting for a cumulative total of 9,19Te and requiring an estimated 21 days to complete. Current capacity far outstrips demand for subsea infrastructure removal, and the backlog of pre-217 activities is not expected to have a significant impact. 223

24 2.5 Topside removal SUPPLY AND DEMAND ANALYSIS To assess demand for topside infrastructure removal, the potential demand days for each year was estimated based on potential CoP dates through to 223. The assumptions made were that topside removal activity would take place two years after CoP, except for in the SNS where this was assumed to be one year after CoP. The duration of topside removal activities for each region was estimated based on vessel days per tonnage range, shown in Figure 27. Figure 27 Topside removal vessel days (per tonnage range) by region Topside Tonnage 1,6 1,61-4, 4,1-8, 8,1-16, >16, CNS, NNS IS (including EIS), SNS In total, 115 projects were identified with topsides removal requirements between 213 and 225, comprising a total tonnage of 491,335Te and requiring an estimated 579 vessel days for removal (note this considers actual removal operations, not preparatory work). Figure 28 demonstrates most of these projects are concentrated in the CNS and SNS regions, which account for 94% of all projects. There are no topsides to be removed in the WoS region. The graph shows that demand for topside removals is likely to peak between 219 and 22. Projects associated with activity dates prior to 217 are caused by a current backload of unexecuted work relating to facilities with CoP dates prior to 217. Figure 28 UKCS topside removal potential demand days by region ( ) Potential Topside Demand Days, by Region CNS IS (including EIS) NNS SNS On the supply side, validated survey data was received from 57% of companies contacted with vessels potentially suitable to undertake topsides removal. Fourteen Heavy Lift Vessels (HLVs) were identified as currently available to perform decommissioning work. To assess current capacity to meet future demand, the survey results were used to calculate the maximum number of potential available days for each HLV per region ( available vessel days see Appendix for calculation). The results are shown in Figure 29 together with the number of available HLVs per region. 24 Decommissioning Supply Chain Capacity Report

25 Figure 29 Number of available Heavy Lift Vessels by region Types Total Count Qty that can operate in CNS Qty that can operate in IS (including EIS) Qty that can operate in NNS Qty that can operate in SNS HLV Number of Days Available by Region This snapshot of current availability was compared against potential demand, shown in Figure 3. Figure 3 UKCS topsides removal demand vs supply ( ) Potential Total Max Supply Vs Demand 1,2 1, ,81 1, ,142 Potential Total Demand Potential Maximum Supply ( ) 1,142 STUDY FINDINGS HLV Based on the total 579 estimated demand days, the total available capacity was almost double, revealing significant available excess supply. Any backlog from pre-217 activities is not expected to have a significant impact. Analysis at the regional level revealed similar results. Summary For topside removal activities on the UKCS utilising HLV, analysis reveals there is presently excess capacity to meet decommissioning demand. HLVs are however highly mobile, therefore future capacity will be determined by the level of development and decommissioning projects both on the UKCS and globally, as well as activities in offshore renewables projects. Key observations 115 projects were identified with topside removal requirements based on CoP up to 223. The cumulative removal total was 491,335Te requiring an estimated 579 days for removal (not including time for preparatory work). Current removal capacity is almost double decommissioning demand and the pre-217 backlog of activity is not expected to have a significant impact. Future capacity will be subject to level of development and decommissioning projects on UKCS and globally, as well as activities in other sectors such as offshore wind farm construction. 225

26 2.6 Substructure removal SUPPLY AND DEMAND ANALYSIS To assess demand for substructure removal, the potential demand days for each year was estimated based on potential project CoP dates up to 223. The assumptions made were that substructure removal activity would take place three years after CoP, except in the SNS where this was assumed to be one year after CoP. The duration of substructure removal activities for each region was then estimated based on vessels days per tonnage range shown in Figure 31. Figure 31 Substructure removal vessel days (per tonnage range) by region Substructure Tonnage 1,6 1,61-4, 4,1-8, 8,1-16, >16, CNS NNS IS (including EIS) SNS In total, 19 projects were identified with substructure removal requirements between 214 and 226, comprising a total tonnage of 294,74Te and requiring an estimated 1,15 vessel days for removal. Figure 32 demonstrates most of these projects are concentrated in the CNS and SNS regions, which account for 94% of substructures to be removed. The graph shows that demand for substructure removal is likely to peak between 218 and 221. The analysis revealed that 74% of substructures for removal weigh less than or equal to 1,6Te and 5% are below 1,Te, particularly those in the SNS. Of those remaining, 15 weigh more than 8,Te and 4 are heavier than 16,Te. Figure 32 UKCS substructure removal potential demand days by region ( ) CNS IS (including EIS) NNS SNS On the supply side, substructures are generally removed by Heavy Lift Vessel (HLV) with support from other vessels/ barges. The survey data identified 15 HLVs with current availability for substructure removal. This was based on a response rate of 57% (51 of 9 companies contacted). These figures will therefore not represent total available capacity. The regions in which HLVs could operate was assessed in accordance with water depth. The breakdown of available HLVs based on these criteria is shown in Figure 33. It was recognised that other potential operational constraints would exist such as substructure configuration, but additional factors were not considered for this study. 26 Decommissioning Supply Chain Capacity Report

27 Figure 33 Number of available Heavy Lift Vessels (Te) Types Total Count Up to 1,6 1,61-4, 4, - 8, >16, HLV To assess current capacity to meet future demand, the survey results were used to calculate the maximum number of potential available days for HLVs in each region. The analysis was segmented into three groups: substructures up to 1,6Te, substructures between 1,6Te and 4,Te, and substructures above 4,Te. This snapshot of current availability was compared against potential demand. The results are shown in Figures 34 to 36. The graphs show there is currently far more capacity overall than is required to meet decommissioning demand for substructures less than 1,6Te and up to 4,Te. Moreover, there is no significant backlog of pre-217 activities which might affect this capacity. However, there is potential for a bottleneck of availability to handle the larger structures, given that some of the limited number of suitable HLVs may be employed in other sectors. Figure 34 UKCS substructure removal demand vs supply (up to 1,6Te) STUDY FINDINGS 6 Potential Demand (up to 1,6Te) Potential Maximum Supply ( ) Maximum Supply CNS SNS In Figure 34 projects are predominantly in the SNS region with activity forecast to peak in 218 and continue until 224. Potential supply appears to be more than sufficient for the projected workload. Figure 35 UKCS substructure removal demand vs supply (1,6Te - 4,Te) Potential Demand (1,6-4,Te) Potential Maximum Supply ( ) CNS SNS Maximum Supply 227

28 Figure 36 UKCS substructure removal demand vs supply (over 4,Te) 5 45 Potential Demand (over 4,Te) Potential Maximum Supply ( ) STUDY FINDINGS Maximum Supply CNS SNS NNS In Figure 36, projects are predominantly in the CNS region with activity forecast to peak in 22 and continue until 226. Potential supply appears to be sufficient for the projected workload if demand can be smoothed over several years. Sufficient capacity will also be sensitive to potential utilisation in other sectors, regions and projects with smaller lifts. Summary Overall, there appears to be adequate capacity for substructure removal activities on the UKCS at present. However, several relevant companies did not respond to the supply survey, suggesting vessel availability may in fact be significantly higher. Key observations 19 projects were identified with substructure removal requirements based on CoP up to 223. Total substructure tonnage for removal was 294,74Te, requiring an estimated 1,15 vessel days. Demand for substructure removals is likely to peak between 218 and 221 Current capacity exceeds demand for removal of substructures weighing less than 4,Te Current capacity for substructures over 4,Te appears sufficient to meet current demand 28 Decommissioning Supply Chain Capacity Report

29 2.7 Onshore remediation, dismantling and recycling The onshore element of decommissioning did not compare supply and demand data. This was due to the data for each having different criteria that could not be overlaid. The two elements are therefore presented separately. Demand To assess demand for onshore decommissioning activities, the potential demand days for each year was estimated based on potential CoP dates up to 223. The assumptions made were that onshore activity would take place four years after CoP, except for in the SNS where this was assumed to be one year after CoP. The duration of onshore decommissioning was also estimated based on the type of infrastructure and tonnage using the scale shown in Figure 37. Figure 37 Onshore decommissioning duration by infrastructure type and weight Activity Te Ranges Days Subsea Infrastructures 2, 14 Substructures 1, - 1,5 28 Topsides 2, - 3, 28 The results are shown in Figure 38. In total, 81,66Te of UKCS infrastructure is estimated to require a total of 15,241 days of onshore decommissioning. As much as two-thirds (534,Te) is concentrated in assets to be recovered from the CNS. The graph shows activity is likely to peak in 221 and 222. SUPPLY AND DEMAND ANALYSIS Figure 38 UKCS onshore decommissioning potential demand days by region ( ) 4, 3,5 3, 2,5 2, 1,5 1, CNS IS (including EIS) NNS SNS WoS 2 29

30 Supply Ports and onshore yards were surveyed to determine the number of facilities, with relevant permits/certifications, able to process offshore infrastructure. From the 85 companies contacted, 4 responded. STUDY FINDINGS For the purposes of this survey, a port was defined in terms of having a quayside including berth, lay-down area and any adjacent working area. A yard was defined as a piece of uncultivated ground either adjacent to quayside or standalone out with port grounds. It is understood that a potential bottleneck could arise if ports and yards lack dismantling contractors with the necessary permits / licenses to undertake the work onshore, such as Pollution Prevention and Control permits (PPCs), Radioactive Substances Authorisations (RSAs), Waste Management Licences (WMLs) and Controlled Activities Regulations Licenses (CARs). Respondents were asked to indicate the status of their permits / licenses, results of which show that a range of sites across the UK are available to perform decommissioning work. Scotland has 33 sites with a total of 69 permits, East England has 3 sites with 7 permits, North East England has 13 sites with 31 permits, and Northern Ireland has 5 sites with 15 permits. Note: 19% of sites surveyed did not specify whether they have permits to operate. The survey also revealed that most sites (63% of quaysides and 61% of yards) have laydown areas less than 25,sqm. These sites may therefore be more suited to smaller structures and not large complete topsides, unless removed in modules / or piece small activity. The geographic distribution of sites with sufficient available laydown area to accept large structures is shown in Figure 39. Only 12 sites provided information on the bunded area available for contaminated materials - all located on the east coast. It was therefore not possible to determine west coast capacity which may be preferable for decommissioning assets removed from the IS (including the EIS). 3 Decommissioning Supply Chain Capacity Report

31 Figure 39 Regional location of sites with >25,sqm available laydown area sufficient for larger structures Northern Ireland 17,85 283,m 2 Scotland ,m 2 NE England 44 63,m ,m 2 STUDY FINDINGS NW England 1,m ,m 2 63,m 2 2 SE England 2 8,m 2 Summary The onshore element of decommissioning presented supply and demand for onshore activities separately due to different data criteria that could not be overlaid. The size of the quayside/yard, the extent of permits in place, the presence of nearby infrastructure, and the availability of skilled personnel onsite, can all have a major impact on a region s decommissioning capacity. Key observations A total of 81,66Te of infrastructure estimated to be removed from the UKCS, requiring a total of 15,241 days of onshore work. Demand for onshore activities is likely to peak in and heavily concentrated on assets recovered from the CNS and SNS. 63% of quaysides and 61% of yards have laydown areas less than 25,sqm thereby unable to accommodate large platforms. 231

32 3 CONCLUSIONS Overall, in 217/18 there appears to be sufficient, and at times surplus, available capacity of key assets to meet potential UKCS decommissioning demand, but this could rapidly change. CONCLUSIONS The analysis is based on a snapshot of a market in a downturn and an industry undergoing meaningful change. There are many uncertainties surrounding UKCS decommissioning that make projects coming to fruition and therefore assessing future capacity at the industry level a challenge. Potential capacity constraints were identified for platform wells P&A in the Central North Sea in 218 and a potential reliance in the Northern North Sea on Modular Drilling Units. However, Platform-Based Drilling Rigs may be reactivated and would help to mitigate capacity constraints. Excess capacity was found in relation to demand for subsea infrastructure removal both up to and above 4Te. A large surplus in capacity is likely to affect contractor ability to maintain investment and the integrity and operability of their assets. This could result in re-deployment overseas or stacking or even sale for decommissioning. This presents a risk to meeting future decommissioning demand, particularly if activity and capacity requirements increase in exploration and production and other marine sectors. Similarly, topside and substructure removal was found to have excess capacity in Heavy Lift Vessel (HLV) utilisation. These assets are also highly mobile, therefore future capacity will be determined by the level of new development and decommissioning projects both on the UKCS and globally, as well as activities in offshore renewables projects. The onshore element of decommissioning presented supply and demand for onshore activities separately due to different data criteria that could not be overlaid. The size of quaysides and yards, the permits in place, presence of nearby infrastructure, and availability of skilled personnel onsite, can all have a major impact on a region s decommissioning capacity. Oil and gas companies are operating in an environment today that bears little resemblance to that of just a few years ago. The industry is subject to evolving macroeconomic and market conditions and has been (and will continue to be) shaken and disrupted by forces that go far beyond supply and demand. These external forces may have a significant impact on UKCS decommissioning capacity: Oil price fluctuations The industry is currently adapting to lower oil prices. Should the oil price rebound, and efficiency improvements continue, some late-life fields currently not considered economically viable may become so, pushing decommissioning activities further into the future. A high oil price could also prompt investment to develop new fields, which, in turn, could lead to the supply chain diverting its available capacity towards those projects. Regulatory framework The recent introduction of transferable tax credits2 between buyers and sellers of North Sea assets has the potential to extend economic recovery in the North Sea. This could impact current estimated Cessation of Production dates within the demand profile. Increasing competition for the UK supply chain Offshore wind developments are expected to increase over the next 5 years. This market draws on much of the fleet/equipment and workforce identified in this study. Together with potential increases in exploration and production activity, competition for what is essentially the same supply chain capacity could significantly alter the supply demand dynamics analysed in this report. New decommissioning-centric technologies and processes The technologies and processes leveraged today were not necessarily designed or built with decommissioning in mind. New potential will emerge, for example, the ability to shift from reverse installation to single lift removal (enabled by the Pioneering Spirit). This means that processes and critically underpinning technologies, are likely to develop further and become more decommissioning-centric. The duration and cost of decommissioning will thus be further optimised, with the potential to radically alter existing baselines/estimates for decommissioning projects. This report offers a comparison of current capacity and expected demand. However, this will change over time as project schedules change and assets are added to or removed from the supply chain. 2UK Government - An outline of the transferable tax history mechanism for UK oil producers that will apply to deals that complete on or after 1 November /government /publications/anoutline-of-transferrable-tax-history 32 Decommissioning Supply Chain Capacity Report

33 4 RECOMMENDATIONS FOR FUTURE STUDIES To improve future studies, the following observations and recommendations have been made: It is recommended this study be completed on an annual basis to create transparency and capture emerging trends of supply in relation to demand to ensure sufficient capacity is available (or made available) for decommissioning activities. The survey represents a good proportion of companies with key assets currently available for decommissioning activity in the UKCS. The research was undertaken during May to September 217, therefore impacted by the summer holiday period. Future surveys should be performed out with holiday periods and should seek to increase the number of companies participating to ensure solid representation and increasing accuracy of annual supply and demand trends. Many respondents exited the survey at the point at which detailed information regarding their assets/ vessels was being sought. This may have been because data was not readily available. Future studies should seek to simplify response requirements and provide information in advance on data to be collected, to increase both quantity and quality of responses. The assumptions this study was based on should be further validated and/or improved based on industry feedback. Limited data was available on abandonment methods and capacity for platform wells P&A. The use of platform rigs or modular units could not be quantified. Future studies should seek to incorporate this information. It was not possible to analyse supply and demand for onshore activity due to non-availability of matching data. Future studies should seek to collect data that can be better aligned for analysis. RECOMMENDATIONS FOR FUTURE STUDIES 433

34 Project methodology and approach APPENDIX The primary objective of this project was to understand the capacity of the decommissioning supply chain to fulfil UK/UKCS decommissioning demand in the forthcoming years. The analysis to support this central question was performed by breaking it into two parts: the market supply side (that is, potential capacity available in the supply chain/market today to serve UKCS decommissioning demand) and the market demand side (that is, demand for decommissioning services expected in the years to come). The rationale for this approach was that by understanding the current picture of available capacity in the supply chain and comparing it with the future demand for decommissioning services, insights into potential bottlenecks or oversupply could be gained. Market supply data To establish a view of supply, a survey of relevant supply chain companies was undertaken to determine capacity in key activities. The response rate to the survey is shown below. Figure A1 - Number of Companies in UK Decommissioning Supply Chain Survey by Activity Area Number of Companies Activity Area Contacted for the Survey Responded to the Survey Platform Wells Subsea Wells Topsides 9 51 Substructure 9 51 Subsea Infrastructure Yards 85 4 Ports Decommissioning Supply Chain Capacity Report

35 To finalise the scope of the survey and the questionnaire to be used, Accenture facilitated a survey workshop with the Project Work Group (comprising Decom North Sea, SE and the OGA) and 21 industry experts. The workshop participant list was finalised by the PWG with the aim of ensuring that subject matter experts from companies representing specialist areas within decommissioning were involved. Accenture thereafter proposed the target audience for the survey. The PWG reviewed the participant list and identified any additional companies. The survey was targeted at supply chain members owning major assets/vessels which today serve decommissioning projects. Supply chain members owning other services and activities, such as people services, secondary equipment and project management services which supplement the major assets/vessels were not targeted as part of the survey. This was because it was generally understood that these would be available (or made available) on demand and would not necessarily be cause for capacity concern. The survey questionnaire was designed to gather a view of the current major assets/vessels in the market which can service UK/UKCS decommissioning demand. Additionally, the survey established from respondents the potential annual availability of these major assets/vessels (in days) over the course of a typical year. However, it was understood that there would be numerous factors (like maintenance, transit to field, time contracted with non-ukcs demand etc.) which would potentially limit this availability. To account for this, a duration factor was applied to all available capacity data gathered from the survey. This was calculated as shown below: Available vessel days collated via survey responses (A) Total vessel duration days annually (B) = 16 days o 45 days vessel mobilisation/transit sailing annually, plus o 15 days vessel maintenance days annually, plus o 1 days serving non-uk decommissioning projects - greenfield /brownfield annually. Net available vessel days to be compared to potential decommissioning demand (C) A B = C Applying the above, provided the net available vessel days. 35

36 Market demand data Demand data was provided by the Oil & Gas Authority (OGA). The data numbered 165 projects and their associated or potential year of Cessation of Production (CoP) which ranged from The number of platform and/or subsea wells per project and associated tonnage for subsea, topside and jacket infrastructure was also given. APPENDIX Assumptions were then made by the Project Work Group and industry experts on when key activities were likely to be executed. The table below shows the offset determined, which was based on year of actual or potential CoP plus number of years to P&A or removal. Figure A2 - Table Showing Offset in Execution for Key Decommissioning Activities (CoP + X Years) Region Platform well P&A Subsea well P&A Topside Removal Substructure Removal Onshore Disposal (Start) Subsea Infrastructure Removal NNS CNS SNS WoS IS (including EIS) The demand days for each of the six key activity areas were calculated as follows: 1. Platform Wells - P&A for each platform well would be 32 days, and for installations with more than 1 wells, 1 in every 1 would require an additional 1 days. 2. Subsea Wells - P&A for each subsea well was estimated as 32 days, and for fields with more than 1 wells, 1 in every 1 would require an additional 1 days. 3. Subsea Infrastructure Figure A3 shows the number of removal days to be utilised associated with subsea infrastructure, ranging from 15 days for less than 5Te structures to a maximum of 4 days for more than 2,1Te. Figure A3 - Subsea Infrastructure Removal Days by Weight (Te) Subsea Tonnage , 1,1-2, >2,1 Removal Days Decommissioning Supply Chain Capacity Report

37 4. Topside Removal - The duration of topside removal activities for each region was estimated based on durations as shown in Figure A4. Figure A4 - Topside Removal Duration for each Region (Vessel Days per Tonnage Range) Topside Tonnage 1,6 1,61-4, 4,1-8, 8,1-16, >16, CNS, NNS IS (including EIS), SNS Substructure Removal - The duration of substructure removal activities for each region was estimated based on durations as shown in Figure A5. Figure A5 - Substructure Removal Duration for each Region (Vessel Days per Tonnage Range) Substructure Tonnage 1,6 1,61-4, 4,1-8, 8,1-16, >16, CNS NNS IS (including EIS) SNS Onshore remediation, dismantling and recycling - The duration of onshore decommissioning was also estimated based on the type of infrastructure and tonnage using the scale shown in Figure A6. Figure A6 - Onshore decommissioning duration by infrastructure type and weight Activity Te Ranges Days Subsea Infrastructures 2, 14 Substructures 1, - 1,5 28 Topsides 2, - 3, 28 37

38 For further information on this report please contact: Decom North Sea 21 Abercrombie Court, Prospect Road, Arnhall Business Park, Westhill, AB32 6FE T: E: 38 Decommissioning Supply Chain Capacity Report

CONNECTING CAPABILITY WITH OPPORTUNITY. Supply Chain Capacity and Capability

CONNECTING CAPABILITY WITH OPPORTUNITY. Supply Chain Capacity and Capability CONNECTING CAPABILITY WITH OPPORTUNITY Supply Chain Capacity and Capability Potential size of market 2025 based on anticipated CoP dates (NOTE: Assume removal starts within 2 years of CoP) Topside Tonnage

More information

Decommissioning. Offshore Europe Seminar

Decommissioning. Offshore Europe Seminar Decommissioning Offshore Europe Seminar September 6th 2017 Outline 1. Accountabilities - Pauline Innes 2. Regulatory Guidance - Pauline Innes 3. Decommissioning Context - Gunther Newcombe 4. Cost Estimate

More information

Executive Summary and Table of Contents

Executive Summary and Table of Contents UK UPSTREAM OIL & GAS SECTOR REPORT 2012/13 Executive Summary and Table of Contents Focused, cutting edge information on the UK Upstream oil and gas industry. Providing detailed and robust analysis of

More information

DECOMMISSIONING INSIGHT Contents

DECOMMISSIONING INSIGHT Contents DECOMMISSIONING INSIGHT 2017 DECOMMISSIONING INSIGHT 2017 Contents 1. Foreword 5 2. Key Findings 7 3. The North Sea Decommissioning Market 10 3.1 The Regulatory Environment 11 3.2 A Growing Market 12

More information

-PILOT & Industry development -Decommissioning. Audrey Banner Head of Offshore Decommissioning Unit, DECC

-PILOT & Industry development -Decommissioning. Audrey Banner Head of Offshore Decommissioning Unit, DECC -PILOT & Industry development -Decommissioning Audrey Banner Head of Offshore Decommissioning Unit, DECC PILOT Joint Industry/Government Strategic Forum Membership includes; 8 members of the board of Oil

More information

Kinsale Area Gas Fields Decommissioning Project Information Leaflet

Kinsale Area Gas Fields Decommissioning Project Information Leaflet Kinsale Area s Decommissioning Project Information Leaflet About Kinsale Energy PSE Kinsale Energy Limited has been operating a number of gas fields in the Celtic Sea, off the County Cork coast, since

More information

Brae Area Pre Decommissioning MARATHON BRAE. Brae Area Decommissioning Programme. June Revision 1.0

Brae Area Pre Decommissioning MARATHON BRAE. Brae Area Decommissioning Programme. June Revision 1.0 Brae Area Pre Decommissioning MARATHON BRAE Brae Area Decommissioning Programme June 2017 Revision 1.0 Why is Marathon Oil decommissioning? Decommissioning is a natural step in the life cycle of an oil

More information

Review of the UK oilfield services industry. January 2016

Review of the UK oilfield services industry. January 2016 Review of the UK oilfield services industry January 2016 Wells 04 Review of the UK oilfield services industry January 2016 23 Wells Figure 15: UK upstream oil and gas supply chain sub-sectors Supply chain

More information

Perenco UK Ltd. SNS Decommissioning

Perenco UK Ltd. SNS Decommissioning Perenco UK Ltd. SNS Decommissioning EEEGr / Decom North Sea Decommissioning Special Interest Group Event 22 nd November 2012 SNS Decommissioning PUK Assets and Decommissioning Strategy Welland Case Study

More information

Click to edit Master title style

Click to edit Master title style Lessons Learnt: UKCS Oil and Gas Click to edit Master title style Projects 2011-2016 Jan Manoharan Asset Stewardship Lead, NNS/WoS May 2018 Click to edit Master subtitle style OGA 2018 This presentation

More information

Delivering the Well Cost Reduction challenge

Delivering the Well Cost Reduction challenge Delivering the Well Cost Reduction challenge Delivering the well cost reduction challenge Who are Oil & Gas UK? Maximising economic recovery Well cost reduction Problem definition Business case Execution

More information

Decommissioning - The Cost Challenge

Decommissioning - The Cost Challenge OGA 2018 This presentation is for illustrative purposes only. The OGA makes no representations or warranties, express or implied, regarding the quality, completeness or accuracy of the information contained

More information

Taking the Temperature of Scottish oil & gas industry Gerry Love

Taking the Temperature of Scottish oil & gas industry Gerry Love Taking the Temperature of Scottish oil & gas industry Gerry Love Introduction Scotland has long been recognised as a major oil and gas hub a gateway to the North Sea and the Atlantic Ocean. The depth,

More information

Tony Owen, Subsea and Pipelines Decommissioning Delivery Manager AOG February 2017

Tony Owen, Subsea and Pipelines Decommissioning Delivery Manager AOG February 2017 Decommissioning in Practice Tony Owen, Subsea and Pipelines Decommissioning Delivery Manager AOG February 2017 Disclaimer and important notice This presentation contains forward looking statements that

More information

Murchison and Beyond. John Allan Development and Decommissioning Projects Manager CNR International. Late Life and Decommissioning

Murchison and Beyond. John Allan Development and Decommissioning Projects Manager CNR International. Late Life and Decommissioning Murchison and Beyond John Allan Development and Decommissioning Projects Manager CNR International Late Life and Decommissioning Murchison Decommissioning Update John Allan Development and Decommissioning

More information

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015 Well Control Contingency Plan Guidance Note (version 2) 02 December 2015 Prepared by Maritime NZ Contents Introduction... 3 Purpose... 3 Definitions... 4 Contents of a Well Control Contingency Plan (WCCP)...

More information

DNB s oil and offshore conference. Idar Eikrem, CFO

DNB s oil and offshore conference. Idar Eikrem, CFO DNB s oil and offshore conference Idar Eikrem, CFO Well positioned for future market opportunities 1) Leading contractor within proven track record 2) Competitive position strengthened a) Delivering projects

More information

INTERNATIONAL. June 2017 Volume 13. A Buoyant Future. Reducing Cost and Risk in Floating Offshore Wind

INTERNATIONAL. June 2017 Volume 13. A Buoyant Future. Reducing Cost and Risk in Floating Offshore Wind INTERNATIONAL June 2017 Volume 13 No. 4 A Buoyant Future Reducing Cost and Risk in Floating Offshore Wind Reducing Cost and Risk in Floating Offshore Wind By Robert Proskovics and Gavin Smart, A Buoyant

More information

INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE

INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE 4 What we do 6 Why choose us? 7 Service and product capabilities For more than 35 years, we have been providing clients with standalone and

More information

RENEWABLE ENERGY SOLUTIONS. oceaneering.com

RENEWABLE ENERGY SOLUTIONS. oceaneering.com RENEWABLE ENERGY SOLUTIONS oceaneering.com 2 Oceaneering / Renewable Energy Solutions From initial site surveys through decommissioning, our products and services deliver unmatched value designed to lower

More information

MER UK Forum Meeting 30 th August 2017

MER UK Forum Meeting 30 th August 2017 MER UK Forum Meeting 30 th August 2017 List of Attendees See Appendix 1 Opening Remarks Andy Samuel, Chief Executive Oil and Gas Authority Andy Samuel opened the meeting, he thanked everyone for their

More information

ACTEON FLS - DECOMMISSIONING

ACTEON FLS - DECOMMISSIONING ACTEON FLS - DECOMMISSIONING CLIENT VERSION 15 FEBRUARY 2016 INTRODUCTION TO ACTEON FLS ACTEON FLS Subsea services company Acteon has launched a new service. Acteon Field Life Service (FLS) offers a joined-up

More information

i-tech SERVICES DELIVERING INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE

i-tech SERVICES DELIVERING INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE i-tech SERVICES DELIVERING INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE 3 About us 4 What we do 6 Why choose us? 7 Service and product capabilities OUR VALUES Safety Integrity Innovation

More information

Driving Cost Reductions in Offshore Wind THE LEANWIND PROJECT FINAL PUBLICATION

Driving Cost Reductions in Offshore Wind THE LEANWIND PROJECT FINAL PUBLICATION Driving Cost Reductions in Offshore Wind THE LEANWIND PROJECT FINAL PUBLICATION This project has received funding from the European Union s Co-funded by the Intelligent Energy Europe Seventh Programme

More information

Offshore Support Vessels Located in the US Gulf of Mexico in March 2018

Offshore Support Vessels Located in the US Gulf of Mexico in March 2018 Offshore Support Vessels Located in the US Gulf of Mexico in March 18 IMCA March 1, 18 Prepared by IMCA The International Marine Contractors Association (IMCA) is the international trade association representing

More information

Offshore Renewables Institute

Offshore Renewables Institute Offshore Renewables Institute Introducing the Offshore Renewables Institute (ORI) About Us We bring together experts and expertise from across a broad university partnership: the University of Dundee;

More information

Marine Well Containment Company Outer Continental Shelf Summer Seminar

Marine Well Containment Company Outer Continental Shelf Summer Seminar Marine Well Containment Company Outer Continental Shelf Summer Seminar June 4, 2015 INTRODUCTION 2 Why We re Here In order to receive a permit to drill in the U.S. Gulf of Mexico, regulations require operators

More information

Driving down the costs of decommissioning through technology. Malcolm Banks & Susi Wiseman Offshore Decommissioning Conference, November 2017

Driving down the costs of decommissioning through technology. Malcolm Banks & Susi Wiseman Offshore Decommissioning Conference, November 2017 Driving down the costs of decommissioning through technology Malcolm Banks & Susi Wiseman Offshore Decommissioning Conference, November 2017 Creating value Unlock the potential of the UK North Sea Anchor

More information

Emerging Subsea Networks

Emerging Subsea Networks FIBRE-TO-PLATFORM CONNECTIVITY, WORKING IN THE 500m ZONE Andrew Lloyd (Global Marine Systems Limited) Email: andrew.lloyd@globalmarinesystems.com Global Marine Systems Ltd, New Saxon House, 1 Winsford

More information

HELIX ENERGY SOLUTIONS

HELIX ENERGY SOLUTIONS HELIX ENERGY SOLUTIONS OFFSHORE CAPABILITIES www.helixesg.com About Us WELL OPERATIONS SUBSEA WELL INTERVENTION PRODUCTION FACILITIES The purpose-built vessels of our Well Operations business units serve

More information

BRAZIL ENERGY AND POWER CONFERENCE. Americo Oliveira McDermott Brazil General Manager September 20, 2015

BRAZIL ENERGY AND POWER CONFERENCE. Americo Oliveira McDermott Brazil General Manager September 20, 2015 BRAZIL ENERGY AND POWER CONFERENCE Americo Oliveira McDermott Brazil General Manager September 20, 2015 Forward-Looking Statement In accordance with the Safe Harbor provisions of the Private Securities

More information

Analysis of UKCS Operating Costs in 2016

Analysis of UKCS Operating Costs in 2016 Analysis of UKCS Operating Costs in 216 December 217 Contents Executive summary 3 1. Introduction 4 2. UKCS unit operating costs 5 3. Total OPEX performance 13 4. UKCS offshore field OPEX 14 5. Benchmarking

More information

National Subsea Research Initiative

National Subsea Research Initiative National Subsea Research Initiative Subsea Storage Workshop - Aberdeen NSRI the focal point for Research and Development for the UK subsea industry Peter Blake; NSRI Chairman 2016 Agenda AM Scene setting:

More information

Offshore Decommissioning Conference Fairmont Hotel, St Andrews 8 th October 2014

Offshore Decommissioning Conference Fairmont Hotel, St Andrews 8 th October 2014 Offshore Decommissioning Conference Fairmont Hotel, St Andrews 8 th October 2014 Delivering the Future Together Delivering The Future Together: Nigel Jenkins CEO Decom North Sea Nigel Jenkins, Chief Executive

More information

Decommissioning: The next wave of opportunity in Australian oil and gas

Decommissioning: The next wave of opportunity in Australian oil and gas Decommissioning: The next wave of opportunity in Australian oil and gas There is a tide in the affairs of men. Which, taken at the flood, leads on to fortune; Omitted, all the voyage of their life Is

More information

Morgan Stanley Houston Energy Summit

Morgan Stanley Houston Energy Summit Morgan Stanley Houston Energy Summit February 25, 2014 Forward-Looking Statements This presentation contains forward-looking statements that involve risks, uncertainties and assumptions that could cause

More information

SPE A Systematic Approach to Well Integrity Management Alex Annandale, Marathon Oil UK; Simon Copping, Expro

SPE A Systematic Approach to Well Integrity Management Alex Annandale, Marathon Oil UK; Simon Copping, Expro SPE 123201 A Systematic Approach to Well Integrity Management Alex Annandale, Marathon Oil UK; Simon Copping, Expro Copyright 2009, Society of Petroleum Engineers This paper was prepared for presentation

More information

Tidal Energy. Transmission & Distribution Network. Wind Energy. Offshore Substation. Onshore Substation. Tidal Stream Energy.

Tidal Energy. Transmission & Distribution Network. Wind Energy. Offshore Substation. Onshore Substation. Tidal Stream Energy. Offshore Renewables Tidal Energy Transmission & Distribution Network Offshore Substation Wind Energy Onshore Substation Tidal Stream Energy Consumer Atkins in Offshore Renewables The offshore wind journey

More information

Re-use & Decommissioning in The Netherlands: A Joint Effort

Re-use & Decommissioning in The Netherlands: A Joint Effort EUOAG Meeting Re-use & Decommissioning in The Netherlands: A Joint Effort 20 September 2017 Content Introduction EBN & NOGEPA Netherlands re-use & decommissioning landscape Netherlands Masterplan for Decommissioning

More information

Subsea Engineering: Our Action Plan

Subsea Engineering: Our Action Plan Subsea Engineering: Our Action Plan Subsea Engineering Action Plan 3 FOREWORD Subsea technology and engineering know-how, honed in the North Sea, in the early eighties are now used around the world in

More information

ATP Oil & Gas Corporation. Advanced Asset Acquisition and Divestiture in Oil & Gas. April 26-27, Gerald W. Schlief, Senior Vice President

ATP Oil & Gas Corporation. Advanced Asset Acquisition and Divestiture in Oil & Gas. April 26-27, Gerald W. Schlief, Senior Vice President ATP Oil & Gas Corporation Advanced Asset Acquisition and Divestiture in Oil & Gas April 26-27, 2006 Gerald W. Schlief, Senior Vice President Forward Looking Statement Certain statements included in this

More information

MAERSK SUPPLY SERVICE. Actively taking part in solving the energy challenges of tomorrow

MAERSK SUPPLY SERVICE. Actively taking part in solving the energy challenges of tomorrow MAERSK SUPPLY SERVICE Actively taking part in solving the energy challenges of tomorrow Utilising our marine capabilities, Expanding to new industries At Maersk Supply Service, we use our marine expertise

More information

Strategic performance in the toughest environments

Strategic performance in the toughest environments Strategic performance in the toughest environments April 2016 Floating Structures a heerema company The challenges of floating structures The unique environment of deep-water offshore developments often

More information

NCS Prospects Conference

NCS Prospects Conference NCS Prospects Conference OGA Strategy & Plans Gunther Newcombe Director Operations November 2016 OGA OGA became a GOVCO on 1 st October 2016 Progressive regulation Role of the OGA OGA Approach MER UK Strategy

More information

Petroleum Safety Levy Methodology. Decision Paper

Petroleum Safety Levy Methodology. Decision Paper Petroleum Safety Levy Methodology Decision Paper DOCUMENT TYPE: REFERENCE: Decision Paper CER/14/429 DATE PUBLISHED: 7 th August 2014 VERSION 3.0 The Commission for Energy Regulation, The Exchange, Belgard

More information

"North Sea Decommissioning : Market Forecast"

North Sea Decommissioning : Market Forecast "North Sea Decommissioning -: Market Forecast" Douglas-Westwood Limited 19 th April Ben Wilby, Analyst bw@douglaswestwood.com 1 1 Oil Price Average Spot Price (USD/bbl) 120 100 80 60 40 Spread Mean 20

More information

BRENT E-NEWS SHELL BRENT FIELD DECOMMISSIONING PROJECT

BRENT E-NEWS SHELL BRENT FIELD DECOMMISSIONING PROJECT BRENT E-NEWS SHELL BRENT FIELD DECOMMISSIONING PROJECT ISSUE #19 APRIL 2018 IN THIS ISSUE: A WORD FROM DUNCAN A welcome from the Brent Asset Manager A WORD FROM ALISTAIR An update from the Project Director

More information

ENGINEERING SERVICES CONSULTANCY

ENGINEERING SERVICES CONSULTANCY ENGINEERING SERVICES CONSULTANCY Managing complexity, unlocking value Petrofac Engineering & Production Services 02 03 Discover the difference Consultancy services Petrofac is an international service

More information

Nigel Lees Regional Director Strategy and Growth Wood Group PSN

Nigel Lees Regional Director Strategy and Growth Wood Group PSN THE PRACTICE OF ENTREPRENEURSHIP Nigel Lees Regional Director Strategy and Growth Wood Group PSN INTRODUCTION The process of decommissioning old and uneconomic assets has been described by many as a huge

More information

National Grid s commitments when undertaking works in the UK. Our stakeholder, community and amenity policy

National Grid s commitments when undertaking works in the UK. Our stakeholder, community and amenity policy National Grid s commitments when undertaking works in the UK Our stakeholder, community and amenity policy Introduction This document describes the ten commitments we have made to the way we carry out

More information

ABERDEEN HARBOUR EXPANSION PROJECT November Volume 2: Environmental Statement

ABERDEEN HARBOUR EXPANSION PROJECT November Volume 2: Environmental Statement ABERDEEN HARBOUR EXPANSION PROJECT November 2015 Volume 2: Environmental Statement Chapter 23: OTHER USERS 23. OTHER USERS 23.1 Introduction This chapter assesses the potential effects on other users

More information

Delivering Competitive Wells

Delivering Competitive Wells Delivering Competitive Wells Katy Heidenreich, Operations Optimisation Manager, Oil & Gas UK Mariesha Jaffray, Continuous Improvement Manager, Oil & Gas UK The Mining Institute for Scotland, 14 Feb 2018

More information

Husky Energy - Development Plan Amendment Application. White Rose Extension Project. Public Review. Noia s Submission

Husky Energy - Development Plan Amendment Application. White Rose Extension Project. Public Review. Noia s Submission Husky Energy - Development Plan Amendment Application White Rose Extension Project Public Review Noia s Submission September 10, 2014 Table of Contents FOREWORD WREP PUBLIC REVIEW... 1. Background... 1.1

More information

Decommissioning of Offshore Production Systems Eduardo Hebert Zacaron Gomes

Decommissioning of Offshore Production Systems Eduardo Hebert Zacaron Gomes Decommissioning of Offshore Production Systems Eduardo Hebert Zacaron Gomes Rio de Janeiro September 22, 2017 Agenda: Context National Outlook Decommissioning at Petrobras Main Areas Main Activities Challenges

More information

PROSPEX. UKCS Exploration & Appraisal Status. Gunther Newcombe Director Operations. December 2016

PROSPEX. UKCS Exploration & Appraisal Status. Gunther Newcombe Director Operations. December 2016 PROSPEX UKCS Exploration & Appraisal Status Gunther Newcombe Director Operations December 2016 OGA OGA became a GOVCO on 1 st October 2016 with additional powers and sanctions Progressive Regulation Role

More information

Transition PPT Template. J.P. Morgan. June 2015 V 3.0. Energy Equity Conference June 27, 2017

Transition PPT Template. J.P. Morgan. June 2015 V 3.0. Energy Equity Conference June 27, 2017 Transition PPT Template J.P. Morgan June 2015 V 3.0 Energy Equity Conference 2017 June 27, 2017 Forward-Looking Statements This presentation contains forward-looking statements, including, in particular,

More information

Investor Presentation

Investor Presentation Connecting What s Needed with What s Next Investor Presentation September 2017 Forward-Looking Statements Statements we make in this presentation that express a belief, expectation, or intention are forward

More information

ISO INTERNATIONAL STANDARD. Petroleum and natural gas industries Offshore production installations Basic surface process safety systems

ISO INTERNATIONAL STANDARD. Petroleum and natural gas industries Offshore production installations Basic surface process safety systems INTERNATIONAL STANDARD ISO 10418 Second edition 2003-10-01 Petroleum and natural gas industries Offshore production installations Basic surface process safety systems Industries du pétrole et du gaz naturel

More information

World Offshore Wind Market Forecast Prospects, Technologies, World Markets

World Offshore Wind Market Forecast Prospects, Technologies, World Markets 2016 World Offshore Wind Market Forecast 2016-2025 Prospects, Technologies, World Markets Contents Table of Contents 1 Summary and Conclusions...7 Summary... 8 Conclusions... 9 2 Drivers and Indicators...

More information

Transmission Innovation Strategy

Transmission Innovation Strategy Transmission Innovation Strategy Contents 1 Value-Driven Innovation 2 Our Network Vision 3 Our Stakeholders 4 Principal Business Drivers 5 Delivering Innovation Our interpretation of Innovation: We see

More information

NURTURING OFFSHORE WIND MARKETS GOOD PRACTICES FOR INTERNATIONAL STANDARDISATION

NURTURING OFFSHORE WIND MARKETS GOOD PRACTICES FOR INTERNATIONAL STANDARDISATION NURTURING OFFSHORE WIND MARKETS GOOD PRACTICES FOR INTERNATIONAL STANDARDISATION Summary for POLICY MAKERS SUMMARY FOR POLICY MAKERS The fast pace of offshore wind development has resulted in remarkable

More information

Analyst Day Real change starts here. Doug Pferdehirt, Chief Executive Officer

Analyst Day Real change starts here. Doug Pferdehirt, Chief Executive Officer 2017 Real change starts here Doug Pferdehirt, Chief Executive Officer Disclaimer Forward-looking statements We would like to caution you with respect to any forward-looking statements made in this commentary

More information

Q Q Q Q Q % % 46.8% 61.0% 35.6% 57.5% 52.1% 60.5% 44.6% 63.3% 15,267 15,081 15,260 15,265 16,299

Q Q Q Q Q % % 46.8% 61.0% 35.6% 57.5% 52.1% 60.5% 44.6% 63.3% 15,267 15,081 15,260 15,265 16,299 Press release Paris, May 4, 2017 BOURBON 1 st quarter 2017 financial information Adjusted revenues amounted to 225.5 million ( 204.9 million in consolidated revenues) in the 1 st quarter of 2017, down

More information

Transmission Innovation Strategy

Transmission Innovation Strategy 1 Transmission Innovation Strategy 2 Contents 1. Value-Driven Innovation 2 2. Our Network Vision 3 3. Our Stakeholders 4 4. Principal Business Drivers 4 5. Delivering Innovation 5 Our interpretation of

More information

Repsol E&P T&T Ltd is one of the upstream Repsol YPF Group of companies currently operating in more than 20 countries around the world.

Repsol E&P T&T Ltd is one of the upstream Repsol YPF Group of companies currently operating in more than 20 countries around the world. 1 INTRODUCTION 1.1 Background Repsol E&P T&T Ltd is one of the upstream Repsol YPF Group of companies currently operating in more than 20 countries around the world. Repsol E&P has become one of the major

More information

WHITE ROSE OILFIELD COMPREHENSIVE STUDY REPORT SUBMITTED BY:

WHITE ROSE OILFIELD COMPREHENSIVE STUDY REPORT SUBMITTED BY: WHITE ROSE OILFIELD COMPREHENSIVE STUDY REPORT SUBMITTED BY: HUSKY OIL OPERATIONS LIMITED (AS OPERATOR) SUITE 801, SCOTIA CENTRE 235 WATER STREET ST. JOHN S, NF, A1C 1B6 TEL: (709) 724-3900 FAX: (709)

More information

Sponsored by. Created and produced by

Sponsored by. Created and produced by Sponsored by Diamond Sponsor Supported by Created and produced by CREATING NEW HORIZONS IN OFFSHORE ENERGY BOSKALIS OFFSHORE ENERGY- FLEET DEVELOPMENTS OFFSHORE ENERGY 2018- RAI AMSTERDAM JACK SPAAN 23

More information

...make offshore work OFFSHORE PROJECTS

...make offshore work OFFSHORE PROJECTS ...make offshore work OFFSHORE PROJECTS WHO WE ARE SubC Partner is a project oriented offshore company We provide services across a wide value chain, starting from problem assessment, to solution development

More information

Managing Offshore Field Development & Marine Asset October 2017 Dubai, United Arab Emirates

Managing Offshore Field Development & Marine Asset October 2017 Dubai, United Arab Emirates Managing Offshore Field Development & Marine Asset 22-26 October 2017 Dubai, United Arab Emirates This course is Designed, Developed, and will be Delivered under ISO Quality Standards Managing Offshore

More information

Subsea UK Neil Gordon Chief Executive Officer Championing the UK Subsea Sector Across the World

Subsea UK Neil Gordon Chief Executive Officer Championing the UK Subsea Sector Across the World Subsea UK Neil Gordon Chief Executive Officer Championing the UK Subsea Sector Across the World 1 Overview About Subsea UK Facts and figures UK industry evolution Centre of Excellence Technology and Innovation

More information

OPRED. Wendy Kennedy EUOAG. Vision and Objectives

OPRED. Wendy Kennedy EUOAG. Vision and Objectives OPRED Wendy Kennedy Vision and Objectives EUOAG 22 Offshore Petroleum Regulator for Environment & Decommissioning Chief Executive - Wendy Kennedy Based in Aberdeen OPRED s aims are to regulate the offshore

More information

Offshore Engineering. Design, Fabrication, Installation, Hook-up and Commissioning September 2017 Dubai, United Arab Emirates

Offshore Engineering. Design, Fabrication, Installation, Hook-up and Commissioning September 2017 Dubai, United Arab Emirates Offshore Engineering Design, Fabrication, Installation, Hook-up and Commissioning 17-NOV-16 This course is Designed, Developed, and will be Delivered under ISO Quality Standards 24-28 September 2017 Dubai,

More information

Abstract. Mission. Exceptions

Abstract. Mission. Exceptions Marine transportation manual - a year 2000 joint industry project J.M.R. Lloyd Noble Denton Europe Ltd, Noble House, 131 Aldersgate Street, London EC1A 4EB, UK Abstract Mission To develop and publish a

More information

A A Well Engineer s s Perspective

A A Well Engineer s s Perspective Mining Institute of Scotland IOM 3 Petroleum and Drilling Engineering Division Material Challenges for North Sea Oil & Gas Production A A Well Engineer s s Perspective ITF Advanced Materials Workshop Steve

More information

For personal use only

For personal use only 3D Oil Limited Level 5, 164 Flinders Lane Melbourne VIC 3000 Tel: +61 3 9650 9866 Fax: +61 3 9639 1960 www.3doil.com.au ASX Release 19 July 2013 Milestone Purchase of Rig for the West Seahorse Oil Field

More information

Esso offshore projects

Esso offshore projects Esso offshore projects Introduction Esso Australia, a subsidiary of ExxonMobil Australia, is undertaking a program of work across some of its offshore assets, including those owned jointly by the Gippsland

More information

Founding Manifesto Friends of Floating Offshore Wind 18 May 2016

Founding Manifesto Friends of Floating Offshore Wind 18 May 2016 Founding Manifesto Friends of Floating Offshore Wind 18 May 2016 Members: Pilot Offshore Renewables Hexicon RES Offshore IDEOL Floating Power Plant Glosten PelaStar Principle Power Inc. Atkins ACS Cobra

More information

Ecosse Subsea Systems. Subsea Springboard 2017 David Hunt

Ecosse Subsea Systems. Subsea Springboard 2017 David Hunt Ecosse Subsea Systems Subsea Springboard 2017 David Hunt Contents Presenter Introduction ESS Company Overview SCAR Seabed System SCARJet Project Management Engineering and Design Personnel Questions ESS:

More information

Orkney Electricity Network Reinforcement Stakeholder Consultation Response. August 2014

Orkney Electricity Network Reinforcement Stakeholder Consultation Response. August 2014 Orkney Electricity Network Reinforcement August 2014 Introduction In February 2014 Scottish and Southern Energy Power Distribution 1 (SSEPD) undertook a stakeholder consultation Connecting Orkney: Electricity

More information

A Rebirth in the North Sea or simply a False Dawn

A Rebirth in the North Sea or simply a False Dawn The North Sea has seen record levels of investment in 2012 and 2013 Drilling activity is forecast to increase in the coming years Utilization in the Region is the highest it has ever been and there are

More information

ICT strategy and solutions for upstream oil and gas. Supporting exploration and production globally

ICT strategy and solutions for upstream oil and gas. Supporting exploration and production globally ICT strategy and solutions for upstream oil and gas Supporting exploration and production globally We work extensively with the upstream oil and gas industry to shape IT and communications strategy and

More information

Noble Corporation. Don Jacobsen Senior Vice President Industry & Government Relations Marine/Offshore Industry Conference 29 March 2012

Noble Corporation. Don Jacobsen Senior Vice President Industry & Government Relations Marine/Offshore Industry Conference 29 March 2012 Noble Corporation Don Jacobsen Senior Vice President Industry & Government Relations 20 Marine/Offshore Industry Conference 29 March 202 Forward Looking Statement These presentations contain forward-looking

More information

THE MARINE PARTNER OF CHOICE

THE MARINE PARTNER OF CHOICE THE MARINE PARTNER OF CHOICE The expert marine team MARINE PLANT HIRE MARINE CONSTRUCTION RENEWABLES & ENERGY MARINE CONSULTANCY MARINE RECRUITMENT Red7Marine is the Marine Partner of Choice within the

More information

Subsea 7 Norway. Monica Th. Bjørkmann Sales and Marketing Director

Subsea 7 Norway. Monica Th. Bjørkmann Sales and Marketing Director Subsea 7 Norway 28.06.2012 Monica Th. Bjørkmann Sales and Marketing Director Agenda Subsea 7 Norway What We Do Our Assets Market Going Forward Closing 27-Jun- 12 Page 2 Our new beginning A combination

More information

Stewardship. Expectations. SE-06 Production Optimisation Implementation Guide

Stewardship. Expectations. SE-06 Production Optimisation Implementation Guide Stewardship Expectations SE-06 Production Optimisation Implementation Guide June 2017 2 SE-06 Production Optimisation Implementation Guide 1. Objectives The objectives of this Stewardship Expectation are

More information

The offshore wind market deployment: forecasts for 2020, 2030 and impacts on the European supply chain development

The offshore wind market deployment: forecasts for 2020, 2030 and impacts on the European supply chain development Available online at www.sciencedirect.com Energy Procedia 24 (2012 ) 2 10 DeepWind, 19-20 January 2012, Trondheim, Norway The offshore wind market deployment: forecasts for 2020, 2030 and impacts on the

More information

Access to Infrastructure: A new approach for the North Sea

Access to Infrastructure: A new approach for the North Sea Access to Infrastructure: A new approach for the North Sea 10 th of May 2012 James Paton www.assetdev.com Introduction In the UKCS lack of access to suitable infrastructure is increasingly becoming an

More information

Intervention/Decommissioning

Intervention/Decommissioning Intervention/Decommissioning By Nicholas Samford Lloyds Register Intervention/Decommissioning SME Working together for a safer world Planning Decommissioning Operations Planning Decommissioning and P&A

More information

The New Energy at Global Industries

The New Energy at Global Industries 34 th Annual Marine/Offshore Industry Outlook Conference Offshore Construction Jim Osborn Chief Marketing Officer Global Industries 24 March 2011 1 The New Energy at Global Industries 2500 people 11 offices

More information

UK offshore wind industry progress to cost reduction

UK offshore wind industry progress to cost reduction UK offshore wind industry progress to cost reduction Mike Newman, Innovation manager 30 September 2015 Agenda 1. Introduction to ORE Catapult 2. Cost Reduction Monitoring Framework (CRMF) 2014 3. CRMF

More information

Global Energy Group s multi-client contract showcases UK-based engineering talent to achieve first oil for Catcher

Global Energy Group s multi-client contract showcases UK-based engineering talent to achieve first oil for Catcher News release 12 January 2018 Global Energy Group s multi-client contract showcases UK-based engineering talent to achieve first oil for Catcher Global Energy Group (GEG), a Scotland-headquartered energy

More information

Managing Ageing Infrastructure

Managing Ageing Infrastructure Managing Ageing Infrastructure Leo van der Stap, Louisiana,1967 (Safety standards have moved on since...) Andre van der Stap, Engineering Manager, Civil Marine Offshore Structures, Shell Global Solutions

More information

Engineering. Drafting & Design. Regulatory Interface. Project & Construction Management. Marine Operations Services

Engineering. Drafting & Design. Regulatory Interface. Project & Construction Management. Marine Operations Services Engineering Drafting & Design Regulatory Interface Project & Construction Management Marine Operations Services Corporate Overview EXMAR Offshore is dedicated to the ownership and leasing of offshore assets

More information

Energy Transition Partner. Created and produced by

Energy Transition Partner. Created and produced by Energy Transition Partner Diamond Sponsor Supported by Created and produced by Energy Transition Partner Diamond Sponsor Supported by Created and produced by CREATING NEW HORIZONS IN OFFSHORE ENERGY A

More information

QUARTERLY UPDATE. Summary

QUARTERLY UPDATE. Summary QUARTERLY UPDATE Q1 FY14 Summary Production levels consistent with designed plant capacity Current order backlog of US$86 million which will support full production until the beginning of Q4 FY14 Strong

More information

ALWAYS SWITCHED ON TO YOUR SUBSEA CABLES

ALWAYS SWITCHED ON TO YOUR SUBSEA CABLES ALWAYS SWITCHED ON TO YOUR SUBSEA CABLES The critical role performed by submarine cables in enabling power transmission via subsea interconnectors from offshore wind farms is threatened by an increasing

More information

Great Reasons to Build Your Career in North East England. Subsea, Marine, and Offshore

Great Reasons to Build Your Career in North East England. Subsea, Marine, and Offshore Great Reasons to Build Your Career in North East England Subsea, Marine, and Offshore There are many great reasons to build your career in North East England. This presentation, developed through a partnership

More information

UK EXPLORATION WHERE NEXT? OIL & GAS UK BREAKFAST 8 DECEMBER 2015

UK EXPLORATION WHERE NEXT? OIL & GAS UK BREAKFAST 8 DECEMBER 2015 UK EXPLORATION WHERE NEXT? OIL & GAS UK BREAKFAST 8 DECEMBER 2015 Introduction Phil Kirk MD Chrysaor Co-Chair & Industry Lead MER UK Exploration Board Board member Oil & Gas UK Active member OGIA What

More information

Offshore Cable Installation. November 2010 John Davies Global Marine Systems Limited

Offshore Cable Installation. November 2010 John Davies Global Marine Systems Limited Offshore Cable Installation November 2010 John Davies Global Marine Systems Limited Services and Markets - Overview Both directly and through our Partnerships & Joint Ventures, we offer a wide range of

More information

Unique range of activities OFFSHORE ONSHORE. A world leader in project management, engineering and construction for the energy industry

Unique range of activities OFFSHORE ONSHORE. A world leader in project management, engineering and construction for the energy industry 2 3 Unique range of activities A world leader in project management, engineering and construction for the energy industry S U B S E A OFFSHORE Subsea infrastructures, from deep to shore In subsea hydrocarbon

More information